Appendix N

Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

Cumulative statistics on Exceedances

 

Total no. recorded in this month

Total no. recorded since project commencement 

1-Hour TSP

Action

-

-

Limit

-

-

24-Hour TSP

Action

-

-

Limit

-

-

Noise

Action

-

-

Limit

-

-

Water Quality

Action

-

-

Limit

-

-

Remarks: Exceedances which are not project-related are not presented in this table.

 

Cumulative statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

Date Received

Subject

Status

Total no. received in this month

Total no. received since project commencement 

Environmental complaints

10 May 2013

A complaint referred to the Contractor by EPD on 10 May 2013 regarding the scattered debris of silt curtain noted at Sha Lo Wan and Tung Chung Bay. Immediate inspection and clean up action was taken by the Contractor.

Closed

1

7

 

23 May 2013

A follow-up complaint referred by EPD was received on 23 May 2013 regarding the oil stain noted near Tung Chung Development Pier for past few months.

Closed

2

8

Notification of summons

-

-

 

0

1

Successful Prosecutions

-

-

-

0

0