Appendix N
Cumulative Statistics on Exceedances, Complaints, Notifications
of Summons and Successful Prosecutions
Cumulative statistics on Exceedances
|
Total
no. recorded in this month
|
Total
no. recorded since project commencement
|
|
1-Hour
TSP
|
Action
|
-
|
-
|
Limit
|
-
|
-
|
|
24-Hour
TSP
|
Action
|
-
|
-
|
Limit
|
-
|
-
|
|
Noise
|
Action
|
-
|
-
|
Limit
|
-
|
-
|
|
Water
Quality
|
Action
|
-
|
2
|
Limit
|
-
|
3
|
|
Dolphin
Monitoring
|
Action
|
-
|
-
|
Limit
|
-
|
-
|
Remarks: Exceedances
which are not project-related are not presented in this table.
Cumulative statistics on Exceedances, Complaints,
Notifications of Summons and Successful Prosecutions
|
Date Received
|
Subject
|
Status
|
Total no. received
in this month
|
Total no. received since
project commencement
|
Environmental
complaints
|
15 April
2015
|
Environmental Protection
Department (EPD) referred a noise complaint to this project on 10 April 2015
and ENPO forwarded the noise complaint to Environmental Team on 15 April
2015. The complaint involves a complainant, who is resident of Caribbean
Coast, Tung Chung and he was disturbed by noise from construction activities
of the HZMB Project during weekends and holidays. After
investigation, there is no adequate information to conclude the observed
noise nuisance is related to this Contract. |
Closed
|
1
|
29
|
Notification of
summons
|
-
|
-
|
-
|
-
|
2
|
Successful
Prosecutions
|
-
|
-
|
-
|
-
|
2
|