TABLE
OF CONTENTS
1 |
||
1 |
1-2 |
|
1.1 |
Basic Project
Information |
1 |
1.2 |
Project Organization |
2 |
1.3 |
Construction Programme |
2 |
1.4 |
Construction Works Undertaken During
the Reporting Period |
2 |
|
|
|
2 |
3-4 |
|
2.1 |
Monitoring Locations |
3 |
2.2 |
Monitoring Requirements |
3 |
2.3 |
Monitoring Results |
4 |
|
|
|
3 |
5 |
|
3.1 |
Monitoring Locations |
5 |
3.2 |
Monitoring Requirements |
5 |
3.3 |
Monitoring Results |
5 |
|
|
|
4
|
6-7 |
|
4.1 |
Monitoring Locations |
6 |
4.2 |
Monitoring Requirements |
6-7 |
4.3 |
Monitoring Results
|
7 |
|
|
|
5
|
8 |
|
5.1 |
Monitoring Locations |
8 |
5.2 |
Monitoring Requirements |
8 |
5.3 |
Monitoring Results
|
8 |
|
|
|
6 |
9-12 |
|
6.1 |
Site Inspection |
9 |
6.2 |
Advice on the Solid and
Liquid Waste Management Status |
9-10 |
6.3 |
Environmental Licenses and Permits |
10 |
6.4 |
Implementation
Status of Environmental Mitigation Measures |
11 |
6.5 |
Summary of
Exceedance of the Environmental Quality Performance Limit |
11 |
6.6 |
Summary of
Complaints, Notification of Summons and Successful Prosecution |
11-12 |
|
|
|
7 |
12 |
|
7.1 |
Construction
Programme for the Coming Months |
12 |
7.2 |
Environmental Site Inspection Schedule
for the Coming Month |
12 |
|
|
|
8 |
12-13 |
|
8.1 |
Conclusions |
12-13 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
||||||
Figure 1 |
Air Quality and Noise Monitoring Stations for HKBCF |
|
||||
Figure 2 |
Water Quality Monitoring Stations (construction phases) |
|
||||
Figure 3 |
Dolphin
Monitoring Transect Line and Layout Map |
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
||||
Table |
|
|
||||
Table 1.1 |
Contact Information of Key Personnel |
|
||||
Table 2.1 |
Air Quality Monitoring Locations |
|
||||
Table 2.2 |
Action and Limit Levels for 1-hour TSP |
|
||||
Table 2.3 |
Action and Limit Levels for 24-hour TSP |
|
||||
Table 3.1 |
Construction Noise Monitoring Locations |
|
||||
Table 3.2 |
Action and Limit Levels for Construction Noise |
|
||||
Table 4.1 |
Water Quality Monitoring Stations (construction phases) |
|
||||
Table 4.2 |
Action and Limit Levels for Water Quality |
|
||||
Table |
Action and Limit Levels for Chinese White Dolphin Monitoring ¡V
Approach to Define Action Level ( |
|
||||
Table 5.1b |
Action and Limit Levels for Chinese White Dolphin Monitoring - |
|
||||
Table 6.1 |
Summary of marine sediment disposed to dumping site via Contract No.
HY/2013/03 |
|
||||
Table 7.1 |
Construction Activities for coming month |
|
||||
|
|
|
||||
|
|
|
||||
|
|
|
||||
APPENDICES |
|
|||||
Location of Works Areas |
|
|||||
Project Organization for Environmental Works |
|
|||||
Construction Programme |
|
|||||
Event and Action Plan |
|
|||||
Monthly Summery of Waste Flow Table & Monthly Summery of Marine
Sediment |
|
|||||
Environmental Licenses and Permits |
|
|||||
Implementation Schedule for Environmental Mitigation Measures (EMIS) |
|
|||||
Statistics on Environmental Complaints, Notification of Summons and
Successful Prosecutions |
|
|||||
Environmental Site Inspection Schedule |
|
|||||
Investigation
Reports on Action Level or Limit Level Non-compliance |
|
|||||
Complaint Investigation
Report |
|
|||||
|
|
|
|
|||
|
|
|
|
|||
|
|
This Monthly Environmental
Monitoring and Audit (EM&A) Report is
prepared for Contract HY/2013/02 ¡§Hong Kong¡VZhuhai-Macao Bridge Hong Kong
Boundary Crossing Facilities (HKBCF) ¡V Infrastructure Works Stage I (Western
Portion)¡¨ (hereafter referred to as ¡§the Contract¡¨) for the Highways Department
of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to
China Harbour Engineering Co., Ltd. (hereafter referred to as ¡§the Contractor¡¨)
and ETS-Testconsult Limited was appointed as the Environmental Team (ET) by the
Contractor.
The Contract is part of Hong Kong¡VZhuhai¡VMacao
Bridge HKBCF which is a ¡§Designated Project¡¨, under Schedule 2 of the
Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental
Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for
the Project. The current Environmental Permit (EP) No.
EP-353/2009/K for HKBCF was issued on 11 April 2016. These documents are
available through the EIA Ordinance Register. Site preparation works of the
Contract was started on 25 July 2014 and the construction works of the Contract
commenced on 24 November 2014.
ETS-Testconsult Limited has been appointed by
the Contractor to implement the Environmental Monitoring & Audit (EM&A)
programme for the Contract in accordance with the Updated EM&A Manual for
HKBCF (Version 1.0) and provide environmental team services to the Contract.
This is the Twenty-fourth Monthly Environmental
Monitoring and Audit (EM&A) Report for the Contract which summaries
findings of the EM&A works conducted during the reporting
period from 01 November 2016 to 30 November 2016.
Site Activities
As
informed by the Contractor, site
activities were carried out in
this reporting month:
¡± Bored piles works in Portion C & F;
¡± Pier
/ Abutment in Portion C & F;
¡± Pile
Cap in Portion C & F;
¡± Pre-bored
H-pile for sign gantries in Portion D;
¡± Storm drain and water main construction;
¡± Footing construction of directional signs and duct laying in
Portion I & CLP area;
¡± Marine Delivery of
precast segment & Construction of bridge deck in Portion D, A & E
¡± Marine sediment
excavation activities from the land-based works and corresponding disposal at the designated disposal sites.
Environmental Monitoring and Audit Progress
The monthly EM&A programme was
undertaken in accordance with the Updated EM&A Manual for HKBCF (Version
1.0). It should be noted that the air quality and noise monitoring works for
the Contract are covered by Contract No. HY/2010/02 ¡§Hong Kong-Zhuhai-
Environmental Site Inspection:
03, 10, 17 &
24 November 2016
Breaches
of Action and Limit Levels
Summary of
Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6
shall be referred to the monthly EM&A report prepared by Contract No.
HY/2011/03.
There was no Action and Limit Level exceedance
of 1-hr TSP level and 24-hr TSP level
recorded at station AMS7 by the Environmental Team of Contract No. HY/2010/02 during the reporting period.
There was no Action and Limit Level exceedance
for noise recorded at
station NMS2 and station NMS3B by the Environmental Team of Contract No.
HY/2010/02 during the reporting period.
There was one Action Level exceedance of SS at station SR4(N) during mid-flood tide recorded on 14 November 2016, two Action Level exceedances of SS at
station IS10 and SR5 and one Limit Level
exceedance of SS at station at SR6
during mid-flood tide recorded
on 16 November 2016, five Action Level
exceedances of SS at station IS(Mf)11, IS10,
SR5, SR6 and SR7 during mid-flood tide recorded
on 18 November 2016 and two Action Level
exceedances of SS at station SR
Impact
dolphin monitoring results at all transects are reported in the EM&A Report
prepared for Contract No. HY/2010/02.
Complaint Log
There was a
complaint received by EPD from public on 09 November 2016 and forwarded by EPD
to the ENPO on 09 November 2016.Then the ENPO forwarded the complaint by email
to the R.E. (AECOM), the Contractor (China Harbour) and the ET (ETS-Testconsult
Ltd.) of Contract No. HY/2013/02 at 14:52 on 10 November 2016. The complainant
complained that an engineering works vessel named ¡§ªø²±
The above
mentioned complaint follow-up inspection was performed by the ET of Contract
No. HY/2013/02 on 10 November 2016.The complaint investigation report (Log No. 005)
was issued by the ET of Contract No. HY/2013/02 and verified by the IEC/ENPO on
15 November 2016.
According to the investigation, there was no any marine works carried
out on 07 November 2016 by Contract No. HY/2013/02. The complaint was found
non-related to Contract No. HY/2013/02. The complaint investigation report (Log No. 005) was provided in Appendix K.
Notifications of Summons and Successful
Prosecutions
There were no
notifications of summons or prosecutions received during the reporting period.
Reporting Change
There were no
reporting changes during the reporting period.
Future
Key Issues
The future key
issues to be undertaken in the upcoming month are as follows:
¡± Bored piles works in Portion C & F;
¡± Pier / Abutment in Portion C & F;
¡± Pile Cap in Portion C & F;
¡± Pre-bored H-pile for sign gantries in Portion D;
¡± Storm drain and water main construction;
¡± Retaining wall, slop and earth works
¡± Footing construction of directional signs, cable trench and
ducting;
¡± Delivery of precast segment & Construction of bridge deck in
Portion D, A, E, C & F
¡± Marine sediment
excavation activities from the land-based works and corresponding disposal at the designated disposal sites.
1.
INTRODUCTION
1.1.
Basic Project Information
1.1.1.
This Monthly Environmental
Monitoring and Audit (EM&A) Report is
prepared for Contract HY/2013/02 ¡§Hong Kong¡VZhuhai-Macao Bridge Hong Kong
Boundary Crossing Facilities (HKBCF) ¡V Infrastructure Works Stage I (Western
Portion)¡¨ (hereafter referred to as ¡§the Contract¡¨) for the Highways Department
of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to
China Harbour Engineering Co., Ltd. (hereafter referred to as ¡§the Contractor¡¨)
and ETS-Testconsult Limited was appointed as the Environmental Team (ET) by the
Contractor.
1.1.2.
The Contract is part of
Hong Kong¡VZhuhai¡VMacao Bridge HKBCF which is a ¡§Designated Project¡¨, under
Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499)
and Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009)
was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016.
These documents are available through the EIA Ordinance Register. Site
preparation works of the Contract started on 25 July 2014 and the construction
works of the Contract commenced on 24 November 2014. The works area of the
Contract is shown in Appendix A.
1.1.3.
The proposed works under this
Contract comprise the following:
¡±
Construction of the viaducts and
roads at the western portion of Hong Kong Boundary Crossing Facilities (HKBCF)
mainly for connection with the Hong Kong¡VZhuhai¡VMacao Bridge (HZMB), Hong Kong Link Road (HKLR), Hong Kong International
Airport (HKIA) and the Tuen Mun-Chek Lap Kok Link (TM-CLKL);
¡±
Construction of the road modification at the SkyCity Interchange
at
¡±
Construction of associated street lighting, street
furniture, road marking, road signage, drainage, sewerage, fresh water and
flushing water supply, irrigation, landscape, electrical and mechanical
(E&M), utilities and services works;
¡±
Provisioning of civil engineering works and power supply
installation for the Traffic Control and Surveillance System TCSS;
¡±
Other works in accordance with the
Contract.
1.1.4.
This is the Twenty-fourth Monthly Environmental
Monitoring and Audit (EM&A) Report for the Contract which summaries the
audit findings of the EM&A programme during the reporting
period from 01 November 2016 to 30 November 2016.
1.2.
Project Organization
1.2.1.
The project organization structure and
lines of communication with respect to the on-site environmental management
structure is shown in Appendix B.
The key personnel contact names and numbers are summarized in Table 1.1.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name of Key Staff |
Tel. No. |
Fax No. |
Engineer or Engineer¡¦s
Representative (AECOM Asia Co. Ltd.) |
Resident
Engineer |
Mr. Dominic Mow |
6274
0909 |
315205116 |
Environmental Project Office
/ Independent Environmental Checker (Ramboll Environ Hong Kong
Limited) |
Environmental
Project Office Leader |
Mr. Y. H. Hui |
3465
2888 |
3465
2899 |
Independent
Environmental Checker |
Mr.
Raymond Dai |
3465
2888 |
3465
2899 |
|
Environmental
Site Supervisor |
Mr.
Ray Yan |
5181
8165 |
3465
2899 |
|
Contractor (China
Harbour Engineering Co., Ltd.) |
Environmental
Officer |
Mr.
Richard Ng |
5977
0593 |
3915
0300 |
Assistant
Environmental Officer |
Mr.
Paper Chan |
6486
8967 |
3915
0300 |
|
Environmental
Supervisor |
Mr.
Endy Tse |
5512
2662 |
3915
0300 |
|
Environmental Team (ETS-Testconsult Ltd.) |
Environmental Team Leader |
Mr. C. L. Lau |
2946 7791 |
2695 3944 |
1.3 Construction Programme
1.4 Construction Works Undertaken
During the Reporting Period
1.4.1
A summary of the
construction activities undertaken during this reporting period is shown below:
¡±
Bored piles works in Portion C
& F
¡±
Pier / Abutment in Portion C
& F;
¡±
Pile Cap in Portion C & F ;
¡±
Pre-bored H-pile for sign
gantries in Portion D;
¡±
Storm drain and water main
construction;
¡±
Footing construction of
directional signs and duct laying in Portion I & CLP area;
¡±
Marine
Delivery of precast segment &
Construction of bridge deck in Portion D, A & E
¡±
Marine sediment excavation activities from the land-based works and corresponding disposal at the designated disposal sites.
2.1 Monitoring
Locations
Table 2.1 Air Quality Monitoring Locations
Identification No. |
Location Description |
AMS6(1) |
Dragonair / CNAC (Group) Building
|
AMS7(1) (2) |
Hong Kong SkyCity Marriott Hotel |
Remarks: |
(1)
The ET of this Contract should conduct impact air quality
monitoring at the AMS listed in the table as part of EM&A programme according
to latest notification from ENPO when the monitoring station(s) is/are no
longer covered by another ET of the HZMB project. |
(2)
The air quality monitoring location
AMS of the updated EM&A Manual
started from January 2016. |
2.2 Monitoring
Requirements
Table 2.2 Action and Limit
Levels for 1-hour TSP
Monitoring
Station |
Action
Level,mg/m3 |
Limit
Level,mg/m3 |
AMS6 ¡V Dragnair /
SNAC (Group) Building (HKIA) |
360 |
500 |
AMS7 ¡V Hong Kong SkyCity Marriott Hotel |
370 |
500 |
Table 2.3 Action and Limit Levels for 24-hour TSP
Monitoring
Station |
Action
Level,mg/m3 |
Limit
Level,mg/m3 |
AMS6 ¡V Dragnair /
SNAC (Group) Building (HKIA) |
173 |
260 |
AMS7 ¡V Hong Kong SkyCity Marriott Hotel |
183 |
260 |
2.3 Monitoring
Results
3.1 Monitoring Locations
Table 3.1 Construction Noise Monitoring Locations
Identification No. |
Location Description |
|
NMS2(1) |
Sea |
|
NMS3B(1) (2) |
Site Boundary of Site Office Area at Works Area WA2 |
|
Remarks: |
||
(1)
The ET of this Contract should conduct impact noise monitoring
at the NMS listed in the table as part of EM&A programme according to
latest notification from ENPO when the monitoring station(s) is/are no longer
covered by another ET of the HZMB project. |
||
(2)
The Action and Limit Levels for schools will be applied for this
alternative monitoring location. |
3.2 Monitoring
Requirements
Table 3.2 Action and Limit Levels for Construction Noise
Parameter |
Action Level |
Limit Level |
|
07:00 ¡V
19:00 hours on normal weekdays |
When one documented complaint is received |
75 dB(A)* |
|
Notes: |
|
||
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed. |
|
||
* Reduce to 70
dB(A) for schools and 65 dB(A) during school examination period. |
|
||
3.3 Monitoring Results
4.1
Monitoring
Locations
The water monitoring works for the Contract are
covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-
Table 4.1 Water Quality Monitoring
Stations (construction phases)
Station |
Description |
East |
North |
|
IS7 |
Impact Station (Close to HKBCF
construction site) |
812244 |
818777 |
|
IS10 |
Impact Station (Close to HKBCF
construction site) |
812577 |
820670 |
|
IS(Mf)11 |
Impact Station (Close to HKBCF
construction site) |
813562 |
820716 |
|
SR3 |
Sensitive receivers (San Tau SSSI) |
810525 |
816456 |
|
SR4(N) |
Sensitive receivers (Tai Ho) |
814705 |
817859 |
|
SR5 |
Sensitive receivers (Artificial Reef in
NE Airport) |
811489 |
820455 |
|
SR6 |
Sensitive receivers (Sha Chau and |
805837 |
821818 |
|
SR7 |
Sensitive receivers (Tai Mo Do) |
814293 |
821431 |
|
SR |
Sensitive receivers (Ma Wan FCZ)1 |
823741 |
823495 |
|
SR10B(N)[1] |
Sensitive receivers (Ma Wan FCZ)2 |
823683 |
823187 |
|
CS(Mf)3 |
Control Station |
809989 |
821117 |
|
CS(Mf)5 |
Control Station |
817990 |
821129 |
|
CS4 |
Control Station |
810025 |
824004 |
|
CS6 |
Control Station |
817028 |
823992 |
|
CSA [2] |
Control Station |
818103 |
823064 |
|
Note: |
|
|||
(1)
Additional
monitoring station for Ma Wan FCZ. |
|
|||
(2)
Additional
control monitoring station for Ma Wan FCZ |
|
|||
Remarks: |
|
|||
The ET of
this Contract should conduct impact water quality monitoring at the WQMS
listed in the table as part of EM&A programme according to latest
notification from ENPO when the monitoring station(s) is/are no longer
covered by another ET of the HZMB project. The ET of the Contract shall communicate and share the monitoring
data to the ET(s) of other works contracts if the water quality monitoring
station(s) is/are as part of EM&A programme. |
|
|||
4.2
Monitoring
Requirements
The
monitoring requirements, monitoring equipment, monitoring parameters, frequency
and duration, monitoring methodology, monitoring schedule, meteorological
information are detailed in the monthly EM&A Reports prepared for Contract
No. HY/2010/02.
4.2.1
The event and
action plan is provided in Appendix D.
4.2.2
The Action and Limit Levels for Water Quality are provided in Table 4.2
Table 4.2 Action and Limit Levels
for Water Quality
|
Parameters |
Action |
Limit |
|
|
DO in mg/L (Surface, Middle & Bottom) |
Surface and Middle 5.0 Bottom 4.7 |
Surface and Middle 4.2 (except 5 mg/L for FCZ) Bottom 3.6 |
|
|
SS in mg/L (depth-averaged) at all monitoring stations and control
stations |
23.5 and 120% of upstream control station's SS at the same tide of the
same day* |
34.4 and 130% of upstream control station's SS at the same tide of the
same day and 10mg/L for WSD Seawater intakes* |
|
|
Turbidity in NTU (depth-averaged) |
27.5 and 120% of upstream control station's turbidity at the same tide
of the same day* |
47.0 and 130% of upstream control station's turbidity at the same tide
of the same day* |
|
* Remarks: Reference is made to EPD approval of adjustment of water
quality assessment criteria issued and became effective on 18 February 2013. |
|
|||
Notes: 1. "depth-averaged" is
calculated by taking the arithmetic means of reading of all three depths. |
|
|||
2. For DO, non-compliance of the water quality
limits occurs when monitoring result is lower than the limits. |
|
|||
3. For turbidity, SS, non-compliance of the water quality limits occurs
when monitoring result is higher than the limits. |
|
|||
4. All the figures given in the table are used for
reference only and the EPD may amend the figures whenever it is considered as
necessary. |
|
|||
5. The 1%-ile of baseline data for dissolved oxygen
(surface and middle) and dissolved oxygen (bottom) are 4.2mg/L and 3.6mg/L
respectively. |
|
|||
4.3
Monitoring Result
4.3.1
The monitoring results for the monitoring
stations showed in Table 4.1 are reported in the monthly EM&A Report
prepared for Contract No. HY/2010/02. There
was one Action Level
exceedance of SS at station SR4(N)
during mid-flood tide recorded
on 14 November 2016, two Action Level
exceedances of SS at station IS10 and SR5
and one Limit Level exceedance
of SS at station at
SR6 during mid-flood tide recorded
on 16 November 2016, five Action Level
exceedances of SS at station IS(Mf)11, IS10,
SR5, SR6 and SR7 during mid-flood tide recorded
on 18 November 2016 and two Action Level
exceedances of SS at station SR
4.3.2
Exceedances were not due to operation of the works under Contract No. HY/2013/02
because there was no marine works or
barge of this Contract worked at HKBCF reclamation site during November 2016. Therefore, it is unlikely that the SS
exceedances recorded on
14, 16, 18 and 30 November 2016 during mid-flood tide was contributed by
the works under Contract No. HY/2013/02. The water quality mitigation measures
as mentioned in EM&A Manual and EP was fully implemented in this Contract
which including maintenance of the silt curtain on a daily basis etc. Hence,
the exceedance was considered as non-Project related.
4.3.3
After
investigation, there was concluded that the exceedance was not relevant to this
Contract due to the above mentioned reasons. The Investigation Reports No.
007, 008, 009 and 010 (including the causes of exceedance, action taken and
recommendation for mitigation) for Action or Limit Level Non-compliance were provided
in Appendix J. There was no Action and Limit Level
exceedance on other monitoring date was
recorded by the Environmental Team of Contract No. HY/2010/02 during the
reporting period.
4.3.4
Although the exceedance was not relevant to this
Contract, the contractor was reminded to ensure provision of ongoing
maintenance to the silt curtains and to carry out maintenance work once defects
were found.
5 DOLPHIN MONITORING
5.1 Monitoring Locations
The dolphin monitoring
works for the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-
Remarks:
The ET
of this Contract should conduct impact dolphin monitoring as part of EM&A
programme according to latest notification from ENPO when the monitoring
transect(s) is/are no longer covered by another ET of the HZMB project.
5.2 Monitoring
Requirements
The monitoring
requirements, monitoring equipment, monitoring parameters, frequency and
duration, monitoring methodology, monitoring schedule, meteorological
information are detailed in the monthly EM&A Reports prepared for Contract
Nos. HY/2010/02.
5.2.1
The event and
action plan is provided in Appendix D.
5.2.2
The Action and Limit Levels for Chinese White Dolphin Monitoring are provided in Table
Table
Define
Action Level (
|
|
|
NEL |
NWL |
|
Action Level |
(STG < 70% of baseline) & (ANI < 70% of baseline) |
(STG < 70% of baseline) & (ANI < 70% of baseline) |
Limit Level |
[(STG < 40% of baseline) & (ANI < 40% of baseline)] AND [(STG < 40% of baseline) & (ANI < 40% of baseline)] |
For North Lantau Social Cluster, action level
will be trigger if either NEL or NWL fall below the criteria; limit level will
be triggered if both NEL and NWL fall below the criteria.
Table 5.1b Derived Value of
Action Level (
Dolphin
Monitoring
|
|
|
NEL |
NWL |
|
Action Level |
(STG < 4.2) & (ANI < 15.5) |
(STG < 6.9) & (ANI < 31.3) |
Limit Level |
[(STG < 2.4) & (ANI < 8.9)] AND [(STG
< 3.9) & (ANI < 17.9)] |
5.3
Monitoring Result
The dolphin survey results for all transects are reported in the monthly
EM&A Reports prepared for Contract No. HY/2010/02.
6 ENVIRONMENTAL
SITE INSPECTION AND AUDIT
6. 1 Site
Inspection
27 October 2016
(a)
Oil contaminated soil was observed at Portion C. Oil
contaminated soil was removed at Portion C. The observation was closed
on 03 November 2016.
(b)
Oil container without drip tray was observed at Portion C. The drip tray was provided at Portion C. The
observation was closed on 03 November 2016.
03 November 2016
(a)
C & D wastes were observed at Portion C. C & D wastes were
collected at Portion C. The observation was closed on 10 November 2016.
(b)
Oil
containers without drip tray were observed at Portion C. Drip tray was provided
for the oil containers at Portion C. The observation was closed on 10 November 2016.
10 November 2016
(a)
Damaged
NRMM label on generator was observed at Portion D. NRMM label on generator was
repaired at Portion D. The observation was closed on 17 November 2016.
(b)
C
& D materials were observed at Portion D. C & D materials were
collected at Portion D. The observation was closed on 17
November 2016.
17 November 2016
(a)
General refuse was observed on bridge surface at Portion D. The general refuse was collected on bridge surface at Portion D. The
observation was closed on 24 November 2016.
(b)
Stagnant water was observed on bridge deck surface at Portion D. Stagnant
water was cleared on bridge
deck surface at Portion D. The observation was closed on 24 November 2016.
(c)
General
refuse was observed at Portion D. The general refuse was collected at Portion
D. The observation was closed on 24 November 2016.
24 November 2016
(a)
No label for temporary storage of C & D wastes was observed at
Portion A. Follow-actions
for outstanding observation will be inspected during the next site inspection.
6. 2 Advice on
the Solid and Liquid Waste Management Status
6.2.2
Table 6.1 Summary of marine sediment
disposed to dumping site via Contract No.
HY/2013/03
Month/Year |
Quantity disposed (m3) |
January
2016 |
1272 |
February 2016 |
2816 |
March
2016 |
600 |
April
2016 |
5128 |
May
2016 |
0 |
June
2016 |
1200 |
July
2016 |
728 |
August
2016 |
1784 |
September
2016 |
2328 |
October
2016 |
1096 |
November
2016 |
0 |
Total = |
16952 |
6.3 Environmental Licenses and
Permits
The valid
environmental licenses and permits during the reporting period are summarized
in Appendix F.
6.4 Implementation Status of Environmental Mitigation
Measures
6.5 Summary of
Exceedance of the Environmental Quality Performance Limit
6.6
Summary of
Complaints, Notification of Summons and Successful Prosecution
6.6.1
There was a complaint received by EPD from public
on 09 November 2016 and forwarded by EPD to the ENPO on 09 November 2016.Then
the ENPO forwarded the complaint by email to the R.E. (AECOM), the Contractor
(China Harbour) and the ET (ETS-Testconsult Ltd.) of Contract No. HY/2013/02 at
14:52 on 10 November 2016. The complainant complained that an engineering works
vessel named ¡§ªø²±
The above
mentioned complaint follow-up inspection was performed by the ET of Contract
No. HY/2013/02 on 10 November 2016.The complaint investigation report (Log No. 005)
was issued by the ET of Contract No. HY/2013/02 and verified by the IEC/ENPO on
15 November 2016.
6.6.2.
According to the investigation, there was no any
marine works carried out on 07 November 2016 by Contract No. HY/2013/02. The complaint was found non-related to
Contract No. HY/2013/02. The complaint investigation report (Log No. 005) was provided
in Appendix K.
6.6.3.
Although this complaint was non-related to Contract
No. HY/2013/02, the Contractor of Contract No. HY/2013/02 was reminded to
provide appropriate water pollution mitigation measures for the marine working
vessels during any marine works, such as remind all Captains of the vessels to
avoid arranging vessels to travel in the area during low tide or discharge
waste water to the sea etc.
7.1 Construction
Programme for the Coming Months
Table 7.1 Construction Activities for Coming Month
Site Area |
Description
of Activities |
Portion
C & F |
Bored Piles Works |
Pier / Abutment |
|
Pile Cap |
|
Portion
D |
Pre-bored H-pile for sign gantries |
Portion
D, A, E, C & F |
Marine delivery of precast segment
& Construction of bridge deck |
|
Footing construction of directional
signs and dust laying |
|
Storm drain and water main construction |
|
Retaining wall, slop and earth works |
|
Marine sediment
excavation activities from the land-based works and corresponding disposal at the
designated disposal sites |
7.2 Environmental
Site Inspection Schedule for the Coming Month
8.1 Conclusions
- END OF REPORT -