Verification by IEC

Certification by ET

 

 



Contract No. HY/2013/01

Hong Kong-Zhuhai-Macao Bridge

Hong Kong Boundary Crossing Facilities ˇV Passenger Clearance Building

 

 

 

 

 

Quarterly EM&A Report No. 17

(Covering the Period from 1 September 2018 to 30 November 2018)

 

17 December 2019

 

Revision 2

 

 

 

 

 

 

 

Main Contractor                                                                                                          Environmental Team 

 

 

 

 

Contents

Executive Summary

1....... Introduction. 7

1.1                          Basic Project Information. 7

1.2                          Project Organisation. 7

1.3                          Construction Programme. 8

1.4                          Construction Works Undertaken During the Reporting Period. 8

2....... EM&A Requirement 9

2.1                          Summary of EM&A Requirements. 9

2.2                          Monitoring Requirements. 13

2.3                          Action and Limit Levels. 13

2.4                          Event Action Plans. 15

2.5                          Mitigation Measures. 15

3....... Environmental Monitoring and Audit 16

3.1                          Air Quality Monitoring Results. 16

3.2                          Noise Monitoring Results. 17

3.3                          Water Quality Monitoring Results. 18

3.4                          Dolphins Monitoring Results. 21

3.5                          Implementation of Environmental Measures. 22

3.6                          Advice on the Solid and Liquid Waste Management Status. 23

3.7                          Environmental Licenses and Permits. 23

4....... Summary of Exceedance, Complaint, Notification of Summons and Successful Prosecution. 24

4.1                          Summary of Exceedance of the Environmental Quality Performance Limit 24

4.2                          Summary of Complaints, Notification of Summons and Successful Prosecution. 25

5....... Comments, Recommendations and Conclusion. 25

5.1                          Comments. 25

5.2                          Recommendations. 25

5.3                          Conclusions. 26

 


 

Figures

Figure 2.1      Location of Air Quality and Noise Monitoring Stations

Figure 2.2     Location of Water Quality Monitoring Stations

Figure 2.3    Impact Dolphins Monitoring Line Transect Layout Map

 

Appendices

Appendix A       Landscape Checklist

Appendix B       Location of Works Areas

Appendix C       Project Organization for Environmental Works

Appendix D       Construction Programme 

Appendix E       Event and Action Plan

Appendix F       Implementation Schedule for Environmental Mitigation Measures (EMIS)

Appendix G       Graphical Plot (Air Quality, Noise and Water Quality) 

Appendix H       Site Audit Findings and Corrective Actions

Appendix I         Waste Flow Table  

Appendix J        Environmental Licenses and Permits  

Appendix K       Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions

Appendix L        Investigation Report

 


Executive Summary

This Quarterly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract HY/2013/01 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) ˇV Passenger Clearance Building (hereafter referred to as ˇ§the Contractˇ¨) (includes the construction works of Contract No. HY/2013/06 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ˇV Automatic Vehicle Clearance Support System within Contract No. HY/2013/01 works area) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to Leighton ˇV Chun Wo Joint Venture (construction works of Contract No. HY/2013/06 was awarded to ATAL Technologies Limited within Contract No. HY/2013/01 works area) (hereafter referred to as ˇ§the Contractorˇ¨) and Atkins China Limited was appointed as the Environmental Team (ET) by the Contractor

The Contract is part of Hong Kong ˇV Zhuhai ˇV Macao Bridge HKBCF which is a ˇ§Designated Projectˇ¨, under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. Site preparation works of the Contract started on 26 September 2014 and the construction works of the Contract commenced on 6 October 2014. The construction works of the Contract No. HY/2013/06 within Contract No. HY/2013/01 works area commenced on 20 February 2018.

Atkins China Limited has been appointed by the Contractor to implement the Environmental Monitoring & Audit (EM&A) programme for the Contract in accordance with the Updated EM&A Manual for HKBCF (Version1.0) and will be providing environmental team services to the Contract.

This is the seventeenth Quarterly EM&A Report for the Contract which summaries findings of the EM&A works during the reporting period from 1 September 2018 to 30 November 2018. (includes the construction works of Contract No. HY/2013/06 within Contract No. HY/2013/01 works area)

Landscape Checklist is shown in Appendix A.

Environmental Monitoring and Audit Progress

The EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0). The air quality, noise, water quality and dolphin monitoring works under Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ˇV Reclamation Works were suspended from 1 September 2017. The ET of Contract No. HY/2013/01 is required and continues the same implementation of environmental monitoring commencing on 1 September 2017. It should be noted that the air quality monitoring station (AMS6) is covered by Contract No. HY/2011/03 Hong Kong-Zhuhai Macao Bridge Hong Kong Link Road ˇV Section between Scenic Hill and HKBCF. Noise monitoring station (NMS3C) and air quality monitoring station (AMS3C) are covered by Contract No. HY/2013/04ˇV Hong Kong-Zhuhai-Macao Bridge HKBCF - Infrastructure Works Stage II (Southern Portion) (since 20 August 2018). Noise monitoring station (NMS2), air quality monitoring station (AMS7B), water quality monitoring and Chinese white dolphin monitoring responsibility under the EM&A programme for the HZMB HKBCF Project has been changed from Contract No. HY/2013/01 to Contract No. HY/2013/04 since 1 October 2018.

A summary of the monitoring activities during the reporting period are listed below:

Monitoring Items

Date

September 2018

October 2018(*)

November 2018(*)

1-hour TSP Monitoring

3, 5, 6, 7, 11, 12, 13, 17, 18, 19, 21, 24, 27 and 28

N/A

N/A

24-hour TSP Monitoring

 3(i), 5, 6, 11, 12, 17, 21, 24(ii), 26(iii), 27 and 28

N/A

N/A

Noise Monitoring

4, 5, 10, 11, 17, 20, 26 and 27

N/A

N/A

Water Quality Monitoring

3, 5, 7, 10, 12(iv), 14, 17(v), 19, 21, 24, 26 and 28

N/A

N/A

Chinese White Dolphin Monitoring

10, 14(vi), 19(vi) and 24(vi)

N/A

N/A

Environmental Site Inspection

5, 12, 19 and 26

5, 10, 18, 24 and 31(**)

N/A(**)

Remark (*): Noise monitoring at station (NMS2), air quality monitoring at station (AMS7B), water quality monitoring and Chinese White Dolphin monitoring responsibility under the EM&A programme for the HZMB HKBCF Project has been changed from Contract No. HY/2013/01 to Contract No. HY/2013/04 since 1 October 2018.

(**): The works area in Hong Kong-Zhuhui-Macao Bridge was handed over to the relevant authorities since 24 October 2018 and the site area was changed to closed area, no site inspection was conducted for the Contract No. HY/2013/01 in November 2018.

(i) 24-hour TSP air quality monitoring at AMS7B on 31 August 2018 was rescheduled to 3 September 2018 due to unstable power supply. (ii)24-hour TSP air quality monitoring at AMS7B on 18 September 2018 was rescheduled to 24 September 2018 due to unstable power supply.

(iii) An additional 24-hour TSP air quality monitoring at AMS7B was conducted on 26 September 2018.

(iv) Due to the typhoon signal was hoisted, the water quality monitoring (mid-ebb tide) on 12 September 2018 was cancelled.

(v) Due to the typhoon signal was hoisted, the water quality monitoring on 17 September 2018 was cancelled.

(vi) Due to the typhoon issue, the dolphins monitoring on 18, 20 and 26 September 2018 were rescheduled to 14, 19 and 24 September 2018.

 

Breaches of Action and Limit Levels :

A summary of environmental exceedances for the reporting period are listed below:

Environmental Monitoring

Parameters

Action Level (AL)(*)

Limit Level (LL)(*)

Sep 2018

Oct 2018

Nov 2018

Sep 2018

Oct 2018

Nov 2018

Air Quality

1-hr TSP

-

-

-

-

-

-

24-hr TSP

-

-

-

-

-

-

Noise

Leq (30 min)

-

-

-

-

-

-

Water Quality

Suspended solids level (SS)

2

1

5

-

-

-

Turbidity level

-

1

-

-

-

-

Dissolved oxygen level (DO)

153

-

-

29

-

-

Dolphin Monitoring

Quarterly Analysis

-

1

Total

162

30

 

Remark(*): Based on the investigation results, all exceedances in September 2018 are found that not related to Contract No. HY/2013/01. The exceedances in October and November 2018 can be referred to the corresponding monthly EM&A Report prepared under Contract No. HY/2013/04.

Implementation of Environmental Measures

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. Potential environmental impacts due to the construction activities were monitored and reviewed.

Complaint Log

There was no complaint received in relation to the environmental impact during reporting period. Notifications of Summons and Successful Prosecutions

There was no notification of summon or prosecution received during this reporting period.

Reporting Change

The entire environmental monitoring responsibility under the EM&A programme for the HZMB HKBCF Project has been changed from Contract No. HY/2013/01 to Contract No. HY/2013/04 since 1 October 2018.

The works area in Hong Kong-Zhuhai-Macao Bridge was handed over to the owner since 24 October 2018.




 

 

1          Introduction

1.1                Basic Project Information

1.1.1      This Quarterly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract HY/2013/01 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ˇV Passenger Clearance Building (hereafter referred to as ˇ§the Contractˇ¨) (includes the construction works of Contract No. HY/2013/06 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ˇV Automatic Vehicle Clearance Support System within Contract No. HY/2013/01 works area) for the Highways Department of Hong Kong Special Administrative Region. The Contract was awarded to Leighton ˇV Chun Wo Joint Venture (construction works of Contract No. HY/2013/06 was awarded to ATAL Technologies Limited within Contract No. HY/2013/01 works area) (hereafter referred to as ˇ§the Contractorˇ¨) and Atkins China Limited was appointed as the Environmental Team (ET) by the Contractor.

1.1.2      The Contract is part of Hong Kong ˇV Zhuhai ˇV Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) which is a ˇ§Designated Projectˇ¨, under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499). An Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. Site preparation work of the Contract started on 26 September 2014 and the construction works of the Contract commenced on 6 October 2014. The construction works of the Contract No. HY/2013/06 within Contract No. HY/2013/01 works area commenced on 20 February 2018. The works areas of the Contract are shown in Appendix B.

1.1.3      This is the seventeenth Quarterly EM&A Report for the Contract which summarizes the audit findings of the EM&A programme during the reporting period from 1 September 2018 to 30 November 2018.

1.2                Project Organisation

1.2.1      The project organization structure and lines of communication with respect to the on-site environmental management structure is shown in Appendix C. The key personnel contact names and numbers are summarized in Table 1.1. 

Table 1.1         Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

For Contract No. HY/2013/01

Engineer or Engineerˇ¦s Representative
(AECOM Asia Co. Ltd.)

Chief Resident Engineer

Malcolm Sage

3958 7330

3468 2076

Environmental Project Office / Independent Environmental Checker
(Ramboll Hong Kong Limited)

Environmental Project Office Leader

Y. H. Hui

3465 2888

3465 2899

Independent Environmental Checker

Raymond Dai

3465 2888

3465 2899

Contractor
(Leighton ˇV Chun Wo Joint Venture)

Project Manager

Owen Leung

9232 5750

3621 0180

Environmental Officer

Stephen Tsang

9686 0787

3621 0180

Environmental Team
(Atkins China Limited)

Environmental Team Leader

Keith Chau

2972 1721

2890 6343

24 hours complaint hotline

---

---

3958 7300

---

For Contract No. HY/2013/06 within Contract No. HY/2013/01 works area

Engineer or Engineerˇ¦s Representative
(AECOM Asia Co. Ltd.)

Chief Registered Architect

Malcolm Sage

3958 7330

3468 2076

Environmental Project Office / Independent Environmental Checker (Ramboll Hong Kong Limited)

Environmental Project Office Leader

Y. H. Hui

3465 2888

3465 2899

Independent Environmental Checker

Raymond Dai

3465 2888

3465 2899

Contractor
(ATAL Technologies Limited)

Site Agent

Mr. Eric Yim

2565 3355

3162 5217

Environmental Officer

Mr. W. Li

2565 3137

3162 5217

Environmental Team
(Atkins China Limited)

Environmental Team Leader

Keith Chau

2972 1721

2890 6343

24 hours complaint hotline

---

---

6509 0375

---

1.3                Construction Programme

1.3.1      A copy of the Contractorˇ¦s construction programme is provided in Appendix D. 

 

1.4                Construction Works Undertaken During the Reporting Period

1.4.1      A summary of the construction activities undertaken during this reporting period is shown below:

For Contract No. HY/2013/01

Land-Based Work and Marine Based work (September and October 2018)

ˇP            According to information from the Contractor, the construction works of Contract No. HY/2013/01 have been completed. The related completion certificate (Ref.: BWLM: TTHK: mlmp:60313494/C1/M15/905/M1422-2018009635T) dated 9 August 2018 was issued by Engineerˇ¦s Representative.

ˇP            Landscape works.

ˇP            Maintenance works.

For Contract No. HY/2013/06 within Contractor No. HY/2013/01 works area (September and October 2018)

ˇP           According to information from Contractor, no construction works will be conducted by Contract No. HY/2013/06 except System Testing and Commissioning at ELV & Sever Room, and Zone E PCB

 

1.4.2      As all the sections under Contract No. HY/2013/01 and HY/2013/06 were handed over to the relevant authorities on 24 October 2018 and the site had been changed to closed area, no construction works undertaken in November 2018.

 

 

2          EM&A Requirement

2.1                Summary of EM&A Requirements

2.1.1      The EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1). The air quality, noise, water quality and dolphin monitoring works under Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ˇV Reclamation Works were suspended from 1 September 2017. The ET of Contract No. HY/2013/01 is required and continues the same implementation of environmental monitoring commencing on 1 September 2017. It should be noted that the air quality monitoring station (AMS 6) is covered by Contract No. HY/2011/03 Hong Kong-Zhuhai Macao Bridge Hong Kong Link Road ˇV Section between Scenic Hill and HKBCF.

2.1.2      The permission to carry out impact air quality monitoring work at AMS7 (Hong Kong SkyCity Marriott Hotel) was not granted after 31 January 2015. The impact air quality monitoring location (AMS7) was relocated to a nearby air sensitive receiver, Chu Kong Air-Sea Union Transportation Co. Ltd. (AMS7A), from 5 February 2015 to 30 December 2015. The alternative location at Chu Kong Air-Sea Union Transportation Co. Ltd. was approved by EPD on 5 February 2015. However, AMS7A was relocated back to its original location (AMS7-Hong Kong SkyCity Marriott Hotel) on 30 December 2015. The relocation of air quality monitoring location, AMS7A, back to AMS7 was approved by EPD on 21 December 2015. The baseline and action/limit level for air quality as derived from the baseline monitoring data recorded at Hong Kong SkyCity Marriott Hotel (AMS7) was adopted for the air quality monitoring location. As the permission to carry out air quality monitoring at Hong Kong SkyCity Marriott Hotel was not granted after the end of January 2018, as such, a proposal for the monitoring location relocated to 3RS Site Office(AMS7B) was justified by the ET Leader for Contract No. HY/2013/01 on 22 January 2018; verified by the IEC on 24 January 2018; and submitted to EPD on 30 January 2018, and the AQM has been carrying out at AMS7B with EPDˇ¦s consent since 6 February 2018.

2.1.3      The air quality and meteorological monitoring station at AMS3B and noise monitoring station at NMS3B have been relocated and renamed as AMS3C and NMS3C respectively. The monitoring stations AMS3C and NMS3C are covered by Contract No. HY/2013/04 ˇV Hong Kong-Zhuhai-Macao Bridge HKBCF - Infrastructure Works Stage II (Southern Portion) since 20 August 2018. The air quality monitoring station AMS2 and AMS7B and noise monitoring station NMS2 are covered by Contract No. HY/2013/04 since 1 October 2018. The ET of the Contract or another ET of the HZMB project is required to conduct air quality stations (AMS2, AMS3C and AMS7B) and noise monitoring stations (NMS2 and NMS3C) are no longer covered under Contract No. HY/2013/04.  

2.1.4      A summary of air and noise monitoring locations are presented in Table 2.1. The location of air quality and noise monitoring stations are shown as in Figure 2.1.

Table 2.1         Summary of Impact EM&A Requirements

Environmental Monitoring

ID

Location Description 

Air Quality

AMS2(2)(3)

Tung Chung Development Pier

AMS3C(1)(3)

Ying Tung Estate Market Rooftop

AMS6(3)

Dragonair/CNAC (Group) Building

AMS7B(2)(3)(4)

3RS Site Office

Noise

NMS2(5)(8)

Seaview Crescent

NMS3C(5)(6)(7)

Ying Tung Estate Refuse Collection Point

Remarks:

(1)    Air quality monitoring at AMS3C has been undertaking by the ET for Contract No. HY/2013/04 since 20 August 2018.

(2)    Air quality monitoring at AMS2 and AMS7B have been undertaking by the ET for Contract No. HY/2013/04 since 1 October 2018.

(3)    The ET of this Contract should conduct impact air quality monitoring at the Air Monitoring Station listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

(4)    The original monitoring location was at Hong Kong SkyCity Marriott Hotel (AMS7). As the permission to carry out air quality monitoring at Hong Kong SkyCity Marriott Hotel was not granted after 31 January 2015, the monitoring location was relocated to Chu Kong Air-Sea Union Transportation Co. Ltd. (AMS7A) from 5 February 2015 to 30 December 2015. The alternative monitoring location at Chu Kong Air-Sea Union Transportation Co. Ltd. was approved by EPD on 5 February 2015. However, AMS7A was relocated back to its original location (AMS7-Hong Kong SkyCity Marriott Hotel) on 30 December 2015. The relocation of air quality monitoring location, AMS7A, back to AMS7 was approved by EPD on 21 December 2015. As the permission to carry out air quality monitoring at Hong Kong SkyCity Marriott Hotel was not granted after the end of January 2018, as such, a proposal for the monitoring location relocated to 3RS Site Office(AMS7B) was justified by the ET Leader for Contract No. HY/2013/01 on 22 January 2018; verified by the IEC on 24 January 2018; and submitted to EPD on 30 January 2018, and the AQM has been carrying out at AMS7B with EPDˇ¦s consent since 6 February 2018.

(5)    The ET of this Contract should conduct impact noise monitoring at the Noise Monitoring Station listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

(6)    Limit Level for schools will be applied for NMS3C. Day time noise Limit Level of 70 dB(A) applies to education institutions, while 65 dB(A) applies during the school examination period.

(7)    Noise Monitoring at NMS3C has been undertaking by the ET for Contract No. HY/2013/04 since 20 August 2018.

(8)    Noise Monitoring at NMS2 has been undertaking by the ET for Contract No. HY/2013/04 since 1 October 2018.

 

2.1.5      The water quality monitoring works for the Contract before 1 September 2017 are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ˇV Reclamation Works. The water quality works under Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ˇV Reclamation Works were suspended from 1 September 2017. Water quality monitoring works are covered by the ET of Contract No. HY/2013/01 from 1 September 2017 to 30 September 2018. The ET of Contract No. HY/2013/04 are required and continues the same implementation of water quality monitoring works commencing since 1 October 2018. A total of twenty-one stations (nine Impact Stations (IS), seven Sensitive Receiver Stations (SR) and five Control/Far Field Stations (CS)) are covered by the current EM&A programme.

2.1.6      The water quality monitoring stations at CS(Mf)3 (Coordinate: 809989E, 821117N), IS10 (Coordinate: 812577E, 820670N) and SR5 (811489E, 820455N) have been occupied by the marine work of a designated project - Expansion of Hong Kong International Airport into a Three-Runway System (3RS Project). The alternative water quality monitoring station at CS(Mf)3(N) (Coordinate: 808814E, 822355N), IS10(N) (Coordinate: 812942E, 820881N) and SR5(N) (812569E, 8201475N) were justified and verified by the ET Leader for Contract No. HY/2010/02 and the IEC respectively on 24 March 2017 and it was approved by EPD on 12 May 2017.

2.1.7      There are construction activities of work bridge near SR4(N), the water quality monitoring team were unable to access station SR4(N) in September 2018 due to safety reason. The water quality monitoring for SR4(N) were conducted at the nearest location of SR4(N) as much as practical.

2.1.8      The impact water quality monitoring requirements are detailed in the monthly EM&A Reports prepared by Contract No. HY/2013/04 since 1 October 2018. If exceedance(s) at these survey transect(s) is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

2.1.9      Table 2.2 and Figure 2.2 show the locations of water quality monitoring stations.

Table 2.2         Impact Water Quality Monitoring Stations

Station

Description

East

North

IS5

Impact Station (Close to HKBCF construction site)

811579

817106

IS(Mf)6

Impact Station (Close to HKBCF construction site)

812101

817873

IS7

Impact Station (Close to HKBCF construction site)

812244

818777

IS8

Impact Station (Close to HKBCF construction site)

814251

818412

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

IS10

Impact Station (Close to HKBCF construction site)

812577

820670

IS10(N)*

Impact Station (Close to HKBCF construction site)

812942

820881

IS(Mf)11

Impact Station (Close to HKBCF construction site)

813562

820716

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS17

Impact Station (Close to HKBCF construction site)

814539

820391

SR3(N) ^

Sensitive receivers (San Tau SSSI)

810689

816591

SR4(N)@

Sensitive receivers (Tai Ho)

814705

817859

SR5

Sensitive receivers (Artificial Reef in NE Airport)

811489

820455

SR5(N)*

Sensitive receiver (Artificial Reef in NE Airport)

812569

821475

SR6

Sensitive receivers (Sha Chau and Lung Kwu Chau Marine Park)

805837

821818

SR7

Sensitive receivers (Tai Mo Do)

814293

821431

SR10A(N) ^

Sensitive receivers (Ma Wan FCZ) 1

823644

823484

SR10B(N2) ^

Sensitive receivers (Ma Wan FCZ) 2

823689

823159

CS(Mf)3

Control Station

809989

821117

CS(Mf)3(N)*

Control Station

808814

822355

CS(Mf)5

Control Station

817990

821129

CS4

Control Station

810025

824004

CS6

Control Station

817028

823992

CSA

Control Station

818103

823064

Remarks:

* Alternative water quality monitoring stations at CS(Mf)3(N), SR5(N) and IS10(N) were justified and verified by the ET Leader for Contract No. HY/2010/02 and the IEC respectively on 24 March 2017 and it was approved by EPD on 12 May 2017.

^ Alternative water quality monitoring stations at SR3, SR10A and SR10B(N) were justified by the ET Leader on 8 November 2017 and verified by IEC on 13 November 2017; and submitted to EPD on 29 November 2017 and it was approved by EPD on 22 December 2017.

@ There are construction activities of work bridge near SR4(N). the water quality monitoring team were unable to access station SR4(N) in September 2018 due to safety reason. The water quality monitoring for SR4(N) were conducted at the nearest location of SR4(N) as much as practical.



2.1.10    The dolphin monitoring works for the Contract before 1 September 2017 are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ˇV Reclamation Works. The dolphin monitoring works under Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ˇV Reclamation Works were suspended from 1 September 2017. The ET of Contract No. HY/2013/01 (September 2018) and the ET of Contract No. HY/2013/04 (since 1 October 2018) are required to conduct dolphin monitoring at the twenty-four transects. The monitoring requirements are detailed in the corresponding monthly EM&A Reports prepared by Contract No. HY/2013/01 and Contract No. HY/2013/04.  

2.1.11    The dolphin monitoring should adopt line-transect vessel survey method. The survey follows pre-set and fixed transect lines in the two areas defined by AFCD as: Northeast Lantau survey area; and Northwest Lantau survey area. The change of transect lines 2, 3, 4, 5, 6 and 7 and new vessel-based transect line 24 for dolphin monitoring have been proposed due to the marine work of a designated project - Expansion of Hong Kong International Airport into a Three-Runway System (3RS Project). It was justified and verified by the ET Leader for Contract No. HY/2010/02 and the IEC respectively on 24 March 2017 and it was approved by EPD on 12 May 2017.

2.1.12    The co-ordinates for the transect lines showing the transect lines and are shown in Table 2.3 and Figure 2.3 shows the layout map.

 

Table 2.3          Impact Dolphin Monitoring Line Transect Co-ordinates

Transect ID

                       HK Grid System

 

East

North

 

1*

804671

815456

 

804671

831404

 

2

805476

820800

 

805476

826654

 

3

806464

821150

 

806464

822911

 

4

807518

821500

 

807518

829230

 

5

808504

821850

 

808504

828602

 

6

809490

822150

 

809490

825352

 

7

810499

822000

 

810499

824613

 

8*

811508

821123

 

811508

824254

 

9*

812516

821303

 

812516

824254

 

10*

813525

820827

 

813525

824657

 

11#

814556

818853

 

814556

820992

 

12

815542

818807

 

815542

824882

 

13

816506

819480

 

816506

824859

 

14

817537

820220

 

817537

824613

 

15

818568

820735

 

818568

824433

 

16

819532

821420

 

819532

824209

 

17

820451

822125

 

820451

823671

 

18

821504

822371

 

821504

823761

 

19

822513

823268

 

822513

824321

 

20

823477

823402

 

823477

824613

 

21

805476

827081

 

805476

830562

 

22

806464

824033

 

806464

829598

 

23

814559

821739

 

814559

824768

 

24

805476

815900

 

805476

819100

 

Remarks:

(a)       * Due to the presence of deployed silt curtain systems at the site boundaries of the Contract, some of the transect lines shown in Figure 5.1 could not be fully surveyed during the regular survey. Transect 10 is reduced from 6.4km to approximately 3.6km in length due to the HKBCF construction site. Therefore the total transect length for both NEL and NWL combined is reduced to approximately 108km

(b)       # Coordinates for transect lines 1, 8, 9 and 11 have been updated in respect to the Proposal for Alteration of Transect Line for Dolphin Monitoring approved by EPD on 19 August 2015.

(c)       The change of transect lines 2, 3, 4, 5, 6 and 7 and new vessel-based transect line 24 for dolphin monitoring have been proposed due to the marine work of a designated project-Expansion of Hong Kong International Airport into a Three-Runway System (3RS Project). It was justified and verified by the ET Leader for Contract No. HY/2010/02 and the IEC respectively on 24 March 2017 and it was approved by EPD on 12 May 2017.

(d)       Due to marine work of the Expansion of Hong Kong International Airport into a Three-Runway System (3RS Project), original transect lines of dolphin monitoring 2, 3, 4, 5, 6 and 7 are enclosed by works boundary of 3RS Project. Alternative dolphin monitoring transect lines 2, 3,4, 5, 6, 7 and 24 are adopted starting from 17 May 2017 to replace the original transect lines.

 

2.2                Monitoring Requirements

2.2.1      The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the corresponding monthly EM&A report for Contract No. HY/2013/01 (September 2018 of reporting period) and Contract No. HY/2013/04 (October and November 2018 of reporting period).

2.3                Action and Limit Levels

2.3.1      The Action and Limit Level for 1-hr TSP and 24-hr TSP are provided in Table 2.4 and Table 2.5, respectively.

Table 2.4         Action and Limit Levels for 1-hour TSP

Monitoring Station

Action Level, µg/m3

Limit Level, µg/m3

AMS2 ˇV Tung Chung Development Pier

374

500

AMS3C - Ying Tung Estate Market Rooftop AMS3C - Ying Tung Estate Market Rooftop

368

AMS6 ˇV Dragonair/CNAC (Group) Building (HKIA)

360

AMS7B ˇV 3RS Site Office

370


Table 2.5        Action and Limit Levels for 24-hour TSP

Monitoring Station

Action Level, µg/m3

Limit Level, µg/m3

AMS2 ˇV Tung Chung Development Pier

176

260

AMS3C - Ying Tung Estate Market Rooftop

167

AMS6 ˇV Dragonair/CNAC (Group) Building (HKIA)

173

AMS7B ˇV 3RS Site Office

183

 

2.3.2      The Action and Limit Levels for construction noise are defined in Table 2.6.

Table 2.6         Action and Limit Level for Construction Noise

Monitoring Station

Time Period

Action Level

Limit Level

NMS2

0700-1900 hours on normal weekdays

When one documented complaint is received.

75 dB(A)

NMS3C(i)

70/65 dB(A)(*)

Notes :     

If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.

(i) Noise monitoring at NMS3C has been undertaking by the ET for Contract No. HY/2013/04 since 20 August 2018.

(*) Reduce to 70 dB(A) for schools and 65 dB(A) during school examination period. The Limit Level for schools will be applied for NMS3C. Daytime noise Limit Level of 70 dB(A) applies to education institutions, while 65 dB(A) applies during the school examination period.

 

2.3.3      The Action and Limit Levels for water quality are provided in Table 2.7.

Table 2.7 Action and Limit Levels for Water Quality

Parameters

Action

Limit

DO in mg L-1

(Surface, Middle & Bottom)

Surface and Middle

5.0

Bottom

4.7

Surface and Middle

4 .2 (except 5 mg/L for FCZ)

Bottom

3.6

SS in mg L-1 (depth-averaged) at all monitoring stations and control stations

23.5 and 120% of upstream control station's SS at the same tide of the same day*

34.4 and 130% of upstream control station's SS at the same tide of the same day and 10mg/L for WSD Seawater intakes*

Turbidity in NTU

(depth-averaged)

27.5 and 120% of upstream control station's turbidity at the same tide of the same day*

47.0 and 130% of upstream control station's turbidity at the same tide of the same day*

* Remarks:  Reference is made to EPD approval of adjustment of water quality assessment criteria issued and became
            effective on 18 February 2013.
 
Notes:     1. ˇ§depth-averagedˇ¨ is calculated by taking the arithmetic means of reading of all three depths.

2.For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

3.For turbidity, SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

4.All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

5.The 1%-ile of baseline data for dissolved oxygen (surface and middle) and dissolved oxygen (bottom) are 4.2 mg/L and 3.6 mg/L respectively.

2.3.4      The Action and Limit Levels for Chinese White Dolphin Monitoring are provided in Table 2.8 and Table 2.9, respectively.

Table 2.8 Action and Limit Levels for Chinese White Dolphin Monitoring - Approach to Define Action Level (AL) and Limit Level (LL)

 

North Lantau Social Cluster

 

NEL

NWL

Action Level

(STG  < 70% of baseline) &

(ANI  < 70% of baseline)

(STG  < 70% of baseline) &

(ANI  < 70% of baseline)

Limit Level

[(STG  < 40% of baseline) & (ANI  < 40% of baseline)] AND

[ (STG  < 40% of baseline) & (ANI  < 40% of baseline)]

 

Table 2.9 Derived Value of Action Level (AL) and Limit Level (LL) for Chinese White Dolphin Monitoring

 

North Lantau Social Cluster

 

NEL

NWL

Action Level

(STG < 4.2) & (ANI < 15.5)

(STG < 6.9) & (ANI < 31.3)

Limit Level

[(STG < 2.4) & (ANI <8.9)] AND [ (STG < 3.9) & (ANI < 17.9)]

 

 

2.4                Event Action Plans

2.4.1      The Event Actions Plans for air quality, noise, water quality and dolphin monitoring are provided in Appendix E.

2.5                Mitigation Measures

2.5.1      Environmental mitigation measures for the Contract were recommended in the approved EIA Report. Appendix F lists the recommended mitigation measures and the implementation status.


3          Environmental Monitoring and Audit

3.1                Air Quality Monitoring Results

3.1.1      In accordance with the Contract Specific EM&A Manual, impact 1-hour Total Suspended Particulates (TSP) monitoring was conducted for at least three times every 6 days, while impact 24-hour TSP monitoring was carried out for at least once every 6 days at the 4 monitoring stations (AMS2, AMS3C, AMS6 and AMS7B).

3.1.2      Confirmed by ENPO, the air quality monitoring (both 1-hr and 24-hr TSP) have been undertaking by the ET for Contract No. HY/2013/04 at AMS3C respectively since 20 August 2018. The responsible contract for the air quality monitoring at station AMS7B under the EM&A programme for the HZMB HKBCF Project has been changed from Contract No. HY/2013/01 to Contract No. HY/2013/04 since 1 October 2018.

3.1.3      The graphical plots of the monitoring results are presented in Appendix G. No specific trend of the monitoring results or existence of persistent pollution source was noted.

3.1.4      A severe typhoon Mangkhut was marked in September 2018, the month was wetter than usual which mainly attributing to the rainfall brought by Mangkhut. The weather in Hong Kong was mainly cloudy with occasional showers in early of September 2018. Meanwhile, the weather in Hong Kong became windy with squally heavy rain in mid of September 2018. The weather in Hong Kong became generally fine, slight cooler and dry towards the end of September 2018. Under the influence of the northeast monsoon, the local weather was generally fine and dry and a few rain patches in early of October 2018. The associated northeast monsoon brought some rain and slightly cooler weather in mid of October 2018. Meanwhile, under the influence of anticyclone aloft and the dry northeast monsoon, the weather in Hong Kong became brighter with sunny and very dry with cooler in end of October 2018. Under the combined effect of the northeast monsoon and tropical cyclone Yutu, it was windy and dry with sunny periods in Hong Kong on the first day of November. While local winds subsided gradually, it was mainly cloudy with a few rain patches in next few days. The weather of Hong Kong turned cloudier and windier with light rain in mid of November 2018. The weather of Hong Kong became appreciably cooler and drier with sunny periods in end of November 2018.

3.1.5      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A Reports (for September 2018 to November 2018) prepared by Contract No. HY/2011/03.

3.1.6      The number of exceedances recorded during the reporting period are presented in the Table 3.1. The monitoring results for 1-hour and 24-hour are summarized in Table 3.2 and Table 3.3 respectively.

Table 3.1         Summary of number of exceedances for 1-hr and 24-hr TSP Monitoring

Monitoring Station

September 2018

Action Level

Limit Level

AMS2

-

-

AMS3C

-

-

AMS6

-

-

AMS7B

-

-

 

 

 

 

 


Remark: Confirmed by ENPO, the air quality monitoring (both 1-hr and 24-hr TSP) have been undertaking by the ET for Contract No. HY/2013/04 at AMS3C respectively since 20 August 2018. The responsible contract for the air quality monitoring at station AMS7B under the EM&A programme for the HZMB HKBCF Project has been changed from Contract No. HY/2013/01 to Contract No. HY/2013/04 since 1 October 2018.

 

 

Table 3.2         Summary of 1-hour TSP Monitoring Results in September 2018

Reporting month

Monitoring Station

Average (Łgg/m3)

Range (Łgg/m3)

 

Action Level (Łgg/m3)

Limit Level (Łgg/m3)

September 2018

AMS2

38

11 ˇV 57

374

500

AMS3C

40

26 ˇV 75

368

AMS7B

39

11 - 65

370

 

 

 

 

 

 

 

 

 

 

Remark: Confirmed by ENPO, the air quality monitoring (1-hr TSP) have been undertaking by the ET for Contract No. HY/2013/04 at AMS3C respectively since 20 August 2018. The responsible contract for the air quality monitoring at station AMS7B under the EM&A programme for the HZMB HKBCF Project has been changed from Contract No. HY/2013/01 to Contract No. HY/2013/04 since 1 October 2018.

Table 3.3         Summary of 24-hour TSP Monitoring Results in September 2018

Reporting month

Monitoring Station

Average (Łgg/m3)

Range (Łgg/m3)

 

Action Level (Łgg/m3)

Limit Level (Łgg/m3)

September 2018

AMS2

50

33 ˇV 79

176

260

AMS3C

44

32 ˇV 67

167

AMS7B

76

44 - 170

183

 

 

 

 

 

 

 

 

 

 

Remark: Confirmed by ENPO, the air quality monitoring (24-hr TSP) have been undertaking by the ET for Contract No. HY/2013/04 at AMS3C respectively since 20 August 2018. The responsible contract for the air quality monitoring at station AMS7B under the EM&A programme for the HZMB HKBCF Project has been changed from Contract No. HY/2013/01 to Contract No. HY/2013/04 since 1 October 2018.

 

3.1.7      No Action and Limit Level exceedances of 1-hour TSP were recorded at AMS2, AMS3C and AMS7B in September 2018.

3.1.8      No Action and Limit Level exceedances of 24-hour TSP were recorded at AMS2, AMS3C and AMS7B in September 2018.

3.1.9      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

3.1.10    The monitoring results for 1-hr TSP level and 24-hr TSP level at AMS2, AMS3C and AMS7B are reported in the monthly EM&A report that prepared by Contract No. HY/2013/04 since October 2018. No air quality exceedances were recorded at stations AMS2, AMS3C and AMS7B by the ET of the Contract No. HY/2013/04 in October and November 2018.

3.2                Noise Monitoring Results

3.2.1      In accordance with the Contract Specific EM&A Manual, impact noise monitoring was conducted for at least once per week during the construction phase of the Contract.

3.2.2      The graphical plots of the monitoring results are presented in Appendix G. No specific trend of the monitoring results or existence of persistent pollution source was noted.

3.2.3      The number of exceedances recorded during the reporting period are presented in the Table 3.4. The monitoring results for construction noise are summarized in Table 3.5.



Table 3.4         Summary of number of exceedances for Impact Noise Monitoring

Monitoring Station (2)

September 2018

Action Level

Limit Level

NMS2(1)

-

-

NMS3C(1)(2)

-

-

 

 

 

 

 

 

 

 

 

 

 

Remark: (1) Confirmed by ENPO, the noise monitoring (NMS3C) have been undertaking by the ET for Contract No. HY/2013/04 at NMS3C respectively since 20 August 2018. The responsible contract for the noise monitoring at station NMS2 under the EM&A programme for the HZMB HKBCF Project has been changed from Contract No. HY/2013/01 to Contract No. HY/2013/04 since 1 October 2018.

(2) The Limit Level for schools will be applied for NMS3C. Daytime noise Limit Level of 70 dB(A) applies to education institutions, while 65 dB(A) applies during the school examination period.

 

  Table 3.5     Summary of Construction Noise Monitoring Results in September 2018

Reporting

month

Monitoring Station

Average, dB(A)
Leq (30 mins)

Range, dB(A)
Leq (30 mins)

Limit Level, dB(A)
Leq (30 mins)

September 2018

NMS2(1)

65

63 - 66

75

NMS3C(1) (2)

70

69- 70

70/65

 

 

 

 

 

 

 

 

Remark: (1) Confirmed by ENPO, the noise monitoring (NMS3C) have been undertaking by the ET for Contract No. HY/2013/04 at NMS3C respectively since 20 August 2018. The responsible contract for the noise monitoring at station NMS2 under the EM&A programme for the HZMB HKBCF Project has been changed from Contract No. HY/2013/01 to Contract No. HY/2013/04 since 1 October 2018.

(2) The Limit Level for schools will be applied for NMS3C. Daytime noise Limit Level of 70 dB(A) applies to education institutions, while 65 dB(A) applies during the school examination period.

 

3.2.4      No Action and Limit Level exceedances of noise monitoring were recorded at NMS2 and NMS3C in September 2018.

3.2.5      The event and action plan is provided in Appendix E.

3.2.6      The monitoring results for NMS2 and NMS3C are reported in the monthly EM&A Reports that prepared by Contract No. HY/2013/04 since October 2018. No noise exceedances were recorded at stations NMS2 and NMS3C by the ET of the Contract No. HY/2013/04 in October and November 2018.

3.3                Water Quality Monitoring Results

3.3.1      Impact water quality monitoring was carried out to ensure that any deterioration of water quality was detected, and that timely action was taken to rectify the situation. For impact water quality monitoring, measurement were taken in accordance with the Contract Specific EM&A Manual.

3.3.2      For impact water quality monitoring, number of exceedances recorded during reporting period at each impact station are summarised in Table 3.6.

3.3.3      No Action Level and Limit Level exceedances of turbidity were recorded at mid-ebb tide and mid-flood tide in September 2018. One Action Level exceedance of turbidity was recorded at mid-ebb tide on 24 October 2018 by the ET of Contract No. HY/2013/04 while no Action Level exceedance of turbidity at mid-flood tide was recorded by the ET of Contract No. HY/2013/04 during October and November 2018. No Limit Level exceedances of turbidity was recorded by the ET of Contract No. HY/2013/04 during October and November 2018.

3.3.4      73 Action Level exceedances of dissolved oxygen were recorded at mid-ebb tide on 3, 5, 7, 10 and 14 September 2018 while 80 Action Level exceedances of dissolved oxygen were recorded at mid-flood tide on 3, 5, 7, 10, 12, 14 and 28 September 2018. 12 Limit Level exceedances of dissolved oxygen were recorded at mid-ebb tide on 3, 5, 10 and 14 September 2018 while 17 Limit Level exceedances of dissolved oxygen were recorded at mid-flood tide on 3, 5, 7, 10, 12, 14 and 28 September 2018. No Action Level and Limit Level exceedances of dissolved oxygen were recorded at mid-ebb tide and mid-flood tide by the ET of Contract No. HY/2013/04 during October and November 2018.

3.3.5      Two Action Level exceedances of suspended solid were recorded at mid-flood tide on 10 and 12 September 2018. No Action Level exceedances of suspended solid were recorded at mid-ebb tide and no Limit Level exceedances of suspended solid in September 2018. Six Action Level exceedances of suspended solid were recorded at mid-flood tide on 10 October 2018 and 23 and 26 November 2018 by the ET of Contract No. HY/2013/04 during October and November 2018. No Action Level exceedances of suspended solid were recorded at mid-ebb tide and no Limit Level exceedances of suspended solid was recorded by the ET of Contract No. HY/2013/04 during October and November 2018.

Table 3.6         Summary of Water Quality Exceedances

Station

Exceedance Level

DO (S&M)

DO (Bottom)

Turbidity

SS

Ebb

Flood

Ebb

Flood

Ebb

Flood

Ebb

Flood

IS5

Action Level

2018-09-03;

2018-09-05;

2018-09-07

2018-09-03;

2018-09-10;

2018-09-12

2018-09-03;

2018-09-07;

2018-09-10

2018-09-03;

2018-09-05;

2018-09-10

 

 

 

 

Limit Level

2018-09-10

 

2018-09-05

 

 

 

 

 

IS(Mf)6

Action Level

2018-09-10

2018-09-10;

2018-09-12

 

 

 2018-10-24

 

 

 

Limit Level

 

 

 

 

 

 

 

 

IS7

Action Level

2018-09-10

2018-09-10;

2018-09-12

 

 

 

 

 

 

Limit Level

 

 

 

 

 

 

 

 

IS8

Action Level

2018-09-10

2018-09-10;

2018-09-12

2018-09-03;

2018-09-07;

2018-09-10

2018-09-10;

2018-09-12

 

 

 

 

Limit Level

 

 

 

 

 

 

 

 

IS(Mf)9

Action Level

2018-09-10

2018-09-12

2018-09-03;

2018-09-05;

2018-09-10

2018-09-10;

2018-09-12

 

 

 

 

Limit Level

 

2018-09-10

 

 

 

 

 

 

IS10(N)

Action Level

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10

2018-09-03;

2018-09-05;

2018-09-10;

2018-09-12

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10;

2018-09-12

 

 

 

2018-11-23

Limit Level

 

 

 

 

 

 

 

 

IS(Mf)11

Action Level

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10

2018-09-03;

2018-09-10;

2018-09-12

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10;

2018-09-12

 

 

 

2018-11-23

Limit Level

 

 

 

 

 

 

 

 

IS(Mf)16

Action Level

2018-09-03;

2018-09-14

2018-09-10;

2018-09-12

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10

2018-09-03;

2018-09-10;

2018-09-12

 

 

 

 

Limit Level

2018-09-10

 

 

 

 

 

 

 

IS17

Action Level

2018-09-03;

2018-09-05;

2018-09-14

2018-09-03;

2018-09-12;

2018-09-14

2018-09-03;

2018-09-10;

2018-09-14

2018-09-07;

2018-09-10;

2018-09-12

 

 

 

 

Limit Level

2018-09-10

2018-09-10

2018-09-05

 

 

 

 

 

SR3(N)

Action Level

2018-09-10

2018-09-10;

2018-09-12

2018-09-07;

2018-09-10

2018-09-10;

2018-09-12

 

 

 

 

Limit Level

 

 

 

 

 

 

 

 

SR4(N)

Action Level

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10

2018-09-10;

2018-09-12;

2018-09-14

2018-09-03;

2018-09-07;

2018-09-10

2018-09-03;

2018-09-10;

2018-09-12

 

 

 

 

Limit Level

 

 

2018-09-05

 

 

 

 

 

SR5(N)

Action Level

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10

2018-09-10;

2018-09-12

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10

2018-09-05;

2018-09-10;

2018-09-12

 

 

 

 

Limit Level

 

 

 

 

 

 

 

 

SR6

Action Level

2018-09-07

2018-09-05;

2018-09-07;

2018-09-12

2018-09-07;

2018-09-10

2018-09-03;

2018-09-07;

2018-09-10;

2018-09-12

 

 

 

2018-09-10;

2018-09-12;

2018-10-10

Limit Level

2018-09-10

2018-09-03;

2018-09-10

 

 

 

 

 

 

SR7

Action Level

2018-09-03;

2018-09-10

2018-09-10;

2018-09-12

2018-09-10

2018-09-10;

2018-09-12

 

 

 

2018-11-23

Limit Level

 

 

 

 

 

 

 

 

SR10A(N)

Action Level

 

 

2018-09-05;

2018-09-10

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10;

2018-09-12

 

 

 

2018-11-26

Limit Level

2018-09-10;

2018-09-14

2018-09-03;

2018-09-05;

2018-09-07;

2018-09-10;

2018-09-12;

2018-09-14

 

 

 

 

 

 

SR10B
(
N2)

Action Level

 

 

2018-09-03;

2018-09-05;

2018-09-10

2018-09-03;

2018-09-05;

2018-09-12;

2018-09-14

 

 

 

2018-11-26

Limit Level

2018-09-03;

2018-09-10;

2018-09-14

2018-09-03;

2018-09-05;

2018-09-10;

2018-09-12;

2018-09-14;

2018-09-28

 

2018-09-10

 

 

 

 

Total

Action Level

32

34

41

46

1

0

0

6

162

Limit Level

9

16

3

1

0

0

0

0

29

 

3.3.6      As confirmed by the Contractor, no marine transportation and marine-based work was conducted when water quality monitoring was conducted in September 2018 for Contract No. HY/2013/01. Therefore, it is concluded that the exceedances were not related the Contract. The detailed investigation results of these exceedances recorded are shown in Appendix L. For investigations and the findings with respect to October and November 2018 can be referred to the corresponding monthly EM&A Report prepared for Contract No. HY/2013/04.

 

 

3.4                Dolphins Monitoring Results

Data Analysis

3.4.1      Distribution Analysis ˇV The line-transect survey data was integrated with the Geographic Information System (GIS) in order to visualize and interpret different spatial and temporal patterns of dolphin distribution using sighting positions. Location data of dolphin groups were plotted on map layers of Hong Kong using a desktop GIS (ArcView© 3.1) to examine their distribution patterns in details. The dataset was also stratified into different subsets to examine distribution patterns of dolphin groups with different categories of group sizes, young calves and activities.

3.4.2      Encounter rate analysis ˇV Encounter rates of Chinese white dolphins (number of on-effort sightings per 100 km of survey effort, and total number of dolphins sighted on-effort per 100 km of survey effort) were calculated in NEL and NWL survey areas in relation to the amount of survey effort conducted during each month of monitoring survey. Dolphin encounter rates were calculated in two ways for comparisons with the HZMB baseline monitoring results as well as to AFCD long-term marine mammal monitoring results.

3.4.3      Notably, throughout the present quarterly progress report, the previous monitoring data obtained under Contract No. HY/2011/03 (i.e. HKLR03) are referenced and compared to the present quarterly monitoring data collected for the HKBCF-PCB project, as both HKBCF-PCB and HKLR03 project data was collected by the same HKCRP survey team, to ensure 100% consistency in monitoring methodology including vessel survey method as well as various analyses. On the contrary, the previous monitoring data collected under HZMB HKBCF-Reclamation Works contract (Contract No. HY/2010/02) was from a different survey team that have adopted different survey methodology (e.g. two observers and one data recorder under HKBCF-Reclamation Works contract, as compared to one primary observer and one data recorder under HKLR03 and HKBCF-PCB contract). Therefore, the previous HKLR03 monitoring data was adopted for comparison with the present quarterly findings. This approach was also adopted in previous four verified quarterly reports (i.e. EM&A quarterly reports no. 13th, 14th, 15th and 16th).

3.4.4      Firstly, for the comparison with the HZMB baseline monitoring results, the encounter rates were calculated using primary survey effort alone, and only data collected under Beaufort 3 or below condition would be used for encounter rate analysis. The average encounter rate of sightings (STG) and average encounter rate of dolphins (ANI) were deduced based on the encounter rates from six events during the present quarter (i.e. six sets of line-transect surveys in North Lantau), which was also compared with the one deduced from the six events during the baseline period (i.e. six sets of line-transect surveys in North Lantau). 

3.4.5      Secondly, the encounter rates were calculated using both primary and secondary survey effort collected under Beaufort 3 or below condition as in AFCD long-term monitoring study. The encounter rate of sightings and dolphins were deduced by dividing the total number of on-effort sightings (STG) and total number of dolphins (ANI) by the amount of survey effort for the present quarterly period.

3.4.6      Quantitative grid analysis on habitat use ˇV To conduct quantitative grid analysis of habitat use, positions of on-effort sightings of Chinese White Dolphins collected during the quarterly impact phase monitoring period were plotted onto 1-km2 grids among NWL and NEL survey areas on GIS.  Sighting densities (number of on-effort sightings per km2) and dolphin densities (total number of dolphins from on-effort sightings per km2) were then calculated for each 1 km by 1 km grid with the aid of GIS. Sighting density grids and dolphin density grids were then further normalized with the amount of survey effort conducted within each grid.  The total amount of survey effort spent on each grid was calculated by examining the survey coverage on each line-transect survey to determine how many times the grid was surveyed during the study period.  For example, when the survey boat traversed through a specific grid 50 times, 50 units of survey effort were counted for that grid.  With the amount of survey effort calculated for each grid, the sighting density and dolphin density of each grid were then normalized (i.e. divided by the unit of survey effort). 

3.4.7      The newly-derived unit for sighting density was termed SPSE, representing the number of on-effort sightings per 100 units of survey effort. In addition, the derived unit for actual dolphin density was termed DPSE, representing the number of dolphins per 100 units of survey effort.  Among the 1-km2 grids that were partially covered by land, the percentage of sea area was calculated using GIS tools, and their SPSE and DPSE values were adjusted accordingly. The following formulae were used to estimate SPSE and DPSE in each 1-km2 grid within the study area:

SPSE = ((S / E) x 100) / SA%

DPSE = ((D / E) x 100) / SA%

 

where       S = total number of on-effort sightings

D = total number of dolphins from on-effort sightings

E = total number of units of survey effort

SA% = percentage of sea area

3.4.8      Behavioural analysis ˇV When dolphins were sighted during vessel surveys, their behaviour was observed. Different activities were categorized (i.e. feeding, milling/resting, traveling, socializing) and recorded on sighting datasheets. This data was then input into a separate database with sighting information, which can be used to determine the distribution of behavioural data with a desktop GIS. Distribution of sightings of dolphins engaged in different activities and behaviours would then be plotted on GIS and carefully examined to identify important areas for different activities of the dolphins. 

3.4.9      Ranging pattern analysis ˇV Location data of individual dolphins that occurred during the 3-month impact phase monitoring period were obtained from the dolphin sighting database and photo-identification catalogue. To deduce home ranges for individual dolphins using the fixed kernel methods, the program Animal Movement Analyst Extension, was loaded as an extension with ArcView© 3.1 along with another extension Spatial Analyst 2.0. Using the fixed kernel method, the program calculated kernel density estimates based on all sighting positions, and provided an active interface to display kernel density plots. The kernel estimator then calculated and displayed the overall ranging area at 95% UD level.

Summary of Survey Effort and Dolphin Sightings

3.4.10    During the period of September 2018 to November 2018, six sets of systematic line-transect vessel surveys were conducted for the HKBCF project to cover all transect lines in NWL and NEL survey areas twice per month. The monitoring results for dolphin monitoring in September 2018 are reported in the monthly EM&A Reports (September 2018) prepared for Contract No. HY/2013/01.

3.4.11    The impact dolphin monitoring results at all transects in October and November 2018 are reported in the Monthly EM&A Reports prepared by Contract No. HY/2013/04. The quarterly analysis of dolphin monitoring data for September 2018 to November 2018 is summarized in the quarterly EM&A report (October 2018 to November 2018) prepared for Contract No. HY/2013/04.

Action Level / Limit Level Exceedance

3.4.12    There was one Limit Level exceedance of dolphin monitoring for the quarterly monitoring data (between September 2018 ˇV November 2018).

3.4.13    The details of the dolphin monitoring exceedances can be referred to in the Quarterly EM&A reports under Contract No. HY/2013/04.



3.5                Implementation of Environmental Measures

3.5.1      In response to the site audit findings, the Contractor carried out corrective actions. Details of site audit findings and the corrective actions during the reporting period are presented in Appendix H.

3.5.2      All exposed site area has been paved expect planting area, thus, watering of exposed spoil was not required during reporting period.

3.5.3      The marine traffic records and geographical plots of all the vessels tracks will be submitted by the Contractor to ER, ETL and IEC/ENPO within 3 weeks after the reporting month. As informed by Contractor, there was no marine transportation since 30 January 2018.

3.5.4      Regarding the implementation of dolphin monitoring and protection measures (i.e. implementation of Dolphin Watching Plan, Dolphin Exclusion Zone and Silt Curtain integrity check), regular checking were conducted by the dolphin watcher(s) / dolphin observer(s) within the works area to ensure no dolphin was trapped by the enclosed silt curtain systems. No dolphin spotted within the enclosed silt curtain systems was reported and recorded during the reporting period. Silt curtain systems were also inspected timely in accordance to the submitted plan. All inspection records were kept properly.

3.5.5      Training was provided for barge operators in accordance with the Regular Marine Travel Routes Plan and relevant records were kept properly.

3.5.6      A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix F. Most of the necessary mitigation measures were implemented properly.

3.6               Advice on the Solid and Liquid Waste Management Status

3.6.1      The Contractor registered as a chemical waste producer for the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.

3.6.2      No marine sediment was generated/treated and no treated marine sediment was reused in the reporting period. As informed by the Contractor in May 2016, the transfer of treated marine sediment to Contract no. HY/2010/02 has been discontinued since July 2015.

3.6.3      The summary of waste flow table is detailed in Appendix I.

3.6.4      The Contractor was reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

3.6.5      The work site area of Contract No. HY/2013/01 was handed over to the relevant authorities since 24 October 2018 and no chemical waste and general refuse were generated in November 2018.

3.7               Environmental Licenses and Permits

3.7.1      The valid environmental licenses and permits in September and October 2018 are summarized in Appendix J.

3.7.2      The work site area of Contract No. HY/2013/01 was handed over to the relevant authorities since 24 October 2018, therefore, no environmental licenses and permits is required in November 2018.


4          Summary of Exceedance, Complaint, Notification of Summons and Successful Prosecution

4.1               Summary of Exceedance of the Environmental Quality Performance Limit

4.1.1      For air quality monitoring, no Action and Limit Level exceedances of 1-hour TSP were recorded at AMS2, AMS3C and AMS7B in September 2018. No Action and Limit Level exceedances of 24-hour TSP were recorded at AMS2, AMS3C and AMS7B in September 2018.

4.1.2      No Action and Limit level exceedance of 1-hr TSP level and 24-hr TSP level recorded AMS7B by the Environmental Team of Contract No. HY/2013/04 in October and November 2018.

4.1.3      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A Reports (for September to November 2018) prepared by Contract No. HY/2011/03.

4.1.4      There were no Action and Limit Level exceedance for noise recorded at NMS2 and NMS3C by the ET of Contract No. HY/2013/01 (for September 2018) and the ET of Contract No. HY/2013/04 (for October and November 2018).

4.1.5      For water quality monitoring in September 2018, no Action Level and Limit Level exceedances of turbidity were recorded at mid-ebb tide and mid-flood tide by the ET of Contract No. HY/2013/01. One Action Level exceedance of turbidity was recorded at mid-ebb tide on 24 October 2018 by the ET of Contract No. HY/2013/04 while no Action Level exceedances of turbidity were recorded at mid-flood tide by the ET of Contract No. HY/2013/04 during October and November 2018. No Limit Level exceedances of turbidity was recorded by the ET of Contract No. HY/2013/04 during October and November 2018.

4.1.6      73 Action Level exceedances of dissolved oxygen were recorded at mid-ebb tide on 3, 5, 7, 10, and 14 September 2018 while 80 Action Level exceedances of dissolved oxygen were recorded at mid-flood tide on 3, 5, 7, 10, 12, 14 and 28 September 2018 by the ET of Contract No. HY/2013/01. 12 Limit Level exceedances of dissolved oxygen were recorded at mid-ebb tide on 3, 5, 10 and 14 September 2018 while 17 Limit Level exceedances of dissolved oxygen were recorded at mid-flood tide on 3, 5, 7, 10, 12, 14, and 28 September 2018 by ET of Contract No. HY/2013/01. No Action Level and Limit Level exceedance of dissolved oxygen were recorded at mid-ebb tide and mid-flood tide by the ET of Contract No. HY/2013/04 during October and November 2018.

4.1.7      Two Action Level exceedances of suspended solid were recorded at mid-flood tide on 10 and 12 September 2018 while no Action Level exceedances of suspended solid were recorded at mid-ebb tide and no Limit Level exceedances of suspended solid were recorded by the ET of Contract No. HY/2013/01 in September 2018. Six Action Level exceedances of suspended solid were recorded at mid-flood tide on 10 October 2018, 23 and 26 November 2018 by the ET of Contract No. HY/2013/04. No Action Level exceedances of suspended solid were recorded at mid-ebb tide and no Limit Level exceedances of suspended solid were recorded by the ET of Contract No. HY/2013/04 during October and November 2018.

4.1.8      As confirmed by the Contractor, no marine transportation and marine-based work was conducted during the reporting period. Therefore, it is concluded that the exceedances were not related the Contract No. HY/2013/01.  

4.1.9      Impact dolphin monitoring results at all transects are reported in the EM&A Reports prepared for Contract No. HY/2013/01 (September 2018) and Contract No. HY/2013/04 (October and November 2018). 1 Limit Level exceedance of dolphin monitoring was recorded in the quarterly report prepared for Contract No. HY/2013/04.




4.2               Summary of Complaints, Notification of Summons and Successful Prosecution

4.2.1      There was no complaint received in relation to the environmental impact during the reporting period. The details of cumulative statistics of Environmental Complaints are provided in Appendix K.

4.2.2      No notification of summons and prosecution was received during the reporting period.

4.2.3      Statistics on notifications of summons and successful prosecutions are summarized in Appendix K.

 

5           Comments, Recommendations and Conclusion

5.1               Comments

5.1.1      No particular environmental issue was recorded during the site inspections carried out on 5, 12, 19, and 26 September 2018 and 5, 10, 18, 24 and 31 October 2018.

5.1.2      The works area in Hong Kong-Zhuhai-Macao Bridge was handed over to the relevant authorities since 24 October 2018 and the site area was changed to closed area, no site inspection was conducted for the Contract No. HY/2013/01 in November 2018.

5.1.3      A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix F. Most of the necessary mitigation measures were implemented properly.

5.2               Recommendations

5.2.1      With implementation of the recommended environmental mitigation measures, the contractˇ¦s environmental impacts were considered environmentally acceptable. The weekly environmental site inspections ensured that all the environmental mitigation measures recommended were effectively implemented.

5.2.2      The recommended environmental mitigation measures, as included in the EM&A programme, effectively minimize the potential environmental impacts from the contract. Also, the EM&A programme effectively monitored the environmental impacts from the construction activities and ensure the proper implementation of mitigation measures. No particular recommendation was advised for the improvement of the programme.


 

5.3               Conclusions

5.3.1      The site preparation work of the Contract started on 26 September 2014 and the construction works of the Contract commenced on 6 October 2014. The construction works of the Contract No. HY/2013/06 within Contractor No. HY/2013/01 works area commenced on 20 February 2018. This is the seventeenth Quarterly EM&A Report summaries findings of the EM&A works during the reporting period from 1 September to 30 November 2018(included the construction works of Contract No. HY/2013/06 within Contract No. HY/2013/01 works area). The works area in Hong Kong-Zhuhai-Macao Bridge was handed over to the owner since 24 October 2018.

5.3.2      For air quality monitoring, no Action and Limit Level exceedances of 1-hour TSP were recorded at AMS2, AMS3C and AMS7B in September 2018. No Action and Limit Level exceedances of 24-hour TSP were recorded at AMS2, AMS3C and AMS7B in September 2018.

5.3.3      No Action and Limit level exceedance of 1-hr TSP level and 24-hr TSP level recorded AMS7B by the Environmental Team of Contract No. HY/2013/04 in October and November 2018.

5.3.4      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A Reports (for September to November 2018) prepared by Contract No. HY/2011/03.

5.3.5      There were no Action and Limit Level exceedance for noise recorded at NMS2 and NMS3C by the ET of Contract No. HY/2013/01 (for September 2018) and the ET of Contract No. HY/2013/04 (for October and November 2018).

5.3.6      For water quality monitoring in September 2018, no Action Level and Limit Level exceedances of turbidity were recorded at mid-ebb tide and mid-flood tide by the ET of Contract No. HY/2013/01. One Action Level exceedance of turbidity was recorded at mid-ebb tide on 24 October 2018 by the ET of Contract No. HY/2013/04 while no Action Level exceedances of turbidity were recorded at mid-flood tide by the ET of Contract No. HY/2013/04 during October and November 2018. No Limit Level exceedances of turbidity was recorded by the ET of Contract No. HY/2013/04 during October and November 2018.

5.3.7      73 Action Level exceedances of dissolved oxygen were recorded at mid-ebb tide on 3, 5, 7, 10, and 14 September 2018 while 80 Action Level exceedances of dissolved oxygen were recorded at mid-flood tide on 3, 5, 7, 10, 12, 14 and 28 September 2018 by the ET of Contract No. HY/2013/01. 12 Limit Level exceedances of dissolved oxygen were recorded at mid-ebb tide on 3, 5, 10 and 14 September 2018 while 17 Limit Level exceedances of dissolved oxygen were recorded at mid-flood tide on 3, 5, 7, 10, 12, 14, and 28 September 2018 by ET of Contract No. HY/2013/01. No Action Level and Limit Level exceedance of dissolved oxygen were recorded at mid-ebb tide and mid-flood tide by the ET of Contract No. HY/2013/04 during October and November 2018.

5.3.8      Two Action Level exceedances of suspended solid were recorded at mid-flood tide on 10 and 12 September 2018 while no Action Level exceedances of suspended solid were recorded at mid-ebb tide and no Limit Level exceedances of suspended solid were recorded by the ET of Contract No. HY/2013/01 in September 2018. Six Action Level exceedances of suspended solid were recorded at mid-flood tide on 10 October 2018, 23 and 26 November 2018 by the ET of Contract No. HY/2013/04. No Action Level exceedances of suspended solid were recorded at mid-ebb tide and no Limit Level exceedances of suspended solid were recorded by the ET of Contract No. HY/2013/04 during October and November 2018.

5.3.9      As confirmed by the Contractor, no marine transportation and marine-based work was conducted during the reporting period. Therefore, it is concluded that the exceedances were not related the Contract No. HY/2013/01.

5.3.10    Impact dolphin monitoring results at all transects are reported in the EM&A Reports prepared for Contract No. HY/2013/01 (September 2018) and Contract No. HY/2013/04 (October and November 2018). 1 Limit Level exceedance of dolphin monitoring was recorded in the quarterly report prepared for Contract No. HY/2013/04.

5.3.11    Environmental site inspections were carried out on 5, 12, 19, and 26 September 2018 and 5, 10, 18, 24 and 31 October 2018 for the Contract No. HY/2013/01 (includes the construction works of Contract No. HY/2013/06 within Contract No. HY/2013/01 works area). Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site inspections.

5.3.12    The works area in Hong Kong-Zhuhai-Macao Bridge was handed over to the relevant authorities since 24 October 2018 and the site area was changed to closed area, no site inspection was conducted for the Contract No. HY/2013/01 in November 2018. Landscape Checklist is shown in Appendix A.

5.3.13    There was no complaint received in relation to the environmental impact during the reporting period.

5.3.14    No notification of summons and successful prosecution was received during the reporting period.