TABLE OF CONTENTS
Page
1.4 Summary of Construction Works
2. Summary of EM&A Programme Requirements
2.2 Environmental Quality Performance (Action/Limit
Levels)
2.3 Environmental Mitigation Measures
3.5 Environmental Site Inspection and Audit
4. Advice
on the Solid and Liquid Waste Management Status
4.1 Summary
of Solid and Liquid Waste Management
5. Implementation Status of Environmental Mitigation
Measures
5.1 Implementation
Status of Environmental Mitigation Measures
6. Summary of Exceedances of the Environmental Quality
Performance Limit
6.1 Summary of Exceedances of the Environmental Quality
Performance Limit
7. Summary of Complaints, Notification
of Summons and Successful Prosecutions
7.1 Summary of Environmental Complaints, Notification of Summons and
Successful Prosecutions
8. REVIEW of THE VALIDITY OF THE EIA Prediction
9. Review of ENVIRONMENTAL IMPLEMENTATION STATUS
11. Comments, recommendations and Conclusions
List of Tables
Table 1.1 Contact Information of Key Personnel
Table 3.1 Summary of Number of Monitoring Events for
1-hr & 24-hr TSP Concentration
Table 3.2 Summary of Number of
Exceedances for 1-hr & 24-hr TSP Monitoring
Table 3.3 Maximum Predicted TSP concentrations under the
“Mitigated” scenario
Table 3.4 Summary of Number of Monitoring Events for Impact Noise
Table 3.5 Summary of Number of Monitoring Exceedances
for Impact
Noise
Table 3.6 Construction Noise Impact at Noise Sensitive Receivers
Table 3.7 Summary of Construction Noise Monitoring Results in the Reporting Period
Table 3.8 Summary of Number of Monitoring Events for Impact
Water Quality
Table 3.9 Summary of Water Quality Exceedances in Mar 17 – Apr
18
Table 3.10 Summary of number of water quality exceedances per monitoring month
Table 3.11 Comparison of depth averaged dissolved oxygen levels (Surface &
Mid-depth, Bottom depth) during baseline and impact monitoring period (mgL-1)
Table 3.12 Ambient and Tolerance Values for Suspended Sediment Concentrations (mgL-1)
in the Vicinity of Sensitive Receivers adopted in the EIA
Table 3.13 Calculated Elevations in Suspended Sediment
Concentrations at Sensitive Receivers (mgL-1) under the 2012 mitigated
scenario from the EIA
Table 3.14 Baseline suspended solids levels and 30% of baseline mean (mgL-1)
Table 3.15 Average suspended solids levels at sensitive receivers
(mgL-1) in November 2014
Table 3.16 Summary
of the STG/ANI Quarterly Values
Table 3.17 Summary of All Dolphin Impact Monitoring Sightings from Year 1 (March 2012 – February 2013) to the Year 6 (Mar 2017 – August 17) of the HKBCF Reclamation Works Project
Table
3.18 Comparison of low, moderate and
high habitat utilisation in NEL and NWL between
advanced and impact monitoring (in %)
Table
3.19 Dolphins Frequently Recorded During Impact Monitoring Surveys
Figures
Figure 1 General
Contract Layout Plan
Figure 2a-2e Impact Air Quality and Noise Monitoring
Stations and Wind Station
Figure 3a-3f Impact Water Quality Monitoring Stations
Figure 4a-4d Impact Dolphin
Monitoring Line Transect Layout Map
Figure 5 Environmental Complaint Handling
Procedure
List of Appendices
Appendix A Contract Organization for
Environmental Works
Appendix B Three Month Rolling Construction Programmes
Appendix C Implementation Schedule of Environmental
Mitigation Measures (EMIS)
Appendix D Summary of Action and Limit Levels
Appendix E Graphical Presentation of Impact Air Quality
Monitoring Results
Appendix F Graphical Presentation of Impact Daytime Construction
Noise Monitoring Results
Appendix G Graphical Presentation of Impact Water Quality
Monitoring Results
Appendix H Impact Dolphin Monitoring Survey Findings and Analysis
Appendix I Summary of Waste Flow Table
As informed by the
Contractor, major activities in the reporting period were:-
Marine-base
-
Additional GI
installation |
-
Backfill cellular
structure |
-
Band drain
installation |
-
Capping Beams
structures |
-
Cellular structure (capping beams, connecting arcs, installation & backfilling) |
-
Cone penetration test; |
-
Conforming sloping
seawalls |
-
Connecting arc cell
installation |
-
Construction of cellular
structure |
-
Construction of
conveyors for public fill |
-
Construction of
temporary jetties for surcharge laying |
-
Construction of
temporary pier at Portion A |
-
Construction of temporary
seawall |
-
Deep Cement Mixing |
-
Earthwork fill |
-
Flat barge of
unloading public fill for surcharge laying |
-
Geotechnical
Instrumentation works |
-
Geotextile laying and
fabrication; |
-
Ground investigation |
-
Installation of silt
screen at sea water intake of HKIA |
-
Installations of
Precast Culverts except sloping outfalls |
-
Instrumentation works |
-
Jet grout columns
works |
-
Laying geo-textile |
-
Laying stone blanket |
-
Maintenance of Silt
curtain |
-
Maintenance of silt
curtain & silt screen at sea water intake of HKIA |
-
Optimizing rubble
mound seawalls |
-
Outfall installation |
-
Portion D Construction
of Access to Portion A |
-
Precast Yard for
seawall blocks & culverts |
-
Precast Yard setup |
-
Public filling |
-
Reinstatement of
seawall |
-
Removal of Temporary
Seawall |
-
Rock filling |
-
Rubble Mound Seawall |
-
Sand blanket laying |
-
Sand blanket trial |
-
Sand filling |
-
Seawall blocks for
temporary construction |
-
Silt curtain deployment
and repairing |
-
Silt curtain
fabrication and deployment; and |
-
Sloping Seawalls |
-
Stone blankets laying. |
-
Stone column
installation and installation trial |
-
Surcharge laying and
removal |
-
Temporary bridge at
Portion D |
-
Temporary Watermain
construction along access at Portion D |
-
Vibro-compaction on
surcharge |
- Maintenance
of silt curtain & silt screen at sea water intake of HKIA (As informed by
the Contractor, the silt
curtain at NE Airport Cooling Water
Intake has been removed on 10 May 2016.) |
Land-base
-
Constructing site
access at Works Area WA2 to Ying Hei Road, Tung
Chung; |
-
Construction of
Permanent Seawall |
-
Construction of
Sloping Outfalls |
-
Construction of
Temporary Marine Access at Works Area WA2 |
-
Deep Cement Mixing |
-
Drainage works at Works
Area WA2 and WA3; |
-
Earthwork fill |
-
Erection of site
office for CHEC(GD) at Works Area WA2 |
-
Geotechnical
Instrumentation Works |
-
Geotextile fabrication
at Works Area WA2 and WA4; and |
-
Green roof
construction at Works Area WA2 |
-
Hoarding erection at
Work Areas Portion D and Works Area WA2 |
-
Installations of
Precast Culverts except sloping outfalls |
-
Installed sand bag at
Works Area WA2 |
-
Jet grout columns
works |
-
Maintenance of
Temporary Marine Access at Works Area WA2 |
-
Maintenance works of
Public Works Regional Laboratory at Works Area WA3 |
-
Maintenance works of
Site Office at Works Area WA2 |
-
Public Works Regional
Laboratory erection and construction at Works Area WA3; |
-
Removal of Temporary
Seawall |
-
Sign
board erection at Works Area WA2 |
-
Silt curtain fabrication
at Works Area WA2 and WA4; |
-
Site office erection
and construction at Works Area WA2; |
-
Stone column
installation barges setup and their maintenance works at Works Area WA4. |
-
Surcharge removal
& laying |
-
Vertical Band Drains |
A summary of monitoring
and audit activities conducted in the reporting period* is listed below:
24-hour Total Suspended Particulates (TSP)
monitoring 1-hour TSP monitoring |
352 sessions 352 sessions |
Noise monitoring |
281 sessions |
Impact water quality monitoring |
846 sessions |
Impact dolphin monitoring |
132 surveys |
Joint Environmental site inspection |
319 sessions |
*monitoring works between September 2017 and April 2018 for the Contract are covered by Contract No. HY/2013/01 Hong Kong-Zhuhai Macao Bridge HKBCF –Passenger Clearance Building.
Breaches
of Action and Limit Levels
for Air Quality
Breaches of Action and Limit Levels for Noise
1 Limit Level
exceedance of impact noise monitoring was recorded in June 2012. No exceedance of
impact noise monitoring was recorded by Contract No. HY/2013/01 and all
exceedances were recorded by this Contract. Investigation into the possible
causes of each exceedance was undertaken and reported in the respective monthly
EM&A reports. Investigation results show that the exceedance was not due to
the Project works. The Contractor was recommended to continue implementing
existing noise mitigation measures. 1 noise complaint was received in October
2012 and therefore 1 Action Level Exceedance of construction noise was recorded
in October 2012. Investigation into the possible causes of such exceedance was
undertaken and reported in the respective monthly EM&A reports, the
investigations results confirmed that the action and limit level exceedance
were not related to Contract. No other exceedance was recorded at all
monitoring stations in the reporting period.
Breaches of Action and Limit Levels for Water Quality
Triggering
of Event and Action Plan
for Impact
Dolphin Monitoring
15 Limit level
exceedances and 6 Action level exceedances were recorded in the reporting
period for impact dolphin monitoring. After investigation, it was concluded
that the HZMB works is one of the contributing factors affecting the dolphins.
It was also concluded the contribution of impacts due to the HZMB works as a
whole (or individual marine contracts) cannot be quantified nor separate from
the other stress factors. Event Action Plan for Impact Dolphin Monitoring was
triggered. For investigation results please refer to Appendix L of the
corresponding quarterly reports.
Impact dolphin
monitoring results obtained between September 2017 and April 2018, at all
transects are reported in the EM&A Report prepared for Contract No.
HY/2013/01.
Implementation
Status and Review of Environmental Mitigation Measures
Most of the
recommended mitigation measures, as included in the EM&A programme, were
implemented properly in the reporting period. The recommended environmental mitigation
measures effectively minimize the potential environmental impacts from the
Contract.
Changes of EM&A
programme such as conditional omission
of air monitoring station (AMS 6) for this Contract; relocation of air quality
monitoring station, relocation of construction noise monitoring station, impact
water quality monitoring stations, alternation of the transect lines of dolphin
monitoring were carried out during the reporting period. For background
proposal date and approval date of each changes of the EM&A programme,
please refer to the corresponding annual EM&A review report of this
contract.
Overall, the
EM&A programme effectively monitored the environmental impacts from the
construction activities and ensure the proper implementation of mitigation
measures. No particular recommendation was advised for the improvement of the
programme. .
Moreover,
regular review and checking on the construction methodologies, working
processes and plants were carried out to ensure the environmental impacts were
kept minimal and recommended environmental mitigation measures were implemented
effectively.
Complaint,
Notification of Summons and Successful Prosecution
Table
1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Engineer’s Representative (ER) (Ove
Arup & Partners Hong Kong Limited) |
Senior Resident Engineer |
Seven Yau |
3698 5850 |
2698 5999 |
IEC / ENPO (Ramboll Hong Kong Limited) |
Independent Environmental Checker |
Ray Yan |
3465 2836 |
3465 2899 |
Environmental Project Office Leader |
Y. H. Hui |
3456
2850 |
3465 2899 |
|
Contractor (China Harbour
Engineering Company Limited) |
Environmental Officer |
Louie Chan |
36932254 |
2578 0413 |
24-hour Hotline |
Alan C.C. Yeung |
9448 0325 |
-- |
|
ET (AECOM
Asia Company Limited) |
ET Leader |
Echo Leong |
3922 9280 |
2317 7609 |
Marine-base
-
Additional GI installation |
-
Backfill cellular structure |
-
Band drain installation |
-
Capping Beams structures |
-
Cellular structure – (capping
beams, connecting arcs, installation & backfilling) |
-
Cone penetration test; |
-
Conforming sloping seawalls |
-
Connecting arc cell installation |
-
Construction of cellular structure |
-
Construction of conveyors for public fill |
-
Construction of temporary jetties for surcharge
laying |
-
Construction of temporary pier at Portion A |
-
Construction of temporary seawall |
-
Deep Cement Mixing |
-
Earthwork fill |
-
Flat barge of unloading public fill for surcharge
laying |
-
Geotechnical Instrumentation works |
-
Geotextile laying and fabrication; |
-
Ground investigation |
-
Installation of silt screen at sea water intake
of HKIA |
-
Installations of Precast Culverts except sloping
outfalls |
-
Instrumentation works |
-
Jet grout columns works |
-
Laying geo-textile |
-
Laying stone blanket |
-
Maintenance of Silt curtain |
-
Maintenance of silt curtain & silt screen at
sea water intake of HKIA |
-
Optimizing rubble mound seawalls |
-
Outfall installation |
-
Portion D Construction of Access to Portion A |
-
Precast Yard for seawall blocks & culverts |
-
Precast Yard setup |
-
Public filling |
-
Reinstatement of seawall |
-
Removal of Temporary Seawall |
-
Rock filling |
-
Rubble Mound Seawall |
-
Sand blanket laying |
-
Sand blanket trial |
-
Sand filling |
-
Seawall blocks for temporary construction |
-
Silt curtain deployment and repairing |
-
Silt curtain fabrication and deployment; and |
-
Sloping Seawalls |
-
Stone blankets laying. |
-
Stone column installation |
-
Stone column installation trial; |
-
Surcharge laying and removal |
-
Temporary bridge at Portion D |
-
Temporary Watermain construction along access at
Portion D |
-
Vibro-compaction on surcharge |
-
Maintenance of silt curtain & silt screen at sea water intake of HKIA (As
informed by the Contractor, the silt curtain at NE Airport Cooling Water Intake has been removed on 10 May 2016.) |
Land-base
-
Constructing site access at Works Area WA2
to Ying Hei Road, Tung Chung; |
-
Construction of Permanent Seawall |
-
Construction of Sloping Outfalls |
-
Construction of Temporary Marine Access at Works
Area WA2 |
-
Deep Cement Mixing |
-
Drainage works at Works Area WA2 and WA3; |
-
Earthwork fill |
-
Erection of site office for CHEC(GD) at Works
Area WA2 |
-
Geotechnical Instrumentation Works |
-
Geotextile fabrication at Works Area WA2 and WA4;
and |
-
Green roof construction at Works Area WA2 |
-
Hoarding erection at Work Areas Portion D and
Works Area WA2 |
-
Installations of Precast Culverts except sloping
outfalls |
-
Installed sandbag at Works Area WA2 |
-
Jet grout columns works |
-
Maintenance of Temporary Marine Access at Works
Area WA2 |
-
Maintenance works of Public Works Regional
Laboratory at Works Area WA3 |
-
Maintenance works of Site Office at Works Area
WA2 |
-
Public Works Regional Laboratory erection and
construction at Works Area WA3; |
-
Removal of Temporary Seawall |
-
Sign board erection at Works Area WA2 |
-
Silt curtain fabrication at Works Area WA2 and
WA4; |
-
Site office erection and construction at Works
Area WA2; |
-
Stone column installation barges setup and their
maintenance works at Works Area WA4. |
-
Surcharge removal & laying |
-
Vertical Band Drains |
Table 3.1 Summary of Number of Monitoring Events for 1-hr & 24-hr
TSP Concentration
Monitoring Parameter |
Location |
No. of monitoring events* |
Mar
12 – Apr 18 |
||
1-hr TSP |
AMS2 |
1056 |
AMS3A/3B |
1056 |
|
AMS7/7A/7B |
1056 |
|
24-hr TSP |
AMS2 |
352 |
AMS3A/3B |
352 |
|
AMS7/7A/7B |
352 |
*No. of monitoring events
carried out under this Contract only. The rest of the monitoring events between
September 2017 and April 2018 for 1-hour TSP and 24-hour TSP are reported in
the EM&A Report prepared for Contract No. HY/2013/01.
Table 3.2 Summary of Number of Exceedances for 1-hr & 24-hr
TSP Monitoring
Monitoring Parameter |
Location |
Level of Exceedance |
Number of
Exceedance |
Mar 12 – Apr 18 |
|||
1-hr TSP |
AMS2 |
Action |
0 |
Limit |
0 |
||
AMS3A/3B |
Action |
0 |
|
Limit |
0 |
||
AMS7/7A/7B |
Action |
0 |
|
Limit |
0 |
||
Total |
0 |
||
24-hr TSP |
AMS2 |
Action |
2 |
Limit |
1 |
||
AMS3A/3B |
Action |
18 |
|
Limit |
9 |
||
AMS7/7A/7B |
Action |
5 |
|
Limit |
0 |
||
Total |
35 |
Table 3.3 Maximum Predicted TSP concentrations under the
“Mitigated” scenario
ASR |
Location ID in the approved EIA report |
Predicted Daily Concentrations* |
Average Impact 1-hour TSP Levels#, mg/m3 |
Average Impact 24-hour TSP Levels#, mg/m3 |
|
1-hour |
24-hour |
||||
AMS7/AMS7A/ AMS7B |
Hong Kong SkyCity Marriott Hotel |
344 |
92 |
77 |
66 |
*Extracted from Table
5-8 of the EIA report
# Both average Impact 1-hour TSP Levels and average Impact 24-hour TSP
Levels were calculated using monitoring data obtained by this Contract between
March 2012 to August 2017. Monitoring works and monitoring data between
September 2017 and April 2018 for the Contract are covered by Contract No.
HY/2013/01 Hong Kong-Zhuhai Macao Bridge HKBCF –Passenger Clearance Building.
Table 3.4 Summary of Number of Monitoring Events for Impact Noise
Monitoring Parameter |
Location |
No. of monitoring events |
Mar 12- April 18 |
||
Noise |
NMS2 |
283 |
NMS3A/NMS3B |
283 |
*Only no. of monitoring events
carried out under this Contract is reported. The rest of the monitoring events
between September 2017 and April 2018 for construction noise monitoring are
reported in the EM&A Report prepared for Contract No. HY/2013/01.
Table 3.5 Summary of Number of Monitoring Exceedances for Impact Noise
Monitoring Parameter |
Location |
Level of Exceedance |
No. of Exceedance(s) |
Noise |
NMS2 |
Action |
1 |
Limit |
0 |
||
NMS3A/NMS3B |
Action |
0 |
|
Limit |
1 |
||
Total |
2 |
Table
3.6 Construction Noise Impact at Noise Sensitive Receivers
NSR |
Location |
Predicted Noise Levels, dB(A) |
|
Total Noise
Impacts, dB(A) |
Criterion, dB(A) |
||
NMS2 |
Seaview Crescent Tower 1 |
74 |
75 |
Table
3.7 Summary of Construction Noise Monitoring Results in
the Reporting Period
NSR |
Location |
Average#,
dB(A), Leq,30 mins |
Range#,
dB(A), Leq,30 mins |
Limit Level, dB(A), Leq,30 mins |
NMS2 |
Seaview Crescent Tower 1 |
67 |
61 - 74^ |
75 |
NMS3A/NMS3B |
Site Boundary of Site Office Area at Works Area
WA2 |
66 |
53 - 75* |
70 |
* Façade measurements were made at NMS3A on or before 5
September 2012. Free field measurements were made on all monitoring after 5 September 2012 due
to removal of site office located at NMS3A. A correction of +3 dB(A) was be made to all free field
measurements.
# Both average and range of construction noise were calculated using monitoring
data obtained by this Contract between March 2012 to August 2017. Monitoring
works and monitoring data between September 2017 and April 2018 for the
Contract are covered by Contract No. HY/2013/01 Hong Kong-Zhuhai Macao Bridge
HKBCF –Passenger Clearance Building.
Table 3.8 Summary of Number
of Monitoring Events for Impact Water Quality
Monitoring Parameter |
Tide |
No. of monitoring events# |
Mar 17 – Apr 18 |
||
Water Quality |
Mid-Ebb |
844* |
Mid-Flood |
845* |
#monitoring works between September 2017 and April 2018 for the Contract are covered by Contract No. HY/2013/01 Hong Kong-Zhuhai Macao Bridge HKBCF –Passenger Clearance Building.
Table 3.9 Summary of Water
Quality Exceedances in Mar 12 – Apr 18
Station |
Exceedance Level |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Total |
||||||
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
|||
IS5 |
Action |
0 |
0 |
1 |
2 |
0 |
0 |
3 |
4 |
4 |
6 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
IS(Mf)6 |
Action |
0 |
0 |
0 |
0 |
0 |
1 |
5 |
9 |
5 |
10 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
IS7 |
Action |
1 |
0 |
1 |
0 |
0 |
1 |
3 |
10 |
5 |
11 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
IS8 |
Action |
0 |
0 |
0 |
0 |
0 |
1 |
2 |
10 |
2 |
11 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
3 |
0 |
4 |
||
IS(Mf)9 |
Action |
0 |
3 |
0 |
1 |
0 |
0 |
5 |
12 |
5 |
16 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
||
IS10/IS10(N) |
Action |
6 |
4 |
8 |
6 |
0 |
1 |
1 |
13 |
14 |
25 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
0 |
3 |
||
IS(Mf)11 |
Action |
3 |
5 |
7 |
7 |
0 |
2 |
1 |
11 |
11 |
25 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
||
IS(Mf)16 |
Action |
1 |
2 |
5 |
2 |
0 |
0 |
5 |
6 |
12 |
11 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
IS17/IS17(N) |
Action |
3 |
4 |
8 |
3 |
0 |
1 |
5 |
1 |
15 |
10 |
|
Limit |
0 |
0 |
0 |
0 |
1 |
0 |
3 |
0 |
4 |
0 |
||
SR3/SR3(N) |
Action |
2 |
1 |
0 |
0 |
0 |
0 |
3 |
4 |
5 |
5 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
Action |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
12 |
1 |
13 |
|
SR4(N) |
||||||||||||
|
Limit |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
1 |
2 |
|
SR5/SR5(N) |
Action |
1 |
1 |
1 |
1 |
1 |
1 |
0 |
19 |
4 |
21 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
3 |
||
SR6 |
Action |
0 |
2 |
0 |
1 |
0 |
0 |
2 |
12 |
2 |
15 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
2 |
||
SR7 |
Action |
1 |
4 |
0 |
0 |
0 |
0 |
0 |
15 |
1 |
19 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
||
SR10A |
Action |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
3 |
0 |
5 |
|
Limit |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
2 |
||
SR10B(N) |
Action |
0 |
0 |
1 |
2 |
0 |
0 |
0 |
7 |
1 |
8 |
|
Limit |
1 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
2 |
||
Total |
Action |
18 |
26 |
33 |
26 |
1 |
9 |
36 |
148 |
297 |
||
Limit |
2 |
3 |
0 |
0 |
1 |
2 |
5 |
14 |
27 |
Note: S: Surface;
M: Mid-depth;
Dissolved Oxygen
Turbidity
Suspended
Solids
Table 3.10 Summary of number of water quality exceedances per
monitoring month
Month |
Imported Fill* m3/month |
DO (Surface & Middle); and DO (Bottom) |
Depth averaged Turbidity |
Depth averaged SS |
Total |
(mm/yy) |
|||||
Mar-12 |
0 |
0 |
1 |
0 |
1 |
Apr-12 |
0 |
0 |
2 |
3 |
5 |
May-12 |
0 |
1 |
0 |
0 |
1 |
Jun-12 |
0 |
0 |
0 |
2 |
2 |
Jul-12 |
0 |
0 |
0 |
0 |
0 |
Aug-12 |
28,053 |
0 |
0 |
0 |
0 |
Sep-12 |
12,769 |
0 |
0 |
0 |
0 |
Oct-12 |
28,882 |
0 |
1 |
1 |
2 |
Nov-12 |
2,276 |
0 |
0 |
9 |
9 |
Dec-12 |
0 |
0 |
0 |
10 |
10 |
Jan-13 |
0 |
0 |
0 |
6 |
6 |
Feb-13 |
2,608 |
0 |
0 |
0 |
0 |
Mar-13 |
52568 |
0 |
0 |
2 |
2 |
Apr-13 |
119967 |
0 |
1 |
4 |
5 |
May-13 |
448159 |
0 |
0 |
5 |
5 |
Jun-13 |
245188.5 |
7 |
1 |
1 |
9 |
Jul-13 |
252327.4 |
0 |
0 |
3 |
3 |
Aug-13 |
287182.6 |
0 |
1 |
5 |
6 |
Sep-13 |
368995 |
0 |
0 |
5 |
5 |
Oct-13 |
602966 |
0 |
0 |
8 |
8 |
Nov-13 |
593481 |
0 |
0 |
15 |
15 |
Dec-13 |
930460 |
0 |
0 |
5 |
5 |
Jan-14 |
952135 |
0 |
0 |
7 |
7 |
Feb-14 |
886830 |
0 |
0 |
1 |
1 |
Mar-14 |
1,111,998 |
0 |
1 |
9 |
10 |
Apr-14 |
1,291,808 |
0 |
0 |
0 |
0 |
May-14 |
1,181,417 |
0 |
0 |
0 |
0 |
Jun-14 |
752,771 |
0 |
0 |
0 |
0 |
Jul-14 |
1,252,437 |
0 |
0 |
0 |
0 |
Aug-14 |
1,427,973 |
14 |
0 |
0 |
14 |
Sep-14 |
1,370,511 |
0 |
0 |
4 |
4 |
Oct-14 |
1,750,755 |
0 |
1 |
17 |
18 |
Nov-14 |
1,788,611 |
0 |
0 |
1 |
1 |
Dec-14 |
1,608,665 |
0 |
0 |
2 |
2 |
Jan-15 |
1,774,785 |
0 |
0 |
13 |
13 |
Feb-15 |
1,120,668 |
0 |
0 |
2 |
2 |
Mar-15 |
376,294 |
0 |
0 |
2 |
2 |
Apr-15 |
240,642 |
0 |
0 |
0 |
0 |
May-15 |
743,731 |
0 |
0 |
0 |
0 |
Jun-15 |
368,595 |
0 |
0 |
0 |
0 |
Jul-15 |
35,549 |
0 |
0 |
2 |
2 |
Aug-15 |
23,625 |
0 |
0 |
0 |
0 |
Sep-15 |
34,520 |
0 |
0 |
1 |
1 |
Oct-15 |
9,246 |
0 |
0 |
1 |
1 |
Nov-15 |
0 |
0 |
0 |
1 |
1 |
Dec-15 |
0 |
0 |
0 |
1 |
1 |
Jan-16 |
0 |
0 |
0 |
0 |
0 |
Feb-16 |
0 |
0 |
2 |
2 |
4 |
Mar-16 |
38,318.70 |
0 |
0 |
0 |
0 |
Apr-16 |
18,738.00 |
0 |
0 |
0 |
0 |
May-16 |
45,272.30 |
0 |
0 |
1 |
1 |
Jun-16 |
27,882.00 |
0 |
0 |
0 |
0 |
Jul-16 |
54,308.70 |
0 |
0 |
0 |
0 |
Aug-16 |
18,958.70 |
0 |
0 |
0 |
0 |
Sep-16 |
30,298.70 |
0 |
0 |
3 |
3 |
Oct-16 |
24,499.30 |
0 |
0 |
5 |
5 |
Nov-16 |
280,380 |
0 |
0 |
12 |
12 |
Dec-16 |
11,704.00 |
0 |
0 |
1 |
1 |
Jan-17 |
18,892.70 |
0 |
0 |
0 |
0 |
Feb-17 |
17,574.70 |
0 |
0 |
3 |
3 |
Mar-17 |
20,601.30 |
0 |
2 |
4 |
6 |
Apr-17 |
39,960.70 |
0 |
0 |
1 |
1 |
May-17 |
22,430.70 |
0 |
0 |
0 |
0 |
Jun-17 |
0 |
0 |
0 |
0 |
0 |
Jul-17 |
0 |
0 |
0 |
2 |
2 |
Aug-17 |
0 |
0 |
0 |
0 |
0 |
Sep-17 |
0 |
86 |
3 |
5 |
94 |
Oct-17 |
0 |
0 |
0 |
2 |
2 |
Nov-17 |
0 |
0 |
0 |
6 |
6 |
Dec-17 |
0 |
0 |
0 |
3 |
3 |
Jan-18 |
0 |
0 |
0 |
0 |
0 |
Feb-18 |
0 |
0 |
0 |
1 |
1 |
Mar-18 |
0 |
0 |
0 |
1 |
1 |
Apr-18 |
0 |
0 |
0 |
3 |
3 |
*Only marine filling is counted
·
WSR 27 - San Tau Beach SSSI with SR3/SR3(N)
·
WSR 22c- Tai Ho Wan Inlet (outside) with SR4(N)
·
WSR 25 - Cooling water intake at HK
International Airport with SR5/SR5(N)
Dissolved
oxygen (DO)
Table 3.11 Comparison of depth averaged dissolved oxygen levels
(Surface & Mid-depth, Bottom depth) during baseline and impact monitoring
period (mgL-1)
Sensitive Receiver in Baseline |
Associated Location during
Impact Monitoring |
Monitoring Depth |
Baseline mean |
Impact mean (November 2014) |
Depletion during Impact Monitoring |
|||
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
|||
SR3 |
SR3/SR3(N)* |
Surface & mid |
6.8 |
6.7 |
8.0 |
7.9 |
-1.2 |
-1.2 |
Bottom |
- |
6.2 |
- |
- |
- |
- |
||
SR4^ |
SR4(N)** |
Surface & mid |
6.1 |
6.3 |
8.4 |
8.4 |
-2.3 |
-2.1 |
Bottom |
6.0 |
6.2 |
8.3 |
8.3 |
-2.3 |
-2.1 |
||
SR5 |
SR5/SR5(N)** |
Surface & mid |
6.4 |
6.3 |
8.0 |
7.8 |
-1.6 |
-1.5 |
Bottom |
6.1 |
6.1 |
8.0 |
7.7 |
-1.9 |
-1.6 |
||
SR6 |
SR6** |
Surface & mid |
6.6 |
6.5 |
8.1 |
8.2 |
-1.5 |
-1.7 |
Bottom |
6.2 |
6.1 |
8.1 |
8.2 |
-1.9 |
-2.1 |
||
SR7 |
SR7** |
Surface & mid |
6.3 |
6.0 |
7.9 |
7.9 |
-1.6 |
-1.9 |
Bottom |
6.1 |
5.9 |
7.8 |
7.8 |
-1.7 |
-1.9 |
||
SR10A |
SR10A |
Surface & mid |
6.0 |
6.0 |
7.6 |
7.6 |
-1.6 |
-1.6 |
Bottom |
5.7 |
5.8 |
7.6 |
7.6 |
-1.9 |
-1.8 |
||
SR10B^ |
SR10B(N)** |
Surface & mid |
6.1 |
6.0 |
7.6 |
7.6 |
-1.5 |
-1.6 |
Bottom |
6.2 |
5.8 |
7.6 |
7.6 |
-1.4 |
-1.8 |
Suspended
solids (SS)
Table 3.12 Ambient
and Tolerance Values for Suspended Sediment Concentrations (mgL-1)
in the Vicinity of Sensitive Receivers adopted in the EIA
Sensitive Receiver in EIA Report |
Associated EPD Station |
Ambient value (90th Percentile) |
Tolerance value (30% Tolerance) |
||
Dry Season |
Wet Season |
Dry Season |
Wet Season |
||
WSR 27 |
NM5,6,8 |
8.3 |
5.6 |
2.5 |
1.7 |
WSR 22c |
NM1,2,3 |
5.5 |
3.7 |
1.7 |
1.1 |
WSR 25 |
NM1,2,3 |
5.5 |
3.7 |
1.7 |
1.1 |
Table 3.13 Calculated
Elevations in Suspended Sediment Concentrations at Sensitive Receivers (mgL-1)
under the 2012 mitigated scenario from the EIA
Sensitive Receiver in EIA Report |
Associated Location during
Impact Monitoring |
Calculated Elevations |
|
Dry Season |
Wet Season |
||
WSR 27 |
SR3/SR3(N) |
0.0 |
0.0 |
WSR 22c |
SR4(N) |
0.1 |
0.0 |
WSR 25 |
SR5/SR5(N) |
3.0 |
2.7 |
Table 3.14 Baseline suspended solids levels and 30% of
baseline mean (mgL-1)
Associated Location in Baseline
Report |
Baseline mean |
30% of baseline mean |
||
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
|
SR3 |
14.0 |
16.3 |
4.2 |
4.9 |
SR4 |
11.3 |
12.2 |
3.4 |
3.7 |
SR5 |
10.6 |
11.9 |
3.2 |
3.6 |
SR6 |
11.9 |
11.9 |
3.6 |
3.6 |
SR7 |
11.4 |
10.4 |
3.4 |
3.1 |
SR10A |
10.2 |
10.2 |
3.1 |
3.1 |
SR10B |
11.5 |
11.1 |
3.5 |
3.3 |
Table 3.15 Average
suspended solids levels at sensitive receivers (mgL-1) in November 2014
Sensitive Receiver in Baseline |
Associated Location during
Impact Monitoring |
Impact SS Mean (in November 2014) |
|||
Mid-ebb |
Elevation |
Mid-flood |
Elevation |
||
SR3 |
SR3/SR3(N) |
4.7 |
-9.3 |
6.1 |
-10.2 |
SR4 |
SR4(N)* |
6.4 |
-4.9 |
9.4 |
-2.8 |
SR5 |
SR5/SR5(N) |
4.9 |
-5.7 |
8.6 |
-3.3 |
SR6 |
SR6 |
5.3 |
-6.6 |
5.9 |
-6.0 |
SR7 |
SR7 |
6.3 |
-5.1 |
7.2 |
-3.2 |
SR10A |
SR10A |
4.2 |
-6.0 |
5.3 |
-4.9 |
SR10B |
SR10B(N) |
4.4 |
-7.1 |
6.0 |
-5.1 |
3.4.1.1 In accordance with the
requirements specified in Section 9.3 of the EM&A Manuel, monthly vessel-
based surveys were conducted to monitor impacts on the Indo-Pacific humpback or
Chinese white dolphin (Sousa chinensis). The surveys were conducted in the areas
known as NEL and NWL and travelled the transect lines depicted in Figure 4a-4d.
3.4.1.2 The total transect length for NEL
and NWL combined is approximately 111km although some Contract and other works
at times have caused temporary truncation of some lines, particularly lines
1,2,9 and 10. Due to the presence of deployed silt curtain systems at the site
boundaries of the Contract, some of the transect lines shown in Figure 4a-4d
could not be fully surveyed during the regular survey. Transect 10 is reduced
from 6.4km to approximately 3.6km in length due to the HKBCF construction site.
3.4.1.3 Coordinates
for transect lines 1, 2, 7, 8, 9 and 11 have been updated in respect to the
Proposal for Alteration of Transect Line for Dolphin Monitoring approved by EPD
in August 2015 and May 2017. Therefore, the total transect length for both NEL
and NWL combined is reduced to approximately 108km.
3.4.1.4 Surveys were conducted twice per
month, using combined line transect and photo-identification techniques. The
research team comprised qualified and experienced researchers and Marine Mammal
Observers (MMO). The Dolphin Monitoring for this Contract ceased in August 2017
therefore, this report includes survey data from March – August 2017,
inclusive. Monitoring works and monitoring data between September 2017 and
April 2018 for the Contract are covered by Contract No. HY/2013/01 Hong
Kong-Zhuhai Macao Bridge HKBCF –Passenger Clearance Building.
3.4.2.1 Relevant mitigation measures for
dolphins, as recommended in the EIA Report were stipulated in the EM&A
Manual for the Contractor to adopt. The implementation status of mitigation
measures for dolphins is depicted in Appendix C.
3.4.3.1 The enhanced EAP for CWD monitoring
with numerical AL/LL were implemented in the reporting period.
3.4.3.2 15 Limit level exceedances and 6 Action level exceedances were recorded in the reporting year for impact dolphin monitoring. And
the Event Action Plan was triggered (Table 3.16)
Table 3.16 Summary of the STG/ANI
Quarterly Values
Quarterly
period ^ |
|
STG* |
ANI** |
Level
Exceeded |
March 2013- May 2013 |
NEL |
0 |
0 |
Limit Level |
NWL |
3 |
8.6 |
||
June 2013- August 2013 |
NEL |
1.8 |
1.8 |
Action |
NWL |
5.7 |
16.6 |
Action |
|
September 2013- November 2013 |
NEL |
0 |
0 |
Action |
NWL |
6.7 |
24.7 |
Action |
|
December 2013- February 2014 |
NEL |
0.5 |
0.5 |
Action |
NWL |
4.5 |
20.7 |
Action |
|
March 2014- May 2014 |
NEL |
0 |
0 |
Limit Level |
NWL |
0.7 |
3 |
||
June 2014- August 2014 |
NEL |
0.5 |
2.7 |
Limit Level |
NWL |
3.6 |
9.8 |
||
September 2014- November 2014 |
NEL |
0 |
0 |
Limit Level |
NWL |
2.1 |
7.1 |
||
December 2014- February 2015 |
NEL |
0 |
0 |
Limit Level |
NWL |
2.1 |
4.3 |
||
March 2015- May 2015 |
NEL |
0 |
0 |
Limit Level |
NWL |
1.6 |
5.2 |
||
June 2015- August 2015 |
NEL |
0 |
0 |
Limit Level |
NWL |
1.7 |
4.7 |
||
September 2015- November 2015 |
NEL |
0 |
0 |
Limit Level |
NWL |
1.9 |
3.8 |
||
December 2015- February 2016 |
NEL |
0 |
0 |
Limit Level |
NWL |
1.2 |
4.5 |
||
March 2016- May 2016 |
NEL |
0 |
0 |
Limit
Level |
NWL |
1.4 |
4.6 |
||
June
2016- August 2016 |
NEL |
0 |
0 |
Limit
Level |
NWL |
1.4 |
4.6 |
||
September
2016- November 2016 |
NEL |
0 |
0 |
Limit
Level |
NWL |
2.4 |
8 |
||
December
2016- February 2017 |
NEL |
0 |
0 |
Limit
Level |
NWL |
1.9 |
8.3 |
||
March 2017- May 2017 |
NEL |
0 |
0 |
Limit
Level |
NWL |
0.5 |
2.9 |
||
June
2017- August 2017 |
NEL |
0 |
0 |
Limit
Level |
NWL |
1.6 |
5.1 |
* STG represents groups of dolphins (recorded on effort)
** ANI represents number of
individual dolphins (recorded on effort)
^The Dolphin Monitoring for this Contract
ceased in August 2017 therefore, this report includes survey data from March
2012 – August 2017, inclusive. Monitoring works and monitoring data between
September 2017 and April 2018 for the Contract are covered by Contract No.
HY/2013/01 Hong Kong-Zhuhai Macao Bridge HKBCF –Passenger Clearance Building.
3.4.4.1 Vessel-based surveys were
conducted monthly from March 2012 to August 2017. A total of 267 survey days
were completed between March 2012-August 2017. A total of 14,387km were completed of which
14,116.9 km were conducted under favourable
conditions (defined as Beaufort Sea State 3 or better and with visibility of
>1km). In the first year of impact
monitoring (2012-13), 49 survey days were completed (total travelled 2627.5km;
under favourable conditions 2601.4km). In the second year of impact monitoring
(2013-14), 50 survey days were completed (total travelled 2667.1km; 2595.4km
under favourable conditions). In the third year of impact monitoring (2014-15),
48 survey days were completed (total travelled 2641.7km; 2637.1km conducted
under favourable conditions). In the fourth year of impact monitoring
(2015-16), 48 survey days were completed (total travelled 2615.7km; 2572 km
conducted under favourable conditions). In the fifth
year of impact monitoring (2016-17), 48 survey days were completed (total
travelled 2619.7km; 2520.9 km conducted under favourable
conditions). In the final reporting
period of impact monitoring for this contract (March 2017– August 2017), 24
survey days were completed (total travelled 1215.3km; 1190.1km conducted under favourable conditions).
For the entire contract, >98% of the track length covered was
completed under favourable conditions. Between March 2017 and August 2017, a total
of 20 dolphin sightings were recorded, 8 “on effort[1]” and 12 as “opportunistic”. In the first year of impact monitoring, a total
of 203 dolphin sightings were recorded, 145 as on effort and 58 as
opportunistic. In the second year, a total of 135 dolphin sightings were
recorded, 91 on effort and 44 opportunistic. In the third year, a total of 72
dolphin sightings were recorded, 46 on effort and 26 opportunistic. In the
fourth year, a total of 43 dolphin sightings were recorded, 26 on effort and 17
opportunistic. In the fifth year, a total of 50 dolphin sightings were
recorded, 32 on effort and 18 opportunistic. Throughout the monitoring period a
total of 523 sightings were recorded, 348 “on effort” and 175 opportunistic
(Appendix H: Table 1; Figure 1).
Table 3.17 Summary of All Dolphin Impact Monitoring
Sightings from Year 1 (March 2012 – February 2013) to the Year 6 (March 2017 –
August 2017) of the HKBCF Reclamation Works Project
Year |
Total Sightings |
2012-13 |
203 |
2013-14 |
135 |
2014-15 |
72 |
2015-16 |
43 |
2016-17 |
50 |
March 17 – August 2017* |
20 |
* The Dolphin Monitoring for this Contract
ceased in August 2017, monitoring works and monitoring data between September
2017 and April 2018 for the Contract are covered by Contract No. HY/2013/01
Hong Kong-Zhuhai Macao Bridge HKBCF –Passenger Clearance Building.
3.4.5.1. Sightings of dolphins were
divided into yearly periods. The number
of sightings steadily decreased from March 2012 to February 2016, from 145 to
26 on effort sightings. In 2016-17, there was a slight increase to 32 on effort
sightings (Appendix H: Table 1). A
marked shift in sightings from throughout NEL and NWL to the northwest of NWL
and waters adjacent to south NWL occurs from 2012 to 2017 (Appendix H: Figure
2). Dolphins were consistently distributed in areas of rocky, reefy shoreline or where there was a marked depth contour.
These areas are the Sha Chau and Lung Kwu Chau Marine
Protected Area (SCLKCMPA), the adjacent maritime border of Hong Kong SAR and
the Peoples Republic of China (PRC) and the Tai O area. Since long term
monitoring has been initiated by AFCD, there has been a regular and year-round
occurrence of dolphins in these areas of northern Lantau.
3.4.6.1 Encounter rates of “on effort” sightings (i.e. groups) for the years 2012-13 to 2016-17 were calculated[2]. The yearly encounter rate (using on effort sightings recorded during Beaufort Sea State 3 or better) has decreased from 5.57 sightings per 100km effort to 1.01 sightings per 100km effort, between year 1 and year 4 of the impact monitoring period. In year 5 (2016-17) a slight increase in encounter rate was recorded; 1.27 sightings per 100km[3] number of sightings (Appendix H: Table 1).
3.4.6.2 After considering the various
statistical processes that best fit the data collected by this Contract, ANOVA
is powerful enough to discern whether there is significant difference between
baseline and monitored period. We therefore selected the statistical process
for the data specific to this Contract. A repeated measures two-way ANOVA with unequal sample size was conducted. Impact monitoring from all quarters (impact phase) comparison is made to a single time within the baseline monitoring
period, September to November 2011[4], this baseline data set
has been used consistently throughout this projects EM&A reporting. The
requirement of this test was to explore differences between pre and impact
monitoring phase. This comparison evaluates whether there is significant
difference between encounter rates obtained during baseline and encounter rates
obtained right before this Contract ceased construction activities. For details
of Monthly STG and ANI encounter rates used in ANOVA, please refer to Appendix
H: Table 2a and Appendix H: Table 2b.
3.4.6.3 The two variables that were
examined included the two locations (NEL and NWL) and two periods (baseline and
impact phase). For the comparison
between the baseline period and the impact phase, the p-values for the
differences in average dolphin encounter rates of STG and ANI were 0.00 and
0.00 respectively. If the alpha value is
set at 0.05, significant differences were detected between the present quarter
and baseline quarter in both the average dolphin encounter rates of STG and
ANI. The results show that a significant decline of both individuals and groups
of dolphins between baseline and impact monitoring. HZMB works is one of the
contributing factors affecting the dolphins. It was also concluded the
contribution of impacts due to the HZMB works as a whole (or individual marine
contracts) cannot be quantified nor separate from the other stress factors. As
AFCD Monitoring has reported a significant decline in this area prior to HKBCF
construction activities, it is difficult to distinguish how much HKBCF
activities may have influenced this existing decline.
3.4.7. Group Size
3.4.7.1
The majority of all sightings recorded were of less than 5 individuals
(~70%), and sightings of groups containing 10 or more individuals were rare
(2.7%). Larger groups were seen in southern NWL and in, or adjacent to,
SCLKCMP. Groups of five individual dolphins or more were sighted throughout the
year. Groups of 5-9 individuals and more than 10 individuals were also noted
during opportunistic sightings recorded from WL (Appendix H: Figure 3; 4).
3.4.8. Habitat Use
3.4.8.1. The EM&A Manuel stipulated
that surveys be conducted in such a way as to be comparable to the baseline
survey for this Contract (September -November 2011) and to the long term annual
monitoring conducted by AFCD. As such, analyses of density per survey effort
(DPSE) and sightings per survey effort (SPSE) were calculated in accordance
with the methodology detailed in AFCD reports (e.g., AFCD 2012[5]). The survey areas are divided
into 1km x 1km squares and the relative number of sightings and densities are
calculated for each block. NEL has 55
blocks and NWL has 90 blocks (only blocks of more than 0.75km2 are
included). For the period March 2012-August 2017, DPSE was calculated in six
categories, ranging from low use (< 20 DPSE), moderate use (20.1-60 DPSE)
and high use (> 60 DPSE). Within NEL, 1.8% of its area was categorized as
high use; 3.6% as moderate use and 94.6% as low use. Within NWL, 3.3% of its
area was categorized as high use; 15.6% as moderate use and 81.1% as low use
(Appendix H: Figure 5).
3.4.8.2. For the period March 2012-August
2017, SPSE was calculated in six categories, ranging from low use (< 5
SPSE), moderate use (5.1-15 SPSE) and high use (> 15 SPSE). Within NEL, 1.8%
of its area was calculated as high use, 36.4% as moderate use and 61.8% as low
use. Within NWL, 4.4% of its area was
calculated as high use, 68.9% as moderate use and 26.7% as low use (Appendix H:
Figure 6).
3.4.8.3. For the period February 2011 –
January 2012, DPSE was calculated in six categories, ranging from low use to
high use. NEL and NWL have 4% and 17% of
each respective area classified as high use (> 60 DPSE); 20% (NEL) and 16%
(NWL) as moderate use (20.1-60 DPSE); and 76% (NEL) and 68% (NWL) as low use
(< 20 DPSE) (Appendix H: Figure 7). These figures were compared to impact
monitoring data for March 2012-August 2017 (Table 3.18). For DPSE in NWL, there
is a 13% increase in low use grid cells, no change in moderate use cells and a
decrease of 14% in high use cells.
Noting the geographical location of the cells between advanced and impact
monitoring, there are less high use cells in the centre
of the NWL area indicating that habitat utilisation
of this area has decreased. In NEL,
there is a 19% increase in low use grid cells, a 17% decrease in moderate use
cells and a 2% decrease in high use cells.
3.4.8.4. For the period February 2011 –
January 2012, SPSE was calculated in six categories, ranging from low use to
high use. NEL and NWL have 9% and 22% of each respective area classified as
high use (> 15 SPSE); 31% (NEL) and 27% (NWL) as moderate use (5.1-15 SPSE);
and 60% (NEL) and 51% (NWL) as low use (< 5 SPSE) (Appendix H: Figure
7). These figures were compared to
impact monitoring data for March 2012-August 2017 (Table 3.18). For SPSE in NWL, there is a 24% decrease in
low use grid cells, a 42% increase in moderate use grid cells and a 18%
decrease in high use grid cells. For
SPSE in NEL, there is a 2% increase in low use grid cells, a 5% increase in
moderate use cells and a 7% decrease in high use cells.
Table 3.18
Comparison of low, moderate and high habitat utilisation
in NEL and NWL between advanced and impact monitoring (in %)
*Advance = advance baseline
monitoring conducted between 2011 and 2012.
3.4.8.5.
3.4.9. Mother and Calf Pairs
3.4.9.1. During impact monitoring, twelve females
were sighted with calves and/or juveniles; HZMB 014, HZMB 021, HZMB 023, HZMB
026, HZMB 043, HZMB 044, HZMB 047, HZMB 050, HZMB 073, HZMB 098, HZMB 114 and
HZMB 116. Some calves could not be assigned to known or identifiable females
(Appendix H: Figure 8). Mother-offspring bonds are known to last years,
sometimes decades therefore, following calves throughout the impact monitoring
period provides some insight to calf survivorship.
HZMB 014: This female was sighted with a
calf in 2012. In 2015, when last sighted during impact monitoring, there was a
juvenile that, although not closely associated with her, corresponded with the
size and colouration of a 3 year old dolphin.
HZMB 021 (NL37): This female was sighted
with a calf in 2012 and was not sighted again until early 2016. During this resighting, there was no juvenile of the appropriate age/colouration class recorded within the group
HZMB 023: This female was noted in close
association with a juvenile in 2012 (ID: HZMB 022) and the pair have been recorded
consistently throughout the impact monitoring period.
HZMB 026: This female was sighted with a
calf in January 2013. When last resighted during
impact monitoring in October 2014, a juvenille was
recorded in close association.
HZMB 044 (NL98): This female was first
sighted with a new born calf in 2012 (ID: HZMB 125). Although there was a gap
in resightings of approximately 15 months, this
female was sighted with HZMB 125 in May 2016. When HZMB 044 was last sighted
during impact monitoring in January 2017, HZMB 125 was not sighted. HZMB 125
would then have been 4.5 years old and the mother/offspring pair may no longer
have had a close association
HZMB 043: This female was seen once only with
a calf in 2012. No more sightings of this individual have been recorded during
impact monitoring.
HZMB 047: This female was first identified
in 2012. She was recorded with a calf in April 2015 and was not sighted again
during the impact monitoring period.
HZMB 050:
This female was first sighted with a calf in 2012 and resighted with a closely associated juvenile in January
2014. During her last sighting, in July 2014, no juvenile was recorded within
the group.
HZMB 073: This female was first sighted with
a calf in December 2012. In April 2013, the calf was recorded in close
association with this female. When this female was sighted again, and for the
final time during impact monitoring in May 2013, there were several young
animals within this group but none were closely associated with her.
HZMB 098 (NL104): This female was sighted
with a calf in May 2013 and again in February 2015, with a juvenile in close
association. This female was not sighted again until January 2017, at which
time, no dolphin sighted within the group corresponded to the age/colouration profile of 3-4 year old dolphin. This female
was last seen during impact monitoring in May 2017, again without an
appropriately sized/coloured dolphin within the
group.
HZMB 114:
This female was sighted with a new calf in November 2015 and was last
sighted, still in close proximity to a juvenile in January 2017.
HZMB 116: This female was sighted with a
calf in December 2013 and when last sighted during impact monitoring in August
2014, a calf was still in close association with her.
3.4.10. Activities
3.4.10.1. Five distinctive behavioural categories were defined; “feeding”,
“travelling” and “multiple” (more than one behaviour
was observed at one time), “other” and “unknown”. Feeding activity frequency dominated most
years, except 2015-16 where travelling was the most frequently observed
activity. In 2016-17, the last full year of impact monitoring data, feeding and
multiple activities, which included feeding, were the most frequent activities.
Although the frequency of focused surface active behaviour
was relatively small in the first three years of impact monitoring, after March
2015, such behaviour was rarely seen and only in
short bouts between other behavious (so classified
within the multiple behaviour group) (Appendix H:
Figure 9). Although feeding behaviour occurred
throughout the habitat, there is a preference for rocky reefy
habitat along the shorelines of SCLKCMP and Tai O, which is the usual habitat
of the dolphins prey. These areas have been consistently highlighted as
critical habitat for dolphins (Appendix H: Figure 10).
3.4.11. Photo-Identification Catalogue
3.4.11.1. A total of 122 dolphins comprise
the photo identification catalogue established specifically for the HZMB
Contract (Appendix H: Table 3). Not all dolphins
photographed are identifiable as only individuals with unambiguous marks, cuts,
wounds, injuries and/or pigmentation or with uniquely shaped fins can be
included in the photo-identification catalogue.
Several dolphins were resighted frequently (Table
3.19), although the majority of identified individuals were sighted only 1-2
times during the impact monitoring period. This implies that some individuals
rely more on NWL and NEL habitat than others, as also indicated in the long
term AFCD monitoring programme, and also reflects the
declining use NEL and NWL habitat as the Project progressed. In 2016-17, there
was some indication of a return of individuals sighted at the beginning of the
impact monitoring period.
Table 3.19 Dolphins Frequently
Recorded During Impact Monitoring Surveys.
* cannot be determined
3.4.12.1 For dolphin abundance, please
refer to corresponding annual report.
3.4.13.1 It was recognized in the EIA that
the HZMB is adjacent to several areas of importance to the dolphin population
of Hong Kong. As such, it was stipulated in the EM&A Manuel for the HKBCF
that a suitable analytical technique be proposed and implemented so that
significant changes could be detected. A multi-parameter spatial (sometimes
known as predictive) model was proposed and reviewed by management authorities
and analyses developed as and when data has been made available. The purpose of
the model was to make predictions of future habitat use, derived from baseline
information, and compare these predictions to actual observations.
Environmental covariates, such as salinity, temperature, depth, etc., which may
also be drivers of dolphin habitat use, were also tested within spatial models
so as to either eliminate or incorporate any influence these may have. The
model thus incorporated environmental variables salinity, temperature,
turbidity, depth, tidal state, time of day, as well as information associated with
the sighting, e.g., group size, behavior, boat association. Following a meeting in October 2015, ENPO
suggested that the information regarding density surface modelling presented in
Quarterly EM&A Reports and Annual EM&A Review Reports be provided as a
separate report with details for review. This ET agreed all such data and
results be removed and provided separately.
3.4.14.1. The variable nature of habitat
use, group size, behavior, mother and calf occurrence and encounter rates by
small delphinids and the ability to detect significant change in small
populations is a challenge faced by many research studies. Historical data from AFCD also shows such
variability (in AFCD annual monitoring reports). A view of individual distribution and behavioural activities for the reporting year do show that
areas of importance, such as Lung Kwu Chau, are still
being frequented, behavioural activities appear
similar to that known from pre construction
information, although travelling frequency appears to be on the increase, and
that at least one calf identified in 2012-13 has survived to 2016-17. In
2013-14, an emerging trend for decreased use of NEL was noted and no sightings
were seen in NEL in 2016-17. A single,
opportunistic sighting was made in NEL during this monitoring period. In
addition, a decrease in sightings in the mid-section of NWL is also noted.
3.4.15.3
Construction Phase: In section
10.6.4.25 of the EIA report, it is stated that, “Project has low potential to
cause increased sewage discharge, therefore this potential impact is
insignificant. The potential water quality impacts due to site runoff, sewage
from workforce and wastewater from various construction activities, and
accidental spillage would be controlled through the implementation of suitable
mitigation measures, including temporary drainage system, chemical toilets, etc”
3.4.15.4
Contract has largely maintained water quality objectives as described in
the EM&A Manual. The exceedances
noted were short in duration and localised to the
Project site. These incidents were short in duration and when the Contractor
was notified, actions were promptly taken and no further exceedances were
noted.
3.4.15.6
It is noted that for both of the above impact predictions to be
investigated more thoroughly, long term trends in pathogens and toxin loads in
CWD should be analysed. This has recently been completed for the
Pearl River Delta (PRD) population of CWD and it is noted that both
bioaccumulation and biomagnification are significantly higher than populations
elsewhere (Gui et
al 2014[7]). There has been no updated toxin analyses of Chinese white dolphin in
the reporting year.
3.4.15.7
In Section 10.7.2.8 of the EIA report, it is stated that, “164 ha of sea
area (138 ha reclamation and 26 ha works area) will be lost during construction
due to HKBCF reclamation near the northeast Airport Island. Although the sea
area is only utilised by limited number of individual
CWD, it is of moderate ecological value due to the close proximity of the
dolphin hotspot at the Brothers Islands. Moderate impact is anticipated and
mitigation measures are required. As the habitat loss due to construction would
largely be carried forward to the operational phase and become permanent
habitat loss, mitigation measures for operational phase (see Section 10.7.4)
will mitigate this impact as well.”
3.4.15.9
The Ecological Baseline Survey[8] defines an Impact Index which is
used to predict impact for each area through which the HZMB structure
passes. HKBCF is located in the area
defined as the “Northeast Lantau Section (NELS) – from the eastern edge of the
airport platform to its connection to the North Lantau Highway”.
3.4.15.10 It is noted that this report
states (Section 5.7.10) that “it is imperative that cumulative impacts along
the whole alignment [of HZMB] are thoroughly assessed”.
3.4.15.11 A reference to cumulative impacts
is made in Section 10.7.6 of the EIA.
Section 10.7.6.3 is relevant to HKBCF.
This refers only to the cumulative impact of the permanent loss of CWD habitat
and no other impacts of either the construction or operational phase of the
HZMB Contract. Nonetheless, the
conclusion of this section states that the setting up of a marine park
“effectively mitigates” CWD habitat loss. As such, this prediction cannot be
verified until such a time as a marine park is established.
3.4.15.12 A cumulative assessment has been
published using data gathered prior to the initiation of HKBCF construction
activities (Marcotte et al, 2015[9]). This assessment notes that the
increase in high speed ferry traffic has been concomitant to a significant
decrease in dolphins sighted in NEL and adjacent NWL waters. Several other threats were considered in this
study, however, high speed ferries were the most significant impact. Therefore,
this study showed a significant decline in dolphins in NEL and adjacent areas was
ongoing for a decade prior to commencement of HKBCF activities. The high speed
ferry traffic has continued to increase in the area as HKBCF and other Projects
have commenced[10].
3.4.16.1 Monitoring and auditing of marine
mammals was recommended for the construction phase of HKBCF to evaluate impact
on marine mammals.
3.4.16.2 Combined line transect and
photo-identification methodologies have been used as part of the AFCD long term
monitoring programme for over 15 years. As such, a
long term data set can be used to establish trends in population distribution
and abundance over the long term.
3.4.16.3 The AFCD annual monitoring
reports for the period 2011-2012, 2012-13, 2013-14, 2014-15, 2015-16 and
2016-17 have all stated that a significant decline had been detected in
population abundance in the NEL area over the last decade. Only long term inter annual abundance
estimates can be used to detect such changes. This decline was noted prior to
construction had begun at HKBCF and has now been attributed to high speed
ferries by an independent study (see Section 3.4.15.12).
3.4.17.1 Marine mammal monitoring was
conducted between March 2012 and August 2017 in accordance with EM&A Manuel
methodologies. These methodologies have been invaluable in the past in
determining both broad scale and long term patterns of distribution, abundance,
association, habitat use and behavioral activities. There is historically much variation in these
parameters and most observations to date have concurred with observations
documented previously with the now emerging trend of decreased habitat use
within NEL. As AFCD Monitoring has
reported a significant decline in this area prior to HKBCF construction
activities, it is difficult to distinguish how much HKBCF activities may have
influenced this existing decline.
3.4.17.2 15 Limit level exceedances and 6
Action level exceedances were recorded in the reporting period for impact dolphin
monitoring. After investigation, it was concluded that the HZMB works is one of
the contributing factors affecting the dolphins. It was also concluded the
contribution of impacts due to the HZMB works as a whole (or individual marine
contracts) cannot be quantified nor separate from the other stress factors. For
investigation results please refer to Appendix L of the corresponding quarterly
reports.
6.1.4.1
15
Limit level exceedances and 6 Action level exceedances were recorded in the
reporting period for impact dolphin monitoring. After investigation, it was
concluded that the HZMB works is one of the contributing factors affecting the
dolphins. It was also concluded the contribution of impacts due to the HZMB
works as a whole (or individual marine contracts) cannot be quantified nor
separate from the other stress factors. Event Action Plan for Impact Dolphin
Monitoring was triggered. For investigation results please refer to Appendix L
of the corresponding quarterly reports.
l All
working plants and vessels on site should be regularly inspected and properly
maintained to avoid dark smoke emission.
l All vehicles should be washed to
remove any dusty materials before leaving the site.
l Haul roads should be sufficiently
dampened to minimize fugitive dust generation.
l Wheel washing facilities should
be properly maintained and reviewed to ensure properly functioning.
l Temporary exposed slopes and open
stockpiles should be properly covered.
l Enclosure should be erected for
cement debagging, batching and mixing operations.
l Water spraying should be provided to suppress fugitive dust for any dusty
construction activity.
l Quieter powered mechanical
equipment should be used as far as possible.
l Noisy operations should be
oriented to a direction away from sensitive receivers as far as possible.
l Proper and effective noise
control measures for operating equipment and machinery on-site should be
provided, such as erection of movable noise barriers or enclosure for noisy
plants. Closely check and replace the sound insulation materials regularly
l Vessels and equipment operating
should be checked regularly and properly maintained.
l Noise Emission Label (NEL) shall
be affixed to the air compressor and hand-held breaker operating within works
area.
l Better scheduling of construction
works to minimize noise nuisance.
l Regular review and maintenance of
silt curtain systems, drainage systems and desilting facilities in order to
make sure they are functioning effectively.
l Construction of seawall should be
completed as early as possible.
l Regular inspect and review the
loading process from barges to avoid splashing of material.
l Silt, debris and leaves
accumulated at public drains, wheel washing bays and perimeter u-channels and
desilting facilities should be cleaned up regularly.
l Silty effluent should be treated/
desilted before discharged. Untreated effluent should be prevented from
entering public drain channel.
l Proper drainage channels/bunds
should be provided at the site boundaries to collect/intercept the surface
run-off from works areas.
l Exposed slopes and stockpiles
should be covered up properly during rainstorm.
l All types of wastes, both on land
and floating in the sea, should be collected and sorted properly and disposed
of timely and properly. They should be properly stored in designated areas
within works areas temporarily.
l All chemical containers and oil
drums should be properly stored and labelled.
l All plants and vehicles on site
should be properly maintained to prevent oil leakage.
l All kinds of maintenance works
should be carried out within roofed, paved and confined areas.
l All drain holes of the drip trays
utilized within works areas should be properly plugged to avoid any oil and
chemical waste leakage.
l Oil stains on soil surface and
empty chemical containers should be cleared and disposed of as chemical waste.
l Regular review should be
conducted for working barges and patrol boats to ensure sufficient measures and
spill control kits were provided on working barges and patrol boats to avoid
any spreading of leaked oil/chemicals.
l All existing,
retained/transplanted trees at the works areas should be properly fenced off
and regularly inspected.
[1] On effort” sightings are classified as those sightings which are made
when the vessel is on the designated trackline and observers are actively
searching. “Opportunistic sightings” are
those sightings which occur while travelling between tracklines, additional
sightings made when travelling back to a transect line after photographing a
dolphin group and/or any dolphins noted when transiting between areas or on
passage to transect lines.
[2] The same calculation as implemented in the AFCD
Annual Monitoring Reports was used; [(total ‘on effort” sightings/total track
conducted in Beaufort Sea State 3 or better)*100] for both NEL and NWL
separately and for the two areas combined.
[3] The encounter rate of
March-August 2017 is not compared as a full year data set is not available
[4] Baseline period between September to November 2011
[5] Agriculture,
Fisheries and Conservation Department (AFCD) 2012. Annual Marine Mammal Monitoring Programme April 2011-March 2012. ) The
Agriculture, Fisheries and Conservation Department, Government of the Hong Kong
SAR.
[6] Ove Arup &
Partners Hong Kong Ltd 2009 HZMB – HKBCF & HKLR EIA Report.
24037-REP-125-01 Pages 83-5, 97, 115
[7] Gui, D., Yu, R., He,
X., Tu, Q., Chen, L. and Wu, Y. Bioaccumulation and biomagnification of
persistent organic pollutants in Indo-Pacific humpback dolphins (Sousa chinensis) from the Pearl River
Estuary, China. Chemosphere 114:106-113
[8] Agreement No. MW
01/2003. Hong Kong- Zhuhai- Macao Bridge: Hong Kong Section and the North
Lantau
Highway
Connection: Ecological Baseline Survey. Final 9 Month Ecological Baseline
Survey Report the (p 42 – 43)
[9] Marcotte, D., Hung, S. K., & Caquard, S. 2015. Mapping cumulative impacts on Hong Kong's pink dolphin
population. Ocean & Coastal Management, 109,
51-63
[10]
http://www.mardep.gov.hk/en/publication/pdf/portstat_1_y_d2.pdf