20171018091913_00001.jpg20171018091921_00001.jpg


 

TABLE OF CONTENTS

Executive SUMMARY

 

1

INTRODUCTION

1-2

1.1

Basic Project Information

1

1.2

Project Organization

2

1.3

Construction Programme

2

1.4

Construction Works Undertaken During the Reporting Period

2

 

 

 

2

AIR QUALITY MONITORING

3

2.1

Monitoring Locations

3

2.2

Monitoring Requirements

3

2.3

Monitoring Results

3

 

 

 

3

NOISE MONITORING

4

3.1

Monitoring Locations

4

3.2

Monitoring Requirements

4

3.3

Monitoring Results

4

 

 

 

4

WATER QUALITY MONITORING

5-7

4.1

Monitoring Locations

5

4.2

Monitoring Requirements

5-6

4.3

Monitoring Results

6-7

 

 

 

5

DOLPHIN MONITORING

7-8

5.1

Monitoring Locations

7

5.2

Monitoring Requirements

7-8

5.3

Monitoring Results

8

 

 

 

6

ENVIRONMENTAL SITE INSPECTION AND AUDIT

8-11

6.1

Site Inspection

8

6.2

Advice on the Solid and Liquid Waste Management Status

8-10

6.3

Environmental Licenses and Permits

10

6.4

Implementation Status of Environmental Mitigation Measures

10

6.5

Summary of Exceedance of the Environmental Quality Performance Limit

10-11

6.6

Summary of Complaints, Notification of Summons and Successful Prosecution

11

 

 

 

7

FUTURE KEY ISSUES

11-12

7.1

Construction Programme for the Coming Months

11-12

7.2

Environmental Site Inspection Schedule for the Coming Month

12

 

 

 

8

CONCLUSION

12-13

8.1

Conclusions

12-13

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figures

 

Figure 1

Air Quality and Noise Monitoring Stations for HKBCF

 

Figure 2

Water Quality Monitoring Stations(construction phases)

 

Figure 3

Dolphin Monitoring TransectLine and Layout Map

 

 

 

 

 

 

 

 

 

 

TABLE

 

 

Table 1.1

Contact Information of Key Personnel

 

Table 2.1

Air Quality Monitoring Locations

 

Table 2.2

Action and Limit Levels for 1-hour TSP

 

Table 2.3

Action and Limit Levels for 24-hour TSP

 

Table 3.1

Construction Noise Monitoring Locations

 

Table 3.2

Action and Limit Levels for Construction Noise

 

Table 4.1

Water Quality Monitoring Stations (construction phases)

 

Table 4.2

Action and Limit Levels for Water Quality

 

Table 4.3

Number of Exceedance for Water Quality Monitoring

 

Table 5.1

New co-ordinates of changed vessel-based transect lines

 

Table 5.2a

Action and Limit Levels for Chinese White Dolphin Monitoring ¡V Approach to Define Action Level (AL) and Limit Level (LL)

 

Table 5.2b

Action and Limit Levels for Chinese White Dolphin Monitoring -

 

Table 6.1

Summary of marine sediment disposed to dumping site via Contract No. HY/2013/03

 

 

 

 

 

 

 

 

 

 

APPENDICES

 

Appendix A

Location of Works Areas

 

Appendix B

Project Organization for Environmental Works

 

Appendix C

Construction Programme

 

Appendix D

Event and Action Plan

 

Appendix E

Monthly Summery of Waste Flow Table & Monthly Summery of Marine Sediment

 

Appendix F

Environmental Licenses and Permits

 

Appendix G

Implementation Schedule for Environmental Mitigation Measures (EMIS)

 

Appendix H

Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions

 

Appendix I

Environmental Site Inspection Schedule

 

Appendix J

Investigation Reports on Action Level or Limit Level Non-compliance

 

 

 

 

 

 

 

 

 

 

 


 

Executive SUMMARY

 

This Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract HY/2013/02 ¡§Hong Kong¡VZhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) ¡V Infrastructure Works Stage I (Western Portion)¡¨ (hereafter referred to as ¡§the Contract¡¨) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to China Harbour Engineering Co., Ltd. (hereafter referred to as ¡§the Contractor¡¨) and ETS-Testconsult Limited was appointed as the Environmental Team (ET) by the Contractor.

 

The Contract is part of Hong Kong¡VZhuhai¡VMacao Bridge HKBCF which is a ¡§Designated Project¡¨, under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. Site preparation works of the Contract was started on 25 July 2014 and the construction works of the Contract commenced on 24 November 2014.

 

ETS-Testconsult Limited has been appointed by the Contractor to implement the Environmental Monitoring & Audit (EM&A) programme for the Contract in accordance with the Updated EM&A Manual for HKBCF (Version 1.0) and provide environmental team services to the Contract.

 

This is theThirty-fourth Monthly Environmental Monitoring and Audit (EM&A) Report for the Contractwhich summaries findings of the EM&A works conducted during the reporting period from 01September to 30September2017.

 

Site Activities

 

As informed by the Contractor, site activities were carried out in this reporting month:

 

l  Road and Bituminous works;

l  Storm, sewer drainage and water main construction;

l  Retaining wall, slop and earth works;

l  Construction of signs gantries, cable trench and ducting;

l  Demolition of temporary loading and unloading point (Marine-based activity);

l  Construction of bridge deck in Portion D, A, E, C & F

 

 

Environmental Monitoring and Audit Progress

 

The monthly EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0). It should be noted that the air quality and noise monitoring works for the Contract are covered by Contract No. HY/2013/01 ¡§Hong Kong-Zhuhai-Macao Bridge HKBCF ¡VPassenger Clearance Building¡¨and Contract No. HY/2011/03 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill and HKBCF¡¨. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 and AMS7, noise monitoring at NMS2 and NMS3B, water quality monitoring show in Figure 2 and dolphinmonitoring show in Figure 3as part of EM&A programme if these monitoring stations are no longer covered under Contract No. HY/2013/01 and HY/2011/03. However, this is subject to ENPO¡¦s final decision on which ET should carry out the monitoring works at these stations.The dates of site inspection during the reporting period are listed below:

 

Environmental Site Inspection:07,14, 21&28September2017

 


Breaches of Action and Limit Levels

 

Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

 

There was noAction and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 by the Environmental Team of Contract No. HY/2013/01during the reporting period.

 

There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2013/01during the reporting period.

 

During September 2017, there were 137 action level exceedances and 26 limit level exceedances of dissolved oxygen, 5 action level exceedances and 1 limit level exceedance of turbidity, 8action level exceedances and 1 limit level exceedances of suspended solid. The following tablesummarized the number of exceedance on each sampling data.

 

Sampling Date

No. of Exceedances

DO

Turbidity

SS

Action

Limit

Action

Limit

Action

Limit

1/9/2017

8

0

0

0

0

0

6/9/2017

4

4

1

0

3

0

8/9/2017

24

4

4

0

2

1

11/9/2017

30

3

0

0

0

0

13/9/2017

13

3

0

0

0

0

15/9/2017

10

2

0

1

0

0

18/9/2017

8

2

0

0

1

0

20/9/2017

3

2

0

0

1

0

22/9/2017

17

4

0

0

0

0

25/9/2017

1

1

0

0

1

0

27/9/2017

6

1

0

0

0

0

29/9/2017

13

0

0

0

0

0

Total:

137

26

5

1

8

1

 

After investigation, there was concluded that the exceedances were not relevant to this Contract since there was only one marine based activity which is demolition of temporary loading and unloading pointof this Contract worked at HKBCF reclamation site near the sea area or area near the monitoring stations.The demolition of temporary loading and unloading point was started from 18 July 2017. The major marine based activity was the removal of marine piling of temporary loading and unloading point. All marine based activities were carried out within the silt curtain and no defect of silt curtain was recorded by Contract No. HY/2010/02 from 18 July 2017 to 31August 2017. Besides, there was also no DO, turbidity and SS exceedance recorded during 18 July 2017 to 31 August 2017. Therefore, the exceedance was not caused by demolition of temporary loading and unloading point.The Investigation Reports No. 019, 020, 021 and 022(including the causes of exceedance, action taken and recommendation for mitigation) for Action or Limit Level Non-compliance were provided in Appendix J. As confirmed by SRE, removal of temporary loading and unloading point by Contract No. HY/2013/02, which involved marine work, was completed on 10 September and the area was handed back to Reclamation Contractor on 11 September 2017 for subsequent seawall construction. No marine based works for demolition of loading and unloading point was conducted so that no investigation report was provided for all exceedances recorded after 11 September 2017. There was no Action and Limit Level exceedance recorded on other monitoring date at the monitoring stations showed at Table 4.1 by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

 

Impact dolphin monitoring results at all transects are reported in the EM&A Report prepared for Contract No. HY/2013/01.

 

 

Complaint Log

There was no complaint received in relation to the environmental impact during thereporting period.

 

Notifications of Summons and Successful Prosecutions

 

There were no notifications of summons or prosecutions received during thereporting period.

 

Reporting Change

 

From 01 September 2017, the implementation of environmental monitoring for Contract No. HY/2010/02 (covering air quality, noise, water quality and marine ecology) was suspended and the same implementation will be conducted by the ET for Contract No. HY/2013/01 of which the noise monitoring station (NMS3B) and the meteorological station have been slightly re-located to AECOM PRE's Office.

 

Future Key Issues

 

The future key issues to be undertakenin the upcoming month are as follows:

 

l  Road and Bituminous works

l  Storm, sewer drainage and water main construction;

l  Retaining wall, slop and earth works

l  Construction of signs gantries, cable trench and ducting;

l  Construction of parapet & barrier


1.         INTRODUCTION

 

1.1.         Basic Project Information

 

1.1.1.     This Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract HY/2013/02 ¡§Hong Kong¡VZhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) ¡V Infrastructure Works Stage I (Western Portion)¡¨ (hereafter referred to as ¡§the Contract¡¨) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to China Harbour Engineering Co., Ltd. (hereafter referred to as ¡§the Contractor¡¨) and ETS-Testconsult Limited was appointed as the Environmental Team (ET) by the Contractor.

 

1.1.2.     The Contract is part of Hong Kong¡VZhuhai¡VMacao Bridge HKBCF which is a ¡§Designated Project¡¨, under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. Site preparation works of the Contract started on 25 July 2014 and the construction works of the Contract commenced on 24 November 2014. The works area of the Contract is shown in Appendix A.

 

1.1.3.     Theproposed works under this Contract comprise the following:

 

¡±   Construction of the viaducts and roads at the western portion of Hong KongBoundaryCrossing Facilities (HKBCF) mainly for connection with the Hong Kong¡VZhuhai¡VMacaoBridge (HZMB), Hong Kong Link Road (HKLR), Hong Kong International Airport (HKIA) and the Tuen Mun-Chek Lap Kok Link (TM-CLKL);

 

¡±   Construction of the road modification at the SkyCity Interchange at Airport Island;

 

¡±   Construction of associated street lighting, street furniture, road marking, roadsignage,drainage, sewerage, fresh water and flushing water supply, irrigation, landscape, electricaland mechanical (E&M), utilities and services works;

 

¡±   Provisioning of civil engineering works and power supply installation for the Traffic Control and Surveillance System TCSS;

 

¡±   Other works in accordance with the Contract.

 

1.1.4.     This is the Thirty-fourthMonthly Environmental Monitoring and Audit (EM&A) Report for the Contract which summaries the audit findings of the EM&A programme during the reporting period from 01 September to 30September 2017.


 

1.2.         Project Organization

 

1.2.1.     The project organization structure and lines of communication with respect to the on-site environmental management structure is shown in Appendix B. The key personnel contact names and numbers are summarized in Table 1.1.

 

Table 1.1           Contact Information of Key Personnel

Party

Position

Name of Key Staff

Tel. No.

Fax No.

Engineer or Engineer¡¦s Representative

 (AECOM Asia Co. Ltd.)

Resident Engineer

Mr. Winston Wong

6330 8293

31525116

Environmental Project Office / Independent Environmental Checker

(Ramboll Environ Hong Kong Limited)

Environmental Project Office Leader

Mr. Y. H. Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Raymond Dai

3465 2888

3465 2899

Environmental Site Supervisor

Mr. Ray Yan

5181 8165

3465 2899

Contractor

(China Harbour Engineering Co., Ltd.)

EnvironmentalOfficer

Mr. Richard Ng

5977 0593

3915 0300

EnvironmentalOfficer

Mr. Paper Chan

6486 8967

3915 0300

Environmental Supervisor

Mr. Endy Tse

5512 2662

3915 0300

Environmental Team

 (ETS-Testconsult Ltd.)

Environmental Team Leader

Mr. C. L. Lau

2946 7791

2695 3944

 

1.3.         Construction Programme

 

1.3.1.     A copy of the Contractor¡¦s construction programme is provided in Appendix C.

 

1.4.         Construction Works Undertaken During the Reporting Period

 

1.4.1.     A summary of the construction activities undertaken during this reporting period is shown below:

 

 

l    Road and Bituminous works;

l    Storm, sewer drainage and water main construction;

l    Retaining wall, slop and earth works;

l    Construction of signs gantries, cable trench and ducting;

l    Demolition of temporary loading and unloading point (Marine-based activity);

l    Construction of bridge deck in Portion D, A, E, C & F


2.            AIR QUALITY MONITORING

 

2.1.         Monitoring Locations

2.1.1.     Theair quality monitoring works for the Contract are covered by Contract No. HY/2013/01 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡VPassenger Clearance Buildingand Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill and HKBCF. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 and AMS7 as part of EM&A programme if these air quality monitoring stations are no longer covered under Contract No. HY/2013/01 and HY/2011/03.Table 2.1 andFigure 1shows the locations of air monitoring stations.

 

Table 2.1           Air Quality Monitoring Locations

 

IdentificationNo.

LocationDescription

AMS6(1)

Dragonair / CNAC (Group) Building

AMS7(1) (2)

Hong Kong SkyCity Marriott Hotel

 

Remarks:

(1)         The ET of this Contract should conduct impact air quality monitoring at the AMS listed in the table aspart ofEM&A programme according to latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

(2)         The air quality monitoring location AMS7A was relocated back to the original monitoring location AMS7

of the updated EM&A Manual started from January 2016.

 

2.2.         Monitoring Requirements

 

2.2.1.     The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared for Contract Nos. HY/2013/01 and HY/2011/03.

 

2.2.2.     TheAction and Limit Levels for 1-hr TSP and 24-hr TSP are provided in Table 2.2and Table 2.3 respectively. The Action and Limit Levels of AMS7 are as same as its original levels and AMS7A.

 

 Table 2.2          Action and Limit Levels for 1-hour TSP

 

Monitoring Station

Action Level,mg/m3

Limit Level,mg/m3

AMS6 ¡V Dragnair / SNAC (Group) Building (HKIA)

360

500

AMS7 ¡VHong Kong SkyCity Marriott Hotel

370

500

 

Table 2.3               Action and Limit Levels for 24-hour TSP

Monitoring Station

Action Level,mg/m3

Limit Level,mg/m3

AMS6 ¡V Dragnair / SNAC (Group) Building (HKIA)

173

260

AMS7 ¡VHong Kong SkyCity Marriott Hotel

183

260

 

2.2.3.     The event and action plan is provided in Appendix D.

 

2.2.4.     If exceedance(s) at these stations is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

 

2.3.         Monitoring Results

 

2.3.1.     The monitoring results for AMS6 and AMS7 are reported in the monthly EM&A Reports prepared for Contract Nos. HY/2011/03 and HY/2013/01 respectively.

 

2.3.2.     Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

 

2.3.3.     There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 by the Environmental Team of Contract No. HY/2013/01during the reporting period.

3.            NOISE MONITORING

 

3.1.         Monitoring Locations

3.1.1.     The noise monitoring works for the Contract are covered by Contract No. HY/2013/01 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡VPassenger Clearance Building. The ET of the Contract or another ET of the HZMB project is required to conduct noise monitoring at NMS2 and NMS3B as part of EM&A programme if these monitoring stations are no longer covered under Contract No. HY/2013/01. Table 3.1 and Figure 1shows the locations of noise monitoring stations.

 

Table 3.1          Construction Noise Monitoring Locations

 

IdentificationNo.

LocationDescription

NMS2(1)

Sea View Crescent

NMS3B(1) (2)

Site Boundary of Site Office Area at Works Area WA2

Remarks:

 

(1)        The ET of this Contract should conduct impact noise monitoring at the NMS listed in the table as part of EM&A programme according to latest notification from ENPO when the monitoring station(s) is/are no longer covered by anotherET of the HZMB project.

 

(2)        The Action and Limit Levels for schools will be applied for this alternative monitoring location.

 

 

3.2.         Monitoring Requirements

 

3.2.1.     The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared for Contract No. HY/2013/01.

 

3.2.2.     The Action and Limit Levelsfor construction noise are provided in Table 3.2

 

3.2.3.     The event and action plan is provided in Appendix D.

Table 3.2           Action and Limit Levels for Construction Noise

Parameter

Action Level

Limit Level

07:00 ¡V 19:00 hours on normal weekdays

When one documented complaint is received

75 dB(A)*

Notes:

 

Ifworksaretobecarriedout duringrestrictedhours,theconditionsstipulatedintheconstruction noisepermitissuedbytheNoiseControlAuthorityhavetobefollowed.

 

*Reduce to70dB(A) for schools and65 dB(A)duringschoolexaminationperiod.

 

 

 

 

 

 

 

 

 

 

3.2.4.     If exceedance(s) at these stations is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

 

3.3.         Monitoring Results

3.3.1       Themonitoring results for NMS2 and NMS3B are reported in the monthly EM&A Reports prepared for Contract No. HY/2013/01. There was no exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2013/01during the reporting period.


4.            WATER QUALITY MONITORING

 

4.1.         Monitoring Locations

 

The watermonitoring works for the Contract are covered by Contract No. HY/2013/01 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡VPassenger Clearance Building. The ET of the Contract or another ET of the HZMB project is required to conduct waterquality monitoring at twenty one stations (9 Impact Stations, 7 Sensitive Receiver Stations and 5 Control/Far Field Stations). Table 4.1 and Figure 2shows the locations of water quality monitoring stations.

 

Table 4.1       Water Quality Monitoring Stations (construction phases)

Station

Description

East

North

IS5

Impact Station (Close to HKBCF construction site)

811579

817106

IS(Mf)6

Impact Station (Close to HKBCF construction site)

812101

817873

IS7

Impact Station (Close to HKBCF construction site)

812244

818777

IS8

Impact Station (Close to HKBCF construction site)

814251

818412

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

IS10(N)

Impact Station (Close to HKBCF construction site)

812942

820881

IS(Mf)11

Impact Station (Close to HKBCF construction site)

813562

820716

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS17

Impact Station (Close to HKBCF construction site)

814539

820391

SR3

Sensitive receivers (San Tau SSSI)

810525

816456

SR4(N)

Sensitive receivers (Tai Ho)

814705

817859

SR5(N)

Sensitive receiver (Artificial Reef in NE Airport)

812569

821475

SR6

Sensitive receivers (Sha Chau and Lung Kwu Chau Marine Park)

805837

821818

SR7

Sensitive receivers (Tai Mo Do)

814293

821431

SR10A[1]

Sensitive receivers (Ma Wan FCZ)1

823741

823495

SR10B(N)[1]

Sensitive receivers (Ma Wan FCZ)2

823683

823187

CS(Mf)3(N)

Control Station

808814

822355

CS(Mf)5

Control Station

817990

821129

CS4

Control Station

810025

824004

CS6

Control Station

817028

823992

CSA[2]

Control Station

818103

823064

Note:

(1)      Additional monitoring station for Ma Wan FCZ.

(2)      Additional control monitoring station for Ma Wan FCZ

Remarks:

The ET of this Contract should conduct impact water quality monitoring at the WQMS listed in the table as part of EM&A programme according to latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project. The ET of the Contract shall communicate and share the monitoring data to the ET(s) of other works contracts if the water quality monitoring station(s) is/are as part of EM&A programme.

 

4.2          Monitoring Requirements

The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared for Contract No. HY/2013/01.

 

4.2.1       The event and action plan is provided in Appendix D.

 

4.2.2       The Action and Limit Levelsfor Water Quality are provided in Table 4.2

Table 4.2          Action and Limit Levels for Water Quality

 

Parameters

Action

Limit

 

DO in mg/L (Surface, Middle & Bottom)

Surface and Middle 5.0

Bottom 4.7

Surface and Middle 4.2 (except 5 mg/L for FCZ)

Bottom 3.6

 

SS in mg/L(depth-averaged) at all monitoring stations and control stations

23.5 and 120% of upstream control station's SS at the same tide of the same day*

34.4 and 130% ofupstream control station's SS at the same tide of the same day and 10mg/L for WSD Seawater intakes*

 

Turbidity in NTU (depth-averaged)

27.5 and 120% of upstream control station's turbidity at the same tide of the same day*

47.0 and 130% of upstream control station's turbidity at the same tide of the same day*

* Remarks: Reference is made to EPD approval of adjustment of water quality assessment criteria issued and became effective on 18 February 2013.

Notes:  1.  "depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.

2.  For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

3.For turbidity, SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

4.   All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

5.  The 1%-ile of baseline data for dissolved oxygen (surface and middle) and dissolved oxygen (bottom) are 4.2mg/L and 3.6mg/L respectively.

 

4.2.3       If exceedance(s) at these stations is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

                                                                                                                              

4.3          Monitoring Result

 

4.3.1       Themonitoring results for the monitoring stations showed in Table 4.1 are reported in the monthly EM&A Report prepared for Contract No. HY/2013/01. During September 2017, there were 137 action level exceedances and 26 limit level exceedances of dissolved oxygen, 5 action level exceedances and 1 limit level exceedance of turbidity, 8 action level exceedances and 1 limit level exceedances of suspended solid. Table 4.3summarized the number of exceedance on each sampling data.

 

Table 4.3        Number of Exceedances for Water Quality Monitoring

Sampling Date

No. of Exceedances

DO

Turbidity

SS

Action

Limit

Action

Limit

Action

Limit

1/9/2017

8

0

0

0

0

0

6/9/2017

4

4

1

0

3

0

8/9/2017

24

4

4

0

2

1

11/9/2017

30

3

0

0

0

0

13/9/2017

13

3

0

0

0

0

15/9/2017

10

2

0

1

0

0

18/9/2017

8

2

0

0

1

0

20/9/2017

3

2

0

0

1

0

22/9/2017

17

4

0

0

0

0

25/9/2017

1

1

0

0

1

0

27/9/2017

6

1

0

0

0

0

29/9/2017

13

0

0

0

0

0

Total:

137

26

5

1

8

1

 

4.3.2       After investigation, there was concluded that the exceedances were not relevant to this Contract since there was only one marine based activity which is demolition of temporary loading and unloading pointof this Contract worked at HKBCF reclamation site near the sea area or area near the monitoring stationsThe demolition of temporary loading and unloading point was started from 18 July 2017. The major marine based activity was the removal of marine piling of temporary loading and unloading point. All marine based activities were carried out within the silt curtain and no defect of silt curtain was recorded by Contract No. HY/2010/02 from 18 July 2017 to 31August 2017. Besides, there was also no DO, turbidity and SS exceedance recorded during 18 July 2017 to 31 August 2017. Therefore, the exceedance was not caused by demolition of temporary loading and unloading point.The Investigation Reports No. 019, 020, 021 and 022(including the causes of exceedance, action taken and recommendation for mitigation) for Action or Limit Level Non-compliance were provided in Appendix J. As confirmed by SRE, removal of temporary loading and unloading point by Contract No. HY/2013/02, which involved marine work, was completed on 10 September and the area was handed back to Reclamation Contractor on 11 September 2017 for subsequent seawall construction. No marine based works for demolition of loading and unloading point was conducted so thatno investigation report was provided for all exceedances recorded after 11 September 2017.There was no Action and Limit Level exceedance recorded on other monitoring date at the monitoring stations showed at Table 4.1 by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

 

4.3.3       Although the exceedances were not relevant to this Contract, the Contractor was reminded to ensure that the maintenance of perimeter silt curtains with respect to the work boundary of this Contract carried out by the Contractor of Contract No. HY/2010/02is maintained properly.

 

5.            DOLPHIN MONITORING

 

5.1.         Monitoring Locations

The dolphin monitoring works for the Contract are covered by Contract No. HY/2013/01 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡VPassenger Clearance Building. The ET of the Contract or another ET of the HZMB project is required to conduct dolphin monitoring at 24 transects as part of EM&A programme if these transects are no longer covered under Contract No. HY/2013/01. The dolphin monitoring should adopt line-transect vessel survey method. The survey follows pre-set and fixed transect lines in the two areas defined by AFCD as: Northeast Lantau survey area; and Northwest Lantau survey area. Figure 3shows the co-ordinates for the transect lines and layout map.

 

5.2.         Monitoring Requirements

The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared for Contract No. HY/2013/01.

 

5.2.1.     The event and action plan is provided in Appendix D.

 

5.2.2.     The Action and Limit Levels for Chinese White Dolphin Monitoring are provided in Table 5.2a & Table 5.2b

 

Table 5.2a          Action and Limit Levels for Chinese White Dolphin Monitoring ¡V Approach to

                        Define Action Level (AL) and Limit Level (LL)

 

North Lantau Social Cluster

NEL

NWL

Action Level

(STG< 70% of baseline) & (ANI < 70% of baseline)

(STG < 70% of baseline) &

(ANI < 70% of baseline)

Limit Level

[(STG < 40% of baseline) & (ANI < 40% of baseline)]

AND [(STG < 40% of baseline) & (ANI < 40% of baseline)]

For North Lantau Social Cluster, action level will be trigger if either NEL or NWL fall below the criteria; limit level will be triggered if both NEL and NWL fall below the criteria.

 

Table 5.2b        Derived Value of Action Level (AL) and Limit Level (LL) for Chinese White

                        Dolphin Monitoring

 

North Lantau Social Cluster

NEL

NWL

Action Level

(STG < 4.2) & (ANI < 15.5)

(STG < 6.9) & (ANI < 31.3)

Limit Level

[(STG < 2.4) & (ANI < 8.9)] AND [(STG < 3.9) & (ANI < 17.9)]

 

5.2.3.     If exceedance(s) at these transects is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

 

5.3          Monitoring Result

Thedolphin survey results for all transects are reported in the monthly EM&A Reports prepared for Contract No. HY/2013/01.

 

6.            ENVIRONMENTAL SITE INSPECTION AND AUDIT

 

6.1          Site Inspection

 

6.1.1      SiteInspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control mitigation measures for the project. During the reporting period, site inspections were carried out on 07, 14, 21 & 28September 2017.

 

6.1.2      Particular observations during the site inspections are described below:

31    August 2017

(a)        Improper disposal of general refuse was observed at Portion D.General refuse was collected at Portion D.The observation was closed on07 September 2017.

(b)        Oil container without drip tray was observed at Portion F. Oil container was removed at Portion F.The observation was closed on07 September 2017.

(c)        Improper disposal of general refuse was observed at Portion F. General refuse was collected at Portion F.The observation was closed on07 September 2017.

 

07 September 2017

(a)        Improper disposal of general refuse was observed at Portion C.General refuse was collected at Portion C.The observation was closed on14 September 2017.

 

14 September 2017

(a)         Damaged NRMM label was observed on a generator at Portion C.Appropriate NMRR label was provided on a generator at Portion C.The observation was closed on 21 September 2017.

(b)        Oil container without drip tray was observed at Portion F. Oil container was removed at Portion F. The observation was closed on 21 September 2017.

 

21 September 2017

(a)        Oil container without drip tray was observed at Portion C.Drip tray was provided for the oil container at Portion C.The observation was closed on 28September 2017.

(b)        C& D waste was observed at Portion C & D waste was sorted and stored at a designated area at Portion C.The observation was closed on 28 September 2017.

(c)        Substandard NRMM label was observed on a generator at Portion F.Appropriate NRMM label was provided at Portion F.The observation was closed on 28 September 2017.

(d)        Sand was found accumulated in the drip tray at Portion F.Accumulated sand was removed at Portion F.The observation was closed on 28 September 2017.

 

28September 2017

(a)        Missing of NRMM label was observed on an excavator at Portion D.Follow-actions for outstanding observation will be inspected during the next site inspection.

(b)        Cement mixing process without sheltered on top and 3 sides was observed at Portion D.Follow-actions for outstanding observation will be inspected during the next site inspection.

(c)        Substandard NRMM label was observed on a generator at Portion D.Follow-actions for outstanding observation will be inspected during the next site inspection.

 

6.2          Advice on the Solid and Liquid Waste Management Status

 

6.2.1      TheContractor registered as a chemical waste producer for the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.

 

6.2.2      There wasno excavated marine sedimentgenerated in this reporting period. The excavated marine sediment was stored properly on site during this reporting period until further instruction by the Engineer. The disposal of excavated sediment as per EP-353/2009/K to be implemented subject to confirmation.

 

6.2.3      Disposal of Marine Sediment

 

6.2.3.1   For the marine sediment disposal, after the acceptance of the review of the approved Sediment Quality Report (SQR) for this Project under EPD letter dated 19 August 2015, an approval to dispose the marine sediment extracted from bored piling for this Project was then approved under memo from Secretary, Marine Fill Committee of CEDD dated 20 August 2015 for the disposal of marine sediment extracted from bored piling works. The disposal sites allocated to this Project are the Mud Pit CMP2 of the Confined Marine Sediment Disposal Facility to the South of The Brothers (or at the East of Sha Chau). As advised by CEDD in the memo dated 19 February 2016, from 00:00 on 22 March 2016 onward, the disposal space at CMP2 of the South of The Brothers is closed and all disposal of contaminated sediment is to be carried out at CMP Vd to the East of Sha Chau (ESC). As a practical means, the disposal operation is managed by one contractor who is also responsible for applying dumping permit and its subsequent extension applications from EPD. Contract No. HY/2013/03 has been assigned to coordinate and arrange for disposal of extracted marine sediment from Contract No. HY/2013/02, HY/2013/03 and HY/2013/04.

 

6.2.3.2   For the dumping arrangement, the barge for disposal of marine sediment will moor at the temporary loading and unloading at the east shore of the HKBCF Island, which has been being used by contractor Contract No. HY/2010/02 for reclamation activities. In terms of safety consideration and to avoid mixing of sediment between contracts, each dumping date will be allocated to one Contract. The quantity of marine sediment disposed on each date is from one Contract.

 

6.2.3.3   During dumping, HY/2013/02 is responsible for transporting the marine sediment from his site area to the barge by Land transportation. The estimated quantity of marine sediment in each truck is confirmed by Resident Site Staff of each Contract. The trip tickets for transportation and disposal of marine sediment are collected and checked. Contract No. HY/2013/03 as the dumping permit holder is responsible for reporting to EPD the quantity disposed of as the condition stipulated in the dumping permit.

 

6.2.4      There was no marine sediment extracted from bored piling in this Contract disposed to allocated dumping site via Contract No. HY/2013/03 in this reporting period. As confirmed by RSS that the disposal ofexcavated marine sediments has been completed with the last batch disposal on 30 August 2017. The quantity disposed up to end of September 2017 was 20664 m3.The Monthly Summary of Marine sediment disposed to dumping site was provided in Appendix E and Table 6.1.

 

Table 6.1            Summary of marine sediment disposed to dumping site via Contract No.

                               HY/2013/03

Month/Year

Quantity disposed (m3)

January 2016

1272

February 2016

2816

March 2016

600

April 2016

5128

May 2016

0

June 2016

1200

July 2016

728

August 2016

1784

September 2016

2328

October 2016

1096

November 2016

0

December 2016

1568

January 2017

0

February 2017

88

March 2017

0

April 2017

624

May 2017

0

June 2017

1432

July 2017

0

August 2017

0

September 2017

0

Total =

20664

 

6.2.5      The Contractor shall ensure no spilling and overflowing of materials during loading / unloading / transportation is allowed.

 

6.2.6      The monthly summary of waste flow table is detailed in Appendix E.

 

6.2.7      The Contractor was reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packing, Labelling and Storage of Chemical Waste.

 

6.3          Environmental Licenses and Permits

 

6.3.1      The valid environmental licenses and permits during the reporting period are summarized in Appendix F.

 

6.4          Implementation Status of Environmental Mitigation Measures

 

6.4.1      In response to the site audit findings, the Contractor carried out corrective actions.

 

6.4.2      The Contractor waters 8 times per day on all exposed soil within the project site and associated works areas when construction activities are being undertaken.

 

6.4.3      TheContractor wasreminded to provide well-maintained plant operated on-site and plant served regularly;

 

6.4.4      TheContractor wasreminded to switch off vehicles and equipment while not in use;

 

6.4.5      TheContractor wasreminded to schedule the construction works to minimize noise nuisance etc.

 

6.4.6      The implementation status of Regular Marine Travel Route Plan (RMTRP) was checked by ET. Training material of Regular Marine Travel Route Plan was prepared and given to relevant staff. Those records were kept properly. Since the marine delivery of precast segments was completed in July 2017 and the removal of temporary loading and unloading point by Contract No. HY/2013/02, which involved marine work, was completed on 10 September 2017 and the area was handed back to Reclamation Contractor on 11 September 2017 for subsequent seawall construction, no marine traffic records and geographical plots of the vessels tracks to demonstrate the conformance of the vessel to the proposed route in September 2017 would be provided to ER, ETL, IEC/ENPO for checking within the month of October 2017.The implementation status of silt curtain deployment and dolphin watching plan was also checked by ET that silt curtain was deployed and MMO was provided by Contract No. HY/2010/02.

 

6.4.7      The tool box training of dolphin was carried out in Dec 2015. According to the action plan and communication flow chart of dolphin instruction, if any dolphin intruded BCF perimeter silt curtain, ETL should be informed. There was no notification received on any dolphin intrusion during the reporting period.

 

6.4.8      A summary of the implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix G. Most of the necessary mitigation measures were implemented properly.

 

6.5          Summary of Exceedance of the Environmental Quality Performance Limit

 

6.5.1      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

 

6.5.2      There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 by the Environmental Team of Contract No. HY/2013/01during the reporting period.

6.5.3      There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2013/01during the reporting period.

 

6.5.4      There were 137 action level exceedances and 26 limit level exceedances of dissolved oxygen, 5 action level exceedances and 1 limit level exceedance of turbidity, 8 action level exceedances and 1 limit level exceedances of suspended solid. Table 4.3summarized the number of exceedance on each sampling data. The Investigation Reports No. 019, 020, 021 and 022 (including the causes of exceedance, action taken and recommendation for mitigation) for Action or Limit Level Non-compliance were provided in Appendix J. As confirmed by SRE, removal of temporary loading and unloading point by Contract No. HY/2013/02, which involved marine work, was completed on 10 September 2017 and the area was handed back to Reclamation Contractor, Contract No. HY/2010/02,on 11 September 2017 for subsequent seawall construction. No marine based works for demolition of loading and unloading point was conducted so that no investigation report was provided for all exceedances recorded after 11 September 2017. There was no Action and Limit Level exceedance recorded on other monitoring date at the monitoring stations showed at Table 4.1 by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

 

Table 4.3        Number of Exceedances for Water Quality Monitoring

Sampling Date

No. of Exceedances

DO

Turbidity

SS

Action

Limit

Action

Limit

Action

Limit

1/9/2017

8

0

0

0

0

0

6/9/2017

4

4

1

0

3

0

8/9/2017

24

4

4

0

2

1

11/9/2017

30

3

0

0

0

0

13/9/2017

13

3

0

0

0

0

15/9/2017

10

2

0

1

0

0

18/9/2017

8

2

0

0

1

0

20/9/2017

3

2

0

0

1

0

22/9/2017

17

4

0

0

0

0

25/9/2017

1

1

0

0

1

0

27/9/2017

6

1

0

0

0

0

29/9/2017

13

0

0

0

0

0

Total:

137

26

5

1

8

1

 

6.5.5      Impact dolphin monitoring results at all transects are reported in the EM&A Reports prepared for Contract No. HY/2013/01.

 

6.6          Summary of Complaints, Notification of Summons and Successful Prosecution

 

6.6.1      There were no complaints received during the reporting period.

 

6.6.2       There were no notifications of summons or prosecutions received during thereporting period.

 

6.6.3      Statistics on environmentalcomplaints, notifications of summons and successful prosecutions are summarized in Appendix H.

 

7.            FUTURE KEY ISSUES

 

7.1          Construction Programme for the Coming Months

 

7.1.1      As informedby the Contractor, the major construction activities for October 2017 are summarized:

l   Road and Bituminous works

l   Storm, sewer drainage and water main construction;

l   Retaining wall, slop and earth works

l   Construction of signs gantries, cable trench and ducting;

l   Construction of parapet & barrier

 

7.2          Environmental Site Inspection Schedule for the Coming Month

 

7.2.1      The tentative schedule for weekly site inspections for October2017 is provided in Appendix I.

 

8.            CONCLUSION

 

8.1          Conclusions

 

8.1.1      The site preparation work of the Contract was started on 25 July 2014 and the construction works of the Contract commenced on 24 November 2014.

 

8.1.2      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

 

8.1.3      There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 by the Environmental Team of Contract No. HY/2013/01during the reporting period.

 

8.1.4      There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2013/01during the reporting period.

 

8.1.5      There were 137 action level exceedances and 26 limit level exceedances of dissolved oxygen, 5 action level exceedances and 1 limit level exceedance of turbidity, 8 action level exceedances and 1 limit level exceedances of suspended solid. Table 4.3summarized the number of exceedance on each sampling data. The Investigation Reports No. 019, 020, 021, 022, 023 and 024 (including the causes of exceedance, action taken and recommendation for mitigation) for Action or Limit Level Non-compliance were provided in Appendix J. As confirmed by SRE, removal of temporary loading and unloading point by Contract No. HY/2013/02, which involved marine work, was completed on 10 September and the area was handed back to Reclamation Contractor on 11 September 2017 for subsequent seawall construction. No marine based works for demolition of loading and unloading point was conducted so that no investigation report was provided for all exceedances recorded after 11 September 2017. There was no Action and Limit Level exceedance recorded on other monitoring date at the monitoring stations showed at Table 4.1 by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

 

Table 4.3        Number of Exceedances for Water Quality Monitoring

Sampling Date

No. of Exceedances

DO

Turbidity

SS

Action

Limit

Action

Limit

Action

Limit

1/9/2017

8

0

0

0

0

0

6/9/2017

4

4

1

0

3

0

8/9/2017

24

4

4

0

2

1

11/9/2017

30

3

0

0

0

0

13/9/2017

13

3

0

0

0

0

15/9/2017

10

2

0

1

0

0

18/9/2017

8

2

0

0

1

0

20/9/2017

3

2

0

0

1

0

22/9/2017

17

4

0

0

0

0

25/9/2017

1

1

0

0

1

0

27/9/2017

6

1

0

0

0

0

29/9/2017

13

0

0

0

0

0

Total:

137

26

5

1

8

1

 

8.1.6      Impact dolphin monitoring results at all transects are reported in the EM&A Reports prepared for Contract No. HY/2013/01.

 

8.1.7      There were no complaints received during the reporting period.

 

8.1.8      There were no notifications of summons or prosecutions received during thereporting period.

 

- END OF REPORT -