Appendix
J
Cumulative
Statistics on Exceedances, Complaints, Notifications
of Summons and Successful Prosecutions
Cumulative
statistics on Exceedances
|
Total
no. recorded in this month
|
Total
no. recorded since project commencement
|
|
1-Hour TSP
|
Action
|
-
|
-
|
Limit
|
-
|
-
|
|
24-Hour
TSP
|
Action
|
-
|
-
|
Limit
|
-
|
-
|
|
Noise
|
Action
|
-
|
-
|
Limit
|
-
|
-
|
|
Water
Quality
|
Action
|
-
|
-
|
Limit
|
-
|
-
|
Remarks: Exceedances
which are not project-related are not presented in this table.
Cumulative
statistics on Exceedances, Complaints, Notifications
of Summons and Successful Prosecution
|
Date Received
|
Subject
|
Status
|
Total no. received in this month
|
Total no. received since project
commencement
|
Environmental complaints
|
18
Jan 2013
|
EPD referred a complaint from a complainant
on 18 Jan 2013 who advised that turbid water and concrete/cement was arising
from the Hong Kong-Zhuhai-Macao Bridge Hong Kong
Projects to marine water. The source of turbid water and concrete/cement was
not specified by the complainant. After investigation, it could not be concluded whether the
complaint was considered as project related or not. However the Contractor was
reminded to implement necessary mitigation measures. |
Closed
|
1
|
3
|
|
6
Feb13
|
One (1) complaint was referred to the HyD by the Islands District Council (IDC) on the 6
February 2013 regarding a resident from Phase 1 Caribbean Coast who
complained the nuisance brought by construction along Ying Hei Road, Tung
Chung. Complaint investigation was conducted by the HyD
and written reply were subsequently given to IDC by HyD
on 4 March 13. The investigation
results show that the complaint was non-project related. |
Closed
|
1
|
4
|
Notification of summons
|
-
|
-
|
-
|
0
|
0
|
Successful Prosecutions
|
-
|
-
|
-
|
0
|
0
|