Hong Kong Boundary Crossing Facilities – Reclamation Works
 Impact Monitoring Schedule for February 2013
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
                      1-Feb   2-Feb
             
              Impact Water Quality  24-hour TSP
                  Monitoring 1-hour TSP
                Mid-Flood 10:15    
                Mid-Ebb 16:18    
                       
                       
                Mid-Ebb 16:18    
                       
  3-Feb   4-Feb   5-Feb   6-Feb   7-Feb   8-Feb   9-Feb
               
    Impact Water Quality    Impact Water Quality    Impact Water Quality   
    Monitoring   Monitoring   Monitoring  
    Mid-Flood 12:25     Mid-Ebb 10:00   Mid-Ebb 11:56    
    Mid-Ebb 19:35     Mid-Flood 14:51   Mid-Flood 17:01    
                       
                24-hour TSP    
                1-hour TSP    
                Noise    
                         
  10-Feb   11-Feb   12-Feb   13-Feb   14-Feb   15-Feb   16-Feb
               
    Impact Water Quality    Impact Water Quality  24-hour TSP Impact Water Quality   
    Monitoring   Monitoring 1-hour TSP Monitoring  
    Mid-Flood 8:25     Mid-Flood 9:20 Noise Mid-Flood 10:03    
    Mid-Ebb 14:02     Mid-Ebb 15:13   Mid-Ebb 16:24    
                Dolphin         
                Survey Dolphin     
                Survey    
                           
  17-Feb   18-Feb   19-Feb   20-Feb   21-Feb   22-Feb   23-Feb
               
    Impact Water Quality    Impact Water Quality    Impact Water Quality   
    Monitoring   Monitoring   Monitoring  
    Mid-Flood 11:31     Mid-Flood 9:41 Dolphin  Mid-Ebb 11:14    
    Mid-Ebb 19:28     Mid-Ebb 22:09 Survey Mid-Flood 16:22    
                       
            24-hour TSP   Dolphin     
            1-hour TSP   Survey    
            Noise        
                       
  24-Feb   25-Feb   26-Feb   27-Feb   28-Feb        
               
    Impact Water Quality  24-hour TSP Impact Water Quality       
    Monitoring 1-hour TSP Monitoring    
    Mid-Ebb 12:49 Noise Mid-Flood 8:06          
    Mid-Flood 18:37     Mid-Ebb 13:56          
                         
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)             
 Hong Kong Boundary Crossing Facilities – Reclamation Works
Tentative Impact Monitoring Schedule for March 2013
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
                      1-Mar   2-Mar
             
              Impact Water Quality   
                  Monitoring  
              Mid-Flood 9:02    
                       
                Mid-Ebb 15:10    
                       
  3-Mar   4-Mar   5-Mar   6-Mar   7-Mar   8-Mar   9-Mar
               
    Impact Water Quality    Impact Water Quality    Impact Water Quality  24-hour TSP
    Monitoring   Monitoring   Monitoring 1-hour TSP
    Mid-Flood 10:48     Mid-Flood 13:07   Mid-Ebb 11:00    
    Mid-Ebb 17:46     Mid-Ebb 20:42   Mid-Flood 16:03    
                       
    24-hour TSP              
    1-hour TSP              
    Noise              
                         
  10-Mar   11-Mar   12-Mar   13-Mar   14-Mar   15-Mar   16-Mar
               
    Impact Water Quality    Impact Water Quality    Impact Water Quality   
    Monitoring   Monitoring   Monitoring  
    Mid-Ebb 13:02   Mid-Ebb 14:04   Mid-Flood 8:47    
    Mid-Flood 18:43   Mid-Flood 20:11   Mid-Ebb 15:11    
                       
                24-hour TSP    
                1-hour TSP    
                    Noise    
  17-Mar   18-Mar   19-Mar   20-Mar   21-Mar   22-Mar   23-Mar
               
    Impact Water Quality  Dolphin  Impact Water Quality  24-hour TSP Impact Water Quality   
    Monitoring Survey Monitoring 1-hour TSP Monitoring  
    Mid-Flood 10:01   Mid-Flood 6:53 Noise Mid-Ebb 10:11    
    Mid-Ebb 17:15   Mid-Ebb 19:38   Mid-Flood 14:48    
                   
    Dolphin               
    Survey                      
  24-Mar   25-Mar   26-Mar   27-Mar   28-Mar   29-Mar   30-Mar
               
    Impact Water Quality    Impact Water Quality  Dolphin  Impact Water Quality   
    Monitoring   Monitoring Survey Monitoring  
    Mid-Ebb 11:51   Mid-Ebb 12:57   Mid-Flood 7:54    
    Mid-Flood 17:44   Mid-Flood 19:13   Mid-Ebb 14:11    
                     
        24-hour TSP          
        1-hour TSP          
          Noise            
                         
            Dolphin           
            Survey                  
  31-Mar                        
               
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)             
 Hong Kong Boundary Crossing Facilities – Reclamation Works
 Impact Monitoring Schedule for March 2013
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
                      1-Mar   2-Mar
             
              Impact Water Quality   
                  Monitoring  
              Mid-Flood 9:02    
                       
                       
                       
                Mid-Ebb 15:10    
                       
  3-Mar   4-Mar   5-Mar   6-Mar   7-Mar   8-Mar   9-Mar
               
    Impact Water Quality    Impact Water Quality    Impact Water Quality  24-hour TSP
    Monitoring   Monitoring   Monitoring 1-hour TSP
    Mid-Flood 10:48     Mid-Flood 13:07   Mid-Ebb 11:00    
    Mid-Ebb 17:46     Mid-Ebb 20:42   Mid-Flood 16:03    
                       
    24-hour TSP              
    1-hour TSP              
    Noise              
                         
  10-Mar   11-Mar   12-Mar   13-Mar   14-Mar   15-Mar   16-Mar
               
    Impact Water Quality    Impact Water Quality    Impact Water Quality   
    Monitoring   Monitoring   Monitoring  
    Mid-Ebb 13:02   Mid-Ebb 14:04   Mid-Flood 8:47    
    Mid-Flood 18:43   Mid-Flood 20:11   Mid-Ebb 15:11    
                       
                24-hour TSP    
                1-hour TSP    
                    Noise    
  17-Mar   18-Mar   19-Mar   20-Mar   21-Mar   22-Mar   23-Mar
               
    Impact Water Quality  Dolphin  Impact Water Quality  24-hour TSP Impact Water Quality   
    Monitoring Survey Monitoring 1-hour TSP Monitoring  
    Mid-Flood 10:01   Mid-Flood 6:53 Noise Mid-Ebb 10:11    
    Mid-Ebb 17:15   Mid-Ebb 19:38   Mid-Flood 14:48    
                   
    Dolphin               
    Survey                
  24-Mar   25-Mar   26-Mar   27-Mar   28-Mar   29-Mar   30-Mar
               
    Impact Water Quality    Impact Water Quality  Dolphin  Impact Water Quality   
    Monitoring   Monitoring Survey Monitoring  
    Mid-Ebb 11:51   Mid-Ebb 12:57   Mid-Flood 7:54    
    Mid-Flood 17:44   Mid-Flood 19:13   Mid-Ebb 14:11    
                     
        24-hour TSP          
        1-hour TSP          
          Noise            
                         
            Dolphin           
            Survey            
  31-Mar                        
               
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)             
 Hong Kong Boundary Crossing Facilities – Reclamation Works
Tentative Impact Monitoring Schedule for April 2013
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
      1-Apr   2-Apr   3-Apr   4-Apr   5-Apr   6-Apr
               
    Impact Water Quality  Dolphin  Impact Water Quality    Impact Water Quality   
    Monitoring Survey Monitoring     Monitoring  
    Mid-Flood 9:38   Mid-Flood 11:25     Mid-Ebb 9:51    
    Mid-Ebb 16:30     Mid-Ebb 18:43     Mid-Flood 14:49    
    Mid-Ebb 16:30     Mid-Ebb 18:43     Mid-Flood 14:49    
                         
    Dolphin                   
    Survey                  
                         
  7-Apr   8-Apr   9-Apr   10-Apr   11-Apr   12-Apr   13-Apr
               
    Impact Water Quality    Impact Water Quality    Impact Water Quality   
    Monitoring   Monitoring   Monitoring  
    Mid-Ebb 12:04     Mid-Flood 6:51   Mid-Flood 7:40    
    Mid-Flood 17:51     Mid-Ebb 13:06   Mid-Ebb 14:12    
                         
  14-Apr   15-Apr   16-Apr   17-Apr   18-Apr   19-Apr   20-Apr
               
    Impact Water Quality    Impact Water Quality    Impact Water Quality   
    Monitoring   Monitoring   Monitoring  
    Mid-Flood 8:55   Mid-Flood 9:39   Mid-Flood 7:14    
    Mid-Ebb 15:56   Mid-Ebb 17:23   Mid-Ebb 19:46    
                         
  21-Apr   22-Apr   23-Apr   24-Apr   25-Apr   26-Apr   27-Apr
               
    Impact Water Quality  Dolphin  Impact Water Quality    Impact Water Quality   
    Monitoring Survey Monitoring   Monitoring  
    Mid-Ebb 10:47   Mid-Ebb 11:56   Mid-Flood 6:45    
    Mid-Flood 16:37   Mid-Flood 18:18   Mid-Ebb 13:13    
                     
    Dolphin                 
    Survey                
                       
  28-Apr   29-Apr   30-Apr                
               
    Impact Water Quality           
    Monitoring        
    Mid-Flood 8:37              
    Mid-Ebb 15:28              
                           
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)