5.
ECOLOGY MONITORING
5.1 There was no
marine works conducted, no marine transportation and operation impacted to the
ecology during the reporting period and therefore, no relevant monitoring
result is reported. However, ET of the Contract shall closely monitor on the
status of marine works, which shall conduct monitoring when marine works
commence in the future.
5.2 The
ET of the Contract is required to conduct ecology monitoring as part of
EM&A programme if ecology monitoring is no longer covered by another ET of
the HZMB project. The ETL shall review and obtain IEC, ENPO, AFCD and EPD
agreement on the contract specific marine ecology monitoring works at least a
month before the commencement of any marine works, marine transportation or
operation.