TABLE OF
CONTENTS
Page
1.4 Summary
of Construction Works
1.5 Summary
of EM&A Programme Requirements
2.4 Monitoring
Parameters, Frequency and Duration
2.6 Monitoring
Schedule for the Reporting Month
3.4 Monitoring
Parameters, Frequency and Duration
3.6 Monitoring
Schedule for the Reporting Month
4.3 Monitoring
Parameters, Frequency and Duration
4.6 Monitoring
Schedule for the Reporting Month
5.3 Monitoring
Frequency and Conditions
5.4 Monitoring
Methodology and Location
5.6 Monitoring
Schedule for the Reporting Month
6 ENVIRONMENTAL SITE INSPECTION AND AUDIT
6.2 Advice
on the Solid and Liquid Waste Management Status
6.3 Environmental
Licenses and Permits
6.4 Implementation
Status of Environmental Mitigation Measures
6.5 Summary
of Exceedances of the Environmental Quality Performance Limit
6.6 Summary
of Complaints, Notification of Summons and Successful Prosecutions
7.1 Construction
Programme for the Coming Months
7.2 Key
Issues for the Coming Month
7.3 Monitoring
Schedule for the Coming Month
8 ConclusionS AND RECOMMENDATIONS
List of Tables
Table 1.1 Contact
Information of Key Personnel
Table 2.1 Air Quality Monitoring Equipment
Table 2.2 Locations of Impact Air Quality Monitoring Stations
Table 2.3 Air Quality Monitoring Parameters, Frequency and Duration
Table 2.4 Summary of 1-hour TSP Monitoring Results in the Reporting
Period
Table 2.5 Summary of 24-hour TSP Monitoring Results in the Reporting
Period
Table 3.1 Noise Monitoring Equipment
Table 3.2 Locations of Impact Noise Monitoring Stations
Table 3.3 Noise Monitoring Parameters, Frequency and Duration
Table 3.4 Summary of Construction Noise Monitoring Results in the
Reporting Period
Table 4.1 Water Quality Monitoring Equipment
Table 4.2 Impact Water Quality Monitoring Parameters and Frequency
Table 4.3 Impact Water Quality Monitoring Stations
Table 4.4 Laboratory Analysis for Suspended Solids
Table 4.5 Summary of Water Quality Exceedances
Table 5.1 Dolphin Monitoring Equipment
Table 5.2 Impact Dolphin Monitoring Line Transect Co-ordinates
(Provided by AFCD)
Table 5.3 Impact Dolphin Monitoring Survey Effort Summary, Effort by Area and Beaufort Sea State
Table 5.4 Impact Dolphin Monitoring Survey Details February 2016
Table 5.5 The Encounter Rate of Number of Dolphin Sightings & Total
Number of Dolphins per Area^
Table 6.1 Summary of Environmental Licensing and Permit Status
Figures
Figure 1 General
Project Layout Plan
Figure
2 Impact
Air Quality and Noise Monitoring Stations and Wind
Station
Figure
3 Impact
Water Quality Monitoring Stations
Figure
4 Impact
Dolphin Monitoring Line Transect Layout Map
Figure 5 Impact
Dolphin Monitoring Survey Efforts and Sightings in February
2016
Figure 6 Environmental
Complaint Handling Procedures
List of Appendices
Appendix A Project
Organization for Environmental Works
Appendix B Three Month
Rolling Construction Programmes
Appendix C Implementation
Schedule of Environmental Mitigation Measures (EMIS)
Appendix D Summary of Action
and Limit Levels
Appendix E Calibration Certificates of
Monitoring Equipments
Appendix F EM&A Monitoring Schedules
Appendix
G Impact Air
Quality Monitoring Results and their Graphical Presentation
Appendix H Meteorological Data for Monitoring
Periods on Monitoring Dates in February 2016
Appendix
I Impact
Construction Noise Monitoring Results and their Graphical Presentation
Appendix J Impact
Water Quality Monitoring Results and
their Graphical Presentation
Appendix
K Impact
Dolphin Monitoring Survey Sighting Summary
Appendix M Monthly Summary of Waste Flow Table
This report documents
the findings of EM&A works conducted in the period between 1 and 29 February 2016. As informed by the Contractor, major
activities in the reporting period were:-
-
Conforming Sloping Seawalls
-
Rubble Mound Seawall
-
Rock fill
-
Maintenance of silt curtain & silt
screen at sea water intake of HKIA
Land-base
-
Surcharge removal & laying
-
Deep Cement Mixing
-
Installations of Precast Culverts
except sloping outfalls
-
Maintenance works of Site Office at
Works Area WA2
-
Maintenance works of Public Works
Regional Laboratory at Works Area WA3
-
Maintenance of Temporary Marine Access
at Works Area WA2
A summary of
monitoring and audit activities conducted in the reporting period is listed
below:
24-hour
Total Suspended Particulates (TSP) monitoring |
5 sessions |
1-hour
TSP monitoring |
5 sessions |
Noise monitoring |
5
sessions |
Impact
water quality monitoring |
12 sessions |
Impact
dolphin monitoring |
2
surveys |
Joint
Environmental site inspection |
4 sessions |
For impact
air quality monitoring, no exceedance of 1-Hour TSP or 24-Hour TSP was recorded
at all monitoring stations in the reporting month.
Breaches of Action and Limit Levels for Water Quality
Complaint,
Notification of Summons and Successful Prosecution
No
complaint, notification of summons or prosecution was received in the reporting
period.
Reporting Change
Variation
of Environmental Permit (VEP-497/2016) was made on 18 February 2016 by the
Project and it was approved by EPD on 25 February 2016.
Future Key
Issues
Key
issues to be considered in the coming month included:
-
Site runoff should be properly
collected and treated prior to discharge;
-
Minimize loss of sediment from filling
works;
-
Regular review and maintenance of silt
curtain systems, drainage systems and desilting facilities;
-
Exposed surfaces/soil stockpiles should
be properly treated to avoid generation of silty surface run-off during
rainstorm;
-
Regular review and maintenance of wheel
washing facilities provided at all site entrances/exits;
-
Conduct regular inspection of various
working machineries and vessels within works areas to avoid any dark smoke
emission;
-
Suppress dust generated from work
processes with use of bagged cements, earth movements, excavation activities,
exposed surfaces/soil stockpiles and haul road traffic;
-
Quieter powered mechanical equipment
should be used;
-
Provision of proper and effective noise
control measures for operating equipment and machinery on-site, such as
erection of movable noise barriers or enclosure for noisy plants;
-
Closely check and replace the sound
insulation materials regularly;
-
Better scheduling of construction works
to minimize noise nuisance;
-
Properly store and label oil drums and
chemical containers placed on site;
-
Proper chemicals, chemical wastes and
wastes management;
-
Maintenance works should be carried out
within roofed, paved and confined areas;
-
Collection and segregation of
construction waste and general refuse on land and in the sea should be carried
out properly and regularly; and
-
Proper protection and regular
inspection of existing trees, transplanted/retained trees.
-
Control night-time lighting and glare
by hooding all lights.
-
Regular review and provide maintenance
to dust control measures such as sprinkler system.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Engineer¡¦s
Representative (ER) (Ove Arup & Partners Hong Kong Limited) |
Chief
Resident Engineer |
Paul Appleton |
3698 5889 |
2698 5999 |
IEC
/ ENPO (Ramboll
Environ Hong Kong Limited) |
Independent
Environmental Checker |
Raymond
Dai |
3465 2888 |
3465 2899 |
Environmental
Project Office Leader |
Y. H. Hui |
3547 2133 |
3465 2899 |
|
Contractor (China
Harbour Engineering Company Limited) |
Environmental
Officer |
Louie Chan |
3693 2254 |
2578 0413 |
24-hour
Hotline |
Alan C.C.
Yeung |
9448 0325 |
-- |
|
ET
(AECOM Asia Company Limited) |
ET Leader |
Echo
Leong |
3922 9280 |
2317 7609 |
Marine-base
-
Conforming Sloping Seawalls
-
Rubble Mound Seawall
-
Rock fill
-
Maintenance of silt curtain & silt
screen at sea water intake of HKIA
Land-base
-
Surcharge removal & laying
-
Deep Cement Mixing
-
Installations of Precast Culverts
except sloping outfalls
-
Maintenance works of Site Office at
Works Area WA2
-
Maintenance works of Public Works
Regional Laboratory at Works Area WA3
-
Maintenance of Temporary Marine Access
at Works Area WA2
- All monitoring parameters;
- Monitoring schedules for the reporting
month and forthcoming month;
- Action and Limit levels for all
environmental parameters;
- Event / Action Plan;
- Environmental mitigation measures, as
recommended in the Project EIA reports; and
- Environmental requirement in contract
documents.
Table 2.1 Air Quality
Monitoring Equipment
Equipment |
Brand and Model |
Portable direct reading dust meter (1-hour TSP) |
Sibata Digital Dust Monitor (Model No. LD-3 and LD-3B) |
High Volume Sampler |
Tisch Environmental Mass Flow Controlled Total
Suspended Particulate (TSP) High Volume Air Sampler (Model No. TE-5170) |
Table 2.2 Locations
of Impact Air Quality Monitoring Stations
Monitoring
Station |
Location |
Description |
AMS2 |
Tung Chung Development Pier |
Rooftop of the premise |
AMS3B |
Site Boundary of Site Office Area at Works Area WA2 |
On ground at the
area boundary |
AMS6* |
Dragonair/CNAC (Group)
Building |
On ground at
boundary of the premise |
AMS7 |
Hong Kong SkyCity Marriott Hotel |
On ground at
boundary of the premise |
#Remarks:
Reference is made to EPD conditional approval of the omission of air monitoring
station (AMS 6) for the Contract. The omission will be effective on 19 November
2012.
Table
2.3 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency
and Duration |
1-hour TSP |
Three
times every 6 days while the highest dust impact was expected |
24-hour TSP |
Once
every 6 days |
(a)
The HVS was
installed in the vicinity of the air sensitive receivers. The following criteria were considered
in the installation of the HVS.
(i)
A horizontal
platform with appropriate support to secure the sampler against gusty wind was
provided.
(ii)
No two samplers
should be placed less than 2 meters apart.
(iii)
The distance
between the HVS and any obstacles, such as buildings, was at least twice the
height that the obstacle protrudes above the HVS.
(iv)
A minimum of
2 meters separation from walls, parapets and penthouse for rooftop sampler.
(v)
A minimum of 2 meters
separation from any supporting structure, measured horizontally is required.
(vi)
No furnace
or incinerator flues nearby.
(vii)
Airflow
around the sampler was unrestricted.
(viii)
Permission
was obtained to set up the samplers and access to the monitoring stations.
(ix)
A secured
supply of electricity was obtained to operate the samplers.
(x)
The sampler
was located more than 20 meters from any dripline.
(xi)
Any wire
fence and gate, required to protect the sampler, did not obstruct the
monitoring process.
(xii)
Flow control
accuracy was kept within ¡Ó2.5% deviation over 24-hour sampling period.
(b)
Preparation
of Filter Papers
(i)
Glass fibre filters, G810 were labelled and sufficient filters
that were clean and without pinholes were selected.
(ii)
All filters
were equilibrated in the conditioning environment for 24 hours before weighing.
The conditioning environment temperature was around 25 ¢XC and not variable by
more than ¡Ó3 ¢XC; the relative humidity (RH) was < 50% and not variable by
more than ¡Ó5%. A convenient working RH was 40%.
(iii)
All filter
papers were prepared and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited
laboratory and has comprehensive quality assurance and quality control programmes.
(c)
Field
Monitoring
(i)
The power
supply was checked to ensure the HVS works properly.
(ii)
The filter
holder and the area surrounding the filter were cleaned.
(iii)
The filter
holder was removed by loosening the four bolts and a new filter, with stamped
number upward, on a supporting screen was aligned carefully.
(iv)
The filter
was properly aligned on the screen so that the gasket formed an airtight seal
on the outer edges of the filter.
(v)
The swing
bolts were fastened to hold the filter holder down to the frame. The pressure applied was sufficient to
avoid air leakage at the edges.
(vi)
Then the
shelter lid was closed and was secured with the aluminum strip.
(vii)
The HVS was
warmed-up for about 5 minutes to establish run-temperature conditions.
(viii)
A new flow
rate record sheet was set into the flow recorder.
(ix)
On site
temperature and atmospheric pressure readings were taken and the flow rate of
the HVS was checked and adjusted at around 1.1 m3/min,
and complied with the range specified in the updated EM&A Manual (i.e.
0.6-1.7 m3/min).
(x)
The
programmable digital timer was set for a sampling period of 24 hrs, and the starting time, weather condition and the
filter number were recorded.
(xi)
The initial
elapsed time was recorded.
(xii)
At the end
of sampling, on site temperature and atmospheric pressure readings were taken
and the final flow rate of the HVS was checked and recorded.
(xiii)
The final
elapsed time was recorded.
(xiv)
The sampled
filter was removed carefully and folded in half length
so that only surfaces with collected particulate matter were in contact.
(xv)
It was then
placed in a clean plastic envelope and sealed.
(xvi)
All
monitoring information was recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem
(HK) Pty Ltd. for analysis.
(d)
Maintenance
and Calibration
(i)
The HVS and
its accessories were maintained in good working condition, such as replacing
motor brushes routinely and checking electrical wiring to ensure a continuous
power supply.
(ii)
5-point
calibration of the HVS was conducted using TE-5025A Calibration Kit prior to
the commencement of baseline monitoring. Bi-monthly 5-point calibration of the
HVS will be carried out during impact monitoring.
(iii)
Calibration
certificate of the HVSs are provided in Appendix E.
(a)
Measuring
Procedures
The measuring procedures of the 1-hour dust meter were in accordance
with the Manufacturer¡¦s Instruction Manual as follows:-
(i)
Turn the
power on.
(ii)
Close the
air collecting opening cover.
(iii)
Push the
¡§TIME SETTING¡¨ switch to [BG].
(iv)
Push
¡§START/STOP¡¨ switch to perform background measurement for 6 seconds.
(v)
Turn the
knob at SENSI ADJ position to insert the light scattering plate.
(vi)
Leave the
equipment for 1 minute upon ¡§SPAN CHECK¡¨ is indicated in the display.
(vii)
Push
¡§START/STOP¡¨ switch to perform automatic sensitivity adjustment. This
measurement takes 1 minute.
(viii)
Pull out the
knob and return it to MEASURE position.
(ix)
Push the
¡§TIME SETTING¡¨ switch the time set in the display to 3 hours.
(x)
Lower down
the air collection opening cover.
(xi)
Push
¡§START/STOP¡¨ switch to start measurement.
(b)
Maintenance
and Calibration
(i)
The 1-hour
TSP meter was calibrated at 1-year intervals against a continuous particulate
TEOM Monitor, Series 1400ab. Calibration certificates of the Laser Dust Monitors
are provided in Appendix E.
(ii)
1-hour
validation checking of the TSP meter against HVS is carried out on half-year
basis at the air quality monitoring
locations.
Table 2.4 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS2 |
76 |
70-80 |
374 |
500 |
AMS3B |
76 |
71-80 |
368 |
500 |
AMS7 |
77 |
72-81 |
370 |
500 |
Table 2.5 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS2 |
92 |
57-133 |
176 |
260 |
AMS3B |
68 |
40-103 |
167 |
260 |
AMS7 |
83 |
50-114 |
183 |
260 |
Table 3.1 Noise
Monitoring Equipment
Equipment |
Brand and
Model |
Integrated Sound
Level Meter |
Rion NL-31 & B&K2238 |
Acoustic
Calibrator |
Rion NC-73 & B&K 4231 |
Table 3.2 Locations
of Impact Noise Monitoring Stations
Monitoring
Station |
Location |
Description |
NMS2 |
Seaview Crescent
Tower 1 |
Free-field on the rooftop of the premise |
NMS3B |
Site Boundary of
Site Office Area at Works Area WA2 |
Free-field on ground at the area boundary.
|
Table 3.3 Noise
Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
30-mins measurement at each
monitoring station between 0700 and 1900 on normal weekdays (Monday to
Saturday). Leq, L10 and L90
would be recorded. |
At least
once per week |
(a)
The sound
level meter was set on a tripod at a height of 1.2 m above the ground for
free-field measurements at NMS2. A correction of +3 dB(A)
shall be made to the free field measurements.
(b)
All measurement at NMS3B were free field measurements in the
reporting month at NMS3B. A correction of +3 dB(A)
shall be made to the free field measurements.
(c)
The battery
condition was checked to ensure the correct functioning of the meter.
(d)
Parameters
such as frequency weighting, the time weighting and the measurement time were
set as follows:-
(i)
frequency
weighting: A
(ii)
time
weighting: Fast
(iii)
time measurement: Leq(30-minutes) during non-restricted
hours i.e. 07:00 ¡V 1900 on normal weekdays.
(e)
Prior to and
after each noise measurement, the meter was calibrated using the acoustic
calibrator for 94dB(A) at 1000 Hz. If the difference in the calibration
level before and after measurement was more than 1 dB(A),
the measurement would be considered invalid and repeat of noise measurement
would be required after re-calibration or repair of the equipment.
(f)
During the
monitoring period, the Leq, L10
and L90 were recorded.
In addition, site conditions and noise sources were recorded on a
standard record sheet.
(g)
Noise
measurement was paused during periods of high intrusive noise (e.g. dog
barking, helicopter noise) if possible. Observations were recorded when intrusive
noise was unavoidable.
(h)
Noise
monitoring was cancelled in the presence of fog, rain, wind with a steady speed
exceeding 5m/s, or wind with gusts exceeding 10m/s. The wind
speed shall be checked with a portable wind speed meter capable of measuring
the wind speed in m/s.
(a)
The
microphone head of the sound level meter was cleaned with soft cloth at regular
intervals.
(b)
The meter
and calibrator were sent to the supplier or HOKLAS laboratory to check and
calibrate at yearly intervals.
(c)
Calibration
certificates of the sound level meters and acoustic calibrators are provided in
Appendix E.
Table 3.4 Summary
of Construction Noise Monitoring Results in the Reporting Period
|
Average, dB(A), Leq (30 mins) |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
NMS2 |
67 |
65-69* |
75 |
NMS3B |
66 |
63-69* |
70/65^ |
*+3dB(A) Façade
correction included
^ Daytime noise Limit Level of 70 dB(A) applies to
education institutions, while 65dB(A) applies during school examination period.
Table 4.1 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
Dissolved Oxygen (DO) and Temperature
Meter, Salinity Meter and Turbidity Meter |
YSI Model 6820 |
pH Meter |
YSI Model 6820 or Thermo
Orion 230A+ |
Positioning Equipment |
JRC DGPS 224 Model JLR-4341 with J-NAV 500
Model NWZ4551 |
Water Depth Detector |
Eagle Cuda-168 and Lowrance
x-4 |
Water Sampler |
Kahlsio
Water Sampler (Vertical) 2.2 L with messenger |
Table 4.2 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring Stations |
Parameter, unit |
Frequency |
No. of depth |
Impact Stations: IS5,
IS(Mf)6, IS7, IS8, IS(Mf)9, IS10, IS(Mf)11, IS(Mf)16, IS17 Control/Far Field Stations: CS(Mf)3,
CS(Mf)5, CS4, CS6, CSA Sensitive Receiver Stations: SR3-SR7,
SR10A&SR10B |
¡P
Depth, m ¡P
Temperature, oC ¡P
Salinity, ppt ¡P
Dissolved Oxygen
(DO), mg/L ¡P
DO Saturation, % ¡P
Turbidity, NTU ¡P
pH ¡P
Suspended Solids
(SS), mg/L |
Three times per week during mid-ebb and mid-flood tides
(within ¡Ó 1.75 hour of the predicted time) |
3 (1 m below water surface, mid-depth and 1 m above sea
bed, except where the water depth is less than 6 m, in which case the
mid-depth station may be omitted. Should the water depth be less than 3
m, only the mid-depth station will be monitored). |
Table 4.3 Impact
Water Quality Monitoring Stations
Station |
Description |
East |
North |
IS5 |
Impact
Station (Close to HKBCF construction site) |
811579 |
817106 |
IS(Mf)6 |
Impact
Station (Close to HKBCF construction site) |
812101 |
817873 |
IS7 |
Impact
Station (Close to HKBCF construction site) |
812244 |
818777 |
IS8 |
Impact Station
(Close to HKBCF construction site) |
814251 |
818412 |
IS(Mf)9 |
Impact
Station (Close to HKBCF construction site) |
813273 |
818850 |
IS10 |
Impact
Station (Close to HKBCF construction site) |
812577 |
820670 |
Impact
Station (Close to HKBCF construction site) |
813562 |
820716 |
|
Impact
Station (Close to HKBCF construction site) |
814328 |
819497 |
|
IS17 |
Impact
Station (Close to HKBCF construction site) |
814539 |
820391 |
SR3 |
Sensitive
receivers (San Tau SSSI) |
810525 |
816456 |
SR4(N) |
Sensitive
receivers (Tai Ho) |
814705 |
817859 |
SR5 |
Sensitive
receivers (Artificial Reef in NE Airport) |
811489 |
820455 |
SR6 |
Sensitive
receivers (Sha Chau and Lung Kwu Chau Marine Park) |
805837 |
821818 |
SR7 |
Sensitive
receivers (Tai Mo Do) |
814293 |
821431 |
SR10A |
Sensitive
receivers (Ma Wan FCZ)1 |
823741 |
823495 |
SR10B(N) |
Sensitive
receivers (Ma Wan FCZ)2 |
823683 |
823187 |
Control
Station |
809989 |
821117 |
|
Control
Station |
817990 |
821129 |
|
CS4 |
Control
Station |
810025 |
824004 |
CS6 |
Control
Station |
817028 |
823992 |
CSA |
Control
Station |
818103 |
823064 |
(a)
The in-situ
water quality parameters, viz. dissolved oxygen, temperature, salinity,
turbidity and pH, were measured by multi-parameter meters (i.e. Model YSI 6820
CE-C-M-Y) and pH meter (i.e. Thermo
Orion 230A+) respectively.
(a)
Digital Differential Global Positioning
Systems (DGPS) were used to
ensure that the correct location was selected prior to sample collection.
(b)
Portable,
battery-operated echo sounders were used for the determination of water depth
at each designated monitoring station.
(c)
All in-situ
measurements were taken at 3 water depths, 1 m below
water surface, mid-depth and 1 m above sea bed, except where the water depth
was less than 6 m, in which case the mid-depth station was omitted.
Should the water depth be less than 3 m, only the mid-depth station was
monitored.
(d)
At each
measurement/sampling depth, two consecutive in-situ monitoring (DO
concentration and saturation, temperature, turbidity, pH, salinity) and water
sample for SS. The probes were retrieved out of the water after the first
measurement and then re-deployed for the second measurement. Where the
difference in the value between the first and second readings of DO or
turbidity parameters was more than 25% of the value of the first reading, the
reading was discarded and further readings were taken.
(e)
Duplicate
samples from each independent sampling event were collected for SS measurement.
Water samples were collected using the water samplers and the samples were
stored in high-density polythene bottles. Water samples collected were
well-mixed in the water sampler prior to pre-rinsing and transferring to sample
bottles. Sample bottles were pre-rinsed with the same water samples. The sample
bottles were then be packed in cool-boxes (cooled at 4oC without
being frozen), and delivered to ALS Technichem (HK)
Pty Ltd. for the analysis of suspended solids concentrations. The laboratory
determination work would be started within 24 hours after collection of the
water samples. ALS Technichem (HK) Pty
Ltd. is a HOKLAS accredited laboratory and has comprehensive quality assurance
and quality control programmes. For QA/QC procedures,
one duplicate samples of every batch of 20 samples was analyzed.
(f)
The analysis
method and reporting and detection limit for SS is shown in Table 4.4.
Table 4.4 Laboratory
Analysis for Suspended Solids
Parameters |
Instrumentation |
Analytical Method |
Reporting Limit |
Detection Limit |
Suspended Solid (SS) |
Weighting |
APHA
2540-D |
0.5mg/L |
0.5mg/L |
(g)
Other
relevant data were recorded, including monitoring location / position, time,
water depth, tidal stages, weather conditions and any special phenomena or work
underway at the construction site in the field log sheet for
information.
(a)
All in situ
monitoring instruments would be calibrated and calibrated by ALS Technichem (HK) Pty Ltd. before use and at 3-monthly
intervals throughout all stages of the water quality monitoring programme. Calibration details are provided in Appendix E.
(b)
The
dissolved oxygen probe of YSI 6820 was calibrated by wet bulb method. Before
the calibration routine, the sensor for dissolved oxygen was thermally
equilibrated in water-saturated air. Calibration cup is served as a calibration
chamber and it was loosened from airtight condition before it is used for the
calibration. Calibration at ALS Technichem (HK) Pty
Ltd. was carried out once every three months in a water sample with a known
concentration of dissolved oxygen. The sensor was immersed in the water and
after thermal equilibration, the known mg/L value was keyed in and the
calibration was carried out automatically.
(c)
The
turbidity probe of YSI 6820 is calibrated two times a month. A zero check in
distilled water was performed with the turbidity probe of YSI 6820 once per
monitoring day. The probe will be calibrated with a solution of known NTU at
ALS Technichem (HK) Pty Ltd. once every three months.
Table 4.5 Summary of Water
Quality Exceedances
Exceedance Level |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Total |
||||||
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
||
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS(Mf)6 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS7 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS8 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 (5 FEB 16) |
0 |
1 (5 FEB 16) |
Limit |
0 |
0 |
0 |
0 |
0 |
1 (5 FEB 16) |
0 |
0 |
0 |
1 (5 FEB 16) |
|
IS(Mf)9 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS10 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS(Mf)11 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS(Mf)16 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS17 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR3 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR4(N) |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 (5 FEB 16) |
0 |
1 (5 FEB 16) |
Limit |
0 |
0 |
0 |
0 |
0 |
1 (5 FEB 16) |
0 |
0 |
0 |
1 (5 FEB 16) |
|
SR5 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR6 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR7 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR10A |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR10B (N) |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 (5 FEB 16) |
2 (5 FEB 16) |
|
|
Limit |
0 |
0 |
0 |
0 |
0 |
2 (5 FEB 16) |
0 |
0 |
2 (5 FEB 16) |
Note: S:
Surface; and
M: Mid-depth.
1. In situ
measurement was repeated to confirm findings of the exceedance of turbidity.
2. After considering the above mentioned investigation results,
it appears that it is unlikely that the turbidity and suspended solids
exceedances were attributed to active construction activities of this Contract;
3. IEC, contractor
and ER were informed via email;
4. Monitoring
data, all plant, equipment and Contractor's working methods were checked;
5-7. Since it is considered that the turbidity and suspended
solid exceedances are unlikely to be contract related, as such, actions 5-7
under the EAP are not considered applicable.
Table 5.1 Dolphin
Monitoring Equipment
Equipment |
Model |
Commercially
licensed motor vessel |
15m in length with a 4.5m viewing platform |
Global
Positioning System (GPS) x2 |
Integrated into T7000 Garmin GPS Map 76C |
Computers (T7000 Tablet, Intel Atom)
|
Windows 7/MSO 13 Logger |
Camera |
Nikon D7100 300m 2.8D fixed focus Nikon D90 80-400mm zoom lens |
Laser Rangefinder |
Range Finder Bushnell 1000m |
Marine Binocular x3 |
Nexus 7 x 50 marine binocular with compass and
reticules Fujinon 7 x 50 marine binocular with compass
and reticules |
Table 5.2 Impact
Dolphin Monitoring Line Transect Co-ordinates (Provided by AFCD)
|
HK Grid System |
Long Lat in
WGS84 |
||
ID |
X |
Y |
Long |
Lat |
1 |
804671 |
815456 |
113.870287 |
22.277678 |
1 |
804671 |
831404 |
113.869975 |
22.421696 |
2 |
805475 |
815913 |
113.878079 |
22.281820 |
2 |
805477 |
826654 |
113.877896 |
22.378814 |
3 |
806464 |
819435 |
113.887615 |
22.313643 |
3 |
806464 |
822911 |
113.887550 |
22.345030 |
4 |
807518 |
819771 |
113.897833 |
22.316697 |
4 |
807518 |
829230 |
113.897663 |
22.402113 |
5 |
808504 |
820220 |
113.907397 |
22.320761 |
5 |
808504 |
828602 |
113.907252 |
22.396462 |
6 |
809490 |
820466 |
113.916965 |
22.323003 |
6 |
809490 |
825352 |
113.916884 |
22.367128 |
7 |
810499 |
820880 |
113.926749 |
22.326757 |
7 |
810499 |
824613 |
113.926688 |
22.360464 |
8 |
811508 |
821123 |
113.936539 |
22.328966 |
8 |
811508 |
824254 |
113.936486 |
22.357241 |
9 |
812516 |
821303 |
113.946320 |
22.330606 |
9 |
812516 |
824254 |
113.946279 |
22.357255 |
10* |
813525 |
820827 |
113.956112 |
22.326321 |
10* |
813525 |
824657 |
113.956066 |
22.360908 |
11 |
814556 |
818853 |
113.966155 |
22.304858 |
11 |
814556 |
820992 |
113.966125 |
22.327820 |
12 |
815542 |
818807 |
113.975726 |
22.308109 |
12 |
815542 |
824882 |
113.975647 |
22.362962 |
13 |
816506 |
819480 |
113.985072 |
22.314192 |
13 |
816506 |
824859 |
113.985005 |
22.362771 |
14 |
817537 |
820220 |
113.995070 |
22.320883 |
14 |
817537 |
824613 |
113.995018 |
22.360556 |
15 |
818568 |
820735 |
114.005071 |
22.325550 |
15 |
818568 |
824433 |
114.005030 |
22.358947 |
16 |
819532 |
821420 |
114.014420 |
22.331747 |
16 |
819532 |
824209 |
114.014390 |
22.356933 |
17 |
820451 |
822125 |
114.023333 |
22.338117 |
17 |
820451 |
823671 |
114.023317 |
22.352084 |
18 |
821504 |
822371 |
114.033556 |
22.340353 |
18 |
821504 |
823761 |
114.033544 |
22.352903 |
19 |
822513 |
823268 |
114.043340 |
22.348458 |
19 |
822513 |
824321 |
114.043331 |
22.357971 |
20 |
823477 |
823402 |
114.052695 |
22.349680 |
20 |
823477 |
824613 |
114.052686 |
22.360610 |
21 |
805476 |
827081 |
113.877878 |
22.382668 |
21 |
805476 |
830562 |
113.877811 |
22.414103 |
22 |
806464 |
824033 |
113.887520 |
22.355164 |
22 |
806464 |
829598 |
113.887416 |
22.405423 |
23 |
814559 |
821739 |
113.966142 |
22.334574 |
23 |
814559 |
824768 |
113.966101 |
22.361920 |
Table 5.3 Impact Dolphin Monitoring Survey Effort
Summary, Effort by Area and Beaufort Sea State
Survey |
Date |
Area |
Beaufort |
Effort
(km) |
Total Distance Travelled (km) |
|
02/04/2016 |
NWL |
1 |
23.6 |
108.3 |
|
02/04/2016 |
NWL |
2 |
28.4 |
|
|
02/04/2016 |
NWL |
3 |
10.1 |
|
|
02/05/2016 |
NWL |
3 |
3 |
|
|
02/05/2016 |
NWL |
4 |
6.9 |
|
|
02/05/2016 |
NEL |
1 |
4 |
|
1 |
02/05/2016 |
NEL |
2 |
19.9 |
|
02/05/2016 |
NEL |
3 |
10 |
||
02/05/2016 |
NEL |
4 |
2.4 |
||
2 |
02/18/2016 |
NWL |
1 |
62.5 |
108.3 |
02/19/2016 |
NWL |
1 |
10 |
||
02/19/2016 |
NEL |
1 |
35.8 |
||
TOTAL in FEBRUARY 2016 |
216.6 |
*Remark:
Surveys conduct under Beaufort Sea State 3 or below are considered as under favourable condition.
Table 5.4 Impact Dolphin Monitoring Survey Details February 2016
Date |
Location |
No. Sightings ¡§on effort¡¨ |
No. Sightings ¡§opportunistic¡¨ |
02/04/2016 |
NW L |
2 |
0 |
NEL |
0 |
0 |
|
02/05/2016 |
NW L |
0 |
0 |
NEL |
0 |
0 |
|
02/18/2016 |
NW L |
0 |
0 |
NEL |
0 |
0 |
|
02/19/2016 |
NW L |
0 |
0 |
NEL |
0 |
0 |
|
TOTAL in FEBRUARY
2016 |
2 |
0 |
*Location
indicates which area was being surveyed when the sighting was made. The area
noted does not necessarily indicate where the dolphins were when the sighting
was made.
Table 5.5 The Encounter Rate of Number of Dolphin
Sightings & Total Number of Dolphins per Area^
Encounter Rate of Number of Dolphin Sightings (STG)* |
||||||
Date |
NEL
Track (km) |
NWL
Track (km) |
NEL
Sightings |
NWL
Sightings |
NEL
Encounter Rate |
NWL
Encounter Rate |
4 and 5
Feb 16 |
33.9 |
65.1 |
0 |
2 |
0.0 |
3.1 |
18 and
19 Feb 16 |
35.8 |
72.5 |
0 |
0 |
0.0 |
0.0 |
Encounter Rate of Total Number of
Dolphins (ANI)** |
||||||
Date |
NEL
Track (km) |
NWL
Track (km) |
NEL
Dolphins |
NWL
Dolphins |
NEL
Encounter Rate |
NWL
Encounter Rate |
4 and 5
Feb 16 |
33.9 |
65.1 |
0 |
6 |
0.0 |
9.2 |
18 and
19 Feb 16 |
35.8 |
72.5 |
0 |
0 |
0.0 |
0.0 |
* Encounter Rate of Number of Dolphin Sightings (STG) presents encounter
rates in terms of groups per 100km.
** Encounter Rate of Total Number of Dolphins (ANI) presents encounter
rates in terms of individuals per 100km. And the encounter rate is not
corrected for individuals, calculation may represent double counting.
^The table is
made only for reference to the quarterly STG & ANI, which were adopted for
the Event & Action Plan.
Air
Quality
Noise
Water
Quality
Chemical
and Waste Management
Landscape
and Visual Impact
Others
Table 6.1 Summary of Environmental Licensing and Permit
Status
Statutory
Reference |
License/
Permit |
License or
Permit No. |
Valid
Period |
License/
Permit Holder |
Remarks |
|
From |
To |
|||||
EIAO |
Environmental Permit |
EP-353/2009/J |
25/02/2016 |
N/A |
HyD |
Hong Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong Boundary Crossing
Facilities |
EP-354/2009/D |
13/03/2015 |
N/A |
Tuen Mun ¡V Chek Lap Kok Link (TMCLKL
Southern Landfall Reclamation only) |
|||
APCO |
NA
notification |
-- |
30/12/2011 |
-- |
CHEC |
Works Area
WA2 and WA3 |
APCO |
NA
notification |
-- |
25/07/2014 |
-- |
CHEC |
Works Area
WA1 |
WDO |
Chemical Waste Producer Registration |
5213-951-C1186-30 |
28/10/2015 |
N/A |
CHEC |
Chemical waste produced in Contract HY/2010/02 (WA1) |
WDO |
Chemical Waste Producer Registration |
5213-951-C1186-21 |
30/3/2012 |
N/A |
CHEC |
Chemical waste produced in Contract HY/2010/02 (WA2) |
WDO |
Chemical Waste Producer Registration |
5213-839-C3750-02 |
13/09/2012 |
-- |
CHEC |
Registration as Chemical Waste Producer at TKO 137(FB) |
WDO |
Billing Account for
Disposal of Construction Waste |
7014181 |
05/12/2011 |
N/A |
CHEC |
Waste disposal in Contract HY/2010/02 |
NCO |
Construction
Noise Permit |
GW-RE1214-15 |
20/12/2015 |
19/06/2016 |
CHEC |
Section of
TKO Fill Bank under Contract HY/2010/02 |
NCO |
Construction
Noise Permit |
GW-RS0095-16 |
05/02/2016 |
03/08/2016 |
CHEC |
Reclamation
Works in Contract HY/2010/02 |
-
The oil on sea was observed on 17 Feb 2016 by RSS and
the Contractor. The incident was reported to ET, IEC and RSS.
-
The Contractor organised manpower to identify
the spill source, but the source of oil spill was not identified.
-
The Contractor equipped people involved in the cleanup works with
personal protective equipment such as gloves prior to the removal of any leaked
chemical or chemical waste.
-
Pads and Pillow of the Spill Kit were applied to absorb and remove the
spillage.
Marine-base
-
Conforming Sloping Seawalls
-
Rubble Mound Seawall
-
Rock fill
-
Maintenance of silt curtain & silt
screen at sea water intake of HKIA
Land-base
-
Surcharge removal & laying
-
Deep Cement Mixing
-
Installations of Precast Culverts
except sloping outfalls
-
Maintenance works of Site Office at
Works Area WA2
-
Maintenance works of Public Works
Regional Laboratory at Works Area WA3
-
Maintenance of Temporary Marine Access
at Works Area WA2
*Construction
activities in March 2016 and April 2016 will be changed subject to works progress.
-
Site runoff should
be properly collected and treated prior to discharge;
-
Minimize loss of
sediment from filling works;
-
Regular review and
maintenance of silt curtain systems, drainage systems and desilting facilities;
-
Exposed
surfaces/soil stockpiles should be properly treated to avoid generation of
silty surface run-off during rainstorm;
-
Regular review and
maintenance of wheel washing facilities provided at all site entrances/exits;
-
Conduct regular
inspection of various working machineries and vessels within works areas to
avoid any dark smoke emission;
-
Suppress dust
generated from work processes with use of bagged cements, earth movements,
excavation activities, exposed surfaces/soil stockpiles and haul
road traffic;
-
Quieter powered
mechanical equipment should be used;
-
Provision of
proper and effective noise control measures for operating equipment and
machinery on-site, such as erection of movable noise barriers or enclosure for
noisy plants;
-
Closely check and
replace the sound insulation materials regularly;
-
Better scheduling
of construction works to minimize noise nuisance;
-
Properly store and
label oil drums and chemical containers placed on site;
-
Proper chemicals,
chemical wastes and wastes management;
-
Maintenance works
should be carried out within roofed, paved and confined areas;
-
Collection and
segregation of construction waste and general refuse on land and in the sea
should be carried out properly and regularly; and
-
Proper protection
and regular inspection of existing trees, transplanted/retained trees.
-
Control night-time
lighting and glare by hooding all lights.
-
Regular review and
provide maintenance to dust control measures such as sprinkler system.
Air Quality Impact
l
All working
plants and vessels on site should be regularly inspected and properly
maintained to avoid dark smoke emission.
l All
vehicles should be washed to remove any dusty materials before leaving the
site.
l Haul
roads should be sufficiently dampened to minimize fugitive dust generation.
l Wheel
washing facilities should be properly maintained and reviewed to ensure
properly functioning.
l Temporary
exposed slopes and open stockpiles should be properly covered.
l Enclosure
should be erected for cement debagging, batching and mixing operations.
l
Water spraying should be provided to suppress fugitive dust for any dusty
construction activity.
l Regular
review and provide maintenance to dust control measures such as sprinkler
system.
Construction Noise Impact
l Quieter powered mechanical equipment
should be used as far as possible.
l Noisy operations should be oriented to a
direction away from sensitive receivers as far as possible.
l Proper and effective noise control
measures for operating equipment and machinery on-site should be provided, such
as erection of movable noise barriers, enclosure for noisy plants or enhancement
works to provide sufficient acoustic decoupling measure(s). Closely check
and replace the sound insulation materials regularly
l Vessels and equipment operating should
be checked regularly and properly maintained.
l Noise Emission Label (NEL) shall be affixed
to the air compressor and hand-held breaker operating within works area.
l Acoustic decoupling measures should be properly
implemented for all existing and incoming construction vessels with continuous
and regularly checking to ensure effective implementation of acoustic
decoupling measures.
Water Quality Impact
l
Regular
review and maintenance of silt curtain systems, drainage systems and desilting
facilities in order to make sure they are functioning effectively.
l
Construction
of seawall should be completed as early as possible.
l
Regular
inspect and review the loading process from barges to avoid splashing of
material.
l
Silt, debris
and leaves accumulated at public drains, wheel washing bays and perimeter
u-channels and desilting facilities should be cleaned up regularly.
l
Silty
effluent should be treated/ desilted before discharged. Untreated effluent
should be prevented from entering public drain channel.
l
Proper
drainage channels/bunds should be provided at the site boundaries to
collect/intercept the surface run-off from works areas.
l Exposed slopes and stockpiles should be covered up
properly during rainstorm.
Chemical and Waste Management
l
All types of
wastes, both on land and floating in the sea, should be collected and sorted
properly and disposed of timely and properly. They should be properly stored in
designated areas within works areas temporarily.
l
All chemical
containers, batteries and oil drums should be properly stored and labelled.
l
All plants
and vehicles on site should be properly maintained to prevent oil leakage.
Proper measures,
like drip trays and/or bundings, should be provided
for retaining leaked oil/chemical from plants.
l
All kinds of
maintenance works should be carried out within roofed, paved and confined
areas.
l
All drain
holes of the drip trays utilized within works areas should be properly plugged
to avoid any oil and chemical waste leakage.
l
Oil stains
on soil surface, accumulated oil mixture and empty chemical containers should
be cleared and disposed of as chemical waste.
l
Regular review should be conducted for working barges and patrol boats
to ensure sufficient measures and spill control kits were provided on working
barges and patrol boats to avoid any spreading of leaked oil/chemicals.
Landscape and Visual Impact
l
All existing,
retained/transplanted trees at the works areas should be properly fenced off
and regularly inspected.
l
Control
night-time lighting and glare by hooding all lights.
[1] A noteworthy
observation is to show that either the conduct of the surveys themselves is
affected, i.e., the noted vessel or works impedes the progress or view of the
survey platform. In addition, the vessel or construction works may be different
or additional to that observed previously and further, are of such a nature
that they are a likely to create an impact on the movement or behaviour of the subject of the impact survey, in this
case, the dolphins.