Contract No. HY/2010/02 - Hong Kong-Zhuhai-Macao Bridge
 Hong Kong Boundary Crossing Facilities – Reclamation Works
Impact Monitoring Schedule for April 2012
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr
                        Impact Water Quality Monitoring 
    24-hour TSP Impact Water Quality      Impact Water Quality      Mid-ebb: 13:13
    1-hour TSP Monitoring     Monitoring     Mid-flood: 19:47
    Noise Mid-ebb: 10:42     Mid-ebb: 11:55        
    Mid-flood: 16:13   Mid-flood: Cancelled *   24-hour TSP
            1-hour TSP
                   
8-Apr 9-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr
          Impact Water Quality Monitoring   
    Impact Water Quality      Impact Water Quality      Mid-flood: 11:06  
    Monitoring     Monitoring     Mid-ebb: 18:27  
  Mid-flood: 8:06   Mid-flood: 9:23      
  Mid-ebb: 14:40   Mid-ebb: 16:21   24-hour TSP  
                    1-hour TSP    
              Noise  
15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr
      24-hour TSP  
    Impact Water Quality      Impact Water Quality  1-hour TSP Impact Water Quality     
    Monitoring     Monitoring Noise Monitoring    
    Mid-ebb: 10:33     Mid-ebb: 11:43   Mid-ebb: Cancelled *    
  Mid-flood: 15:45   Mid-flood: 17:31 Dolphin  Mid-flood: Cancelled *  
            Survey    
22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr
  Impact Water Quality    Impact Water Quality Monitoring     
    Monitoring     Mid-flood: 8:16     Impact Water Quality     
    Mid-ebb: 14:10     Mid-ebb: 15:14     Monitoring    
    Mid-flood: 20:55           Mid-flood: 9:09    
      24-hour TSP   Mid-ebb: 16:36  
    Dolphin    1-hour TSP        
    Survey   Noise          
29-Apr 30-Apr          
  Impact Water Quality Monitoring           
    Mid-flood: 12:52                
    Mid-ebb: 19:53                
                     
  24-hour TSP          
    1-hour TSP              
    Noise                
Remarks: *  Scheduled monitoirng was cancelled due to adverse weather condition and safety reasons.
Contract No. HY/2010/02 - Hong Kong-Zhuhai-Macao Bridge
 Hong Kong Boundary Crossing Facilities – Reclamation Works
Tentative Impact Monitoring Schedule for May 2012 (Ver. 1)
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
    1-May 2-May 3-May 4-May 5-May
             
    Dolphin  Impact Water Quality    Impact Water Quality   
    Survey Monitoring Monitoring 24-hour TSP
      Mid-ebb: 10:06     Mid-ebb: 11:29 1-hour TSP
          Mid-flood: 15:54     Mid-flood: 17:55    
                     
6-May 7-May 8-May 9-May 10-May 11-May 12-May
          Impact Water Quality Monitoring   
  Impact Water Quality    Impact Water Quality  Dolphin  Mid-flood: 9:56  
  Monitoring   Monitoring Survey Mid-ebb: 17:01  
  Mid-flood: 6:59     Mid-flood: 8:21          
    Mid-ebb: 13:41     Mid-ebb: 15:18     24-hour TSP    
                    1-hour TSP    
                    Noise    
                           
13-May 14-May 15-May 16-May 17-May 18-May 19-May
             
  Impact Water Quality    Impact Water Quality    Impact Water Quality   
  Monitoring   Monitoring 24-hour TSP Monitoring  
    Mid-ebb: 8:58     Mid-ebb: 10:35 1-hour TSP Mid-ebb: 11:44    
    Mid-flood: 14:02     Mid-flood: 16:24 Noise Mid-flood: 18:06    
                           
20-May 21-May 22-May 23-May 24-May 25-May 26-May
      Impact Water Quality Monitoring       
  Impact Water Quality    Mid-flood: 7:23   Impact Water Quality   
  Monitoring   Mid-ebb: 14:25   Monitoring  
    Mid-ebb: 13:19             Mid-flood: 8:28    
    Mid-flood: 20:12     24-hour TSP     Mid-ebb: 15:37    
            1-hour TSP            
            Noise            
                           
27-May 28-May 29-May 30-May 31-May    
             
  Impact Water Quality    Impact Water Quality       
  Monitoring 24-hour TSP Monitoring      
    Mid-flood: 10:58 1-hour TSP Mid-ebb: 8:31            
    Mid-ebb: 17:58 Noise Mid-flood: 14:13            
                           
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)