Appendix J

Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

Cumulative statistics on Exceedances

 

 

Total no. recorded in this month

Total no. recorded since project commencement 

1-Hour TSP

Action

-

-

Limit

-

-

24-Hour TSP

Action

-

-

Limit

-

-

Noise

Action

-

-

Limit

-

-

Water Quality

Action

-

-

Limit

-

-

Dolphin Monitoring

Action

-

-

Limit

-

-

Remarks: Exceedances which are not project-related are not presented in this table.

 

Cumulative statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

Date Received

Subject

Status

Total no. received in this quarter

Total no. received since project commencement 

Environmental complaints

26 Sept 13

One (1) complaint was logged by the Contractor regarding the leakage from work barges causing water pollution near Tuen Mun Richland Garden received on 26 Sept 13. With refer to the available information such as photo record of the incident cannot indicate that the leakage from work barges was caused by the vessel of this Contract and the complaint could not be concluded as project related.

 

Closed

1

9

1 Nov 13

As informed by the Contractor on 5 Nov 13, a noise complaint received on 14 Sept 13 was referred to the Contractor of HKBCF on 1 Nov 13. The captioned complaint involves noise generated by a tug boat operating near a pier at Tung Chung around 05:55am-06:45am on 14 Sept 13. After investigation, the complaint is considered not likely to be related to the construction works.

Closed

2

10

11 Nov 13

As informed by the Contractor, complaint received from Penta-Ocean – Gitanes Joint Venture (CV/2012/03) mentioned that the formation works of the Contaminated Mud Pit CMP1 to the South of the Brothers (CMP1 of SB) which has been completed in mid-August 2013 and the pit has been commissioned for receiving contaminated marine mud from other projects starting from 16 August 2013. However, it was recently observed that some of the project vessels of HY/2010/02 had berthed within the said pit and those anchorages would likely cause disruption to the underlying contaminated mud and thus induce unfavourable contamination impact to the surrounding marine environment. In this regard, they reminded the contractor to avoid berthing of their vessels within the boundary of CMP1 of SB thereafter for the sake of environmental concern. After investigation, the complaint is considered not likely to be related to the construction works.

Closed

3

11

Notification of summons

-

-

-

-

1

Successful Prosecutions

-

-

-

-

-