8.         CONCLUSIONS

 

8.1       Commencement of the Contract took place on 10 April 2015. The commencement date for construction works and the EM&A programme of the Contract commenced on 29 August 2015.

 

8.2       Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

 

8.3       There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7A by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

8.4       There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

8.5       There was no marine works conducted during the reporting period and therefore, no water quality impact monitoring result is reported.

 

8.6       There was no marine transportation and operation during the reporting period and therefore, no ecology monitoring result is reported.

 

8.7       Environmental site inspections were carried out on 3, 10, 17, 23 and 31 December 2015. Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site inspections.

 

8.8       There were no complaints received in relation to the environmental impact during the reporting period.

 

8.9       There were no notifications of summons or prosecutions received during the reporting period.