8......... FUTURE KEY ISSUES

 

8.1       Construction Programme for the Coming Months

 

8.1.1    As informed by the Contractor, the following are the major construction activities anticipated in January 2017.

 

            For Contract No. HY/2013/03

 

1.       Site Investigation at Portion G & N;

2.       Building at Portion A1, B, G, N, J, STP & Pumping Stations;

3.       Piling at Portion C, STP, Area G (Bridge A1 & A9), Box Culvert B & C;

4.       CUE Construction at Portion B, C & J;

5.       Drainage & Sewerage Work, Water Main & Cable Duct at Portion B, H1, H2, J, P, G & A1;

6.       Radiation Screen Wall and Sign Gantry Footing at Portion B, E P, N;

7.       Sewerage Pumping Station, High Mast Lighting Foundation & Box Culvert C at Portion G;

8.       Bridge Works at A1 to A9;

9.       Site Foundation Works at Portion K;

10.    Cover Walkway at Portion H1 & H2;

11.    Box Culvert D at Portion A1; Shuttle kiosk & Subway at Portion E); and

12.    Marine sediment excavation activities from the land-based works and corresponding disposal at the designated disposal sites within Hong Kong as allocated by the Marine Fill Committee.

 

For Contract No. HY/2013/06 within Contract No. HY/2013/03 works area

 

1.       Concealed Conduit works at Inbound and Outbound Vehicle Kiosk.

 

8.2       Environmental Site Inspection Schedule for the Coming Month

 

8.2.1   The tentative schedule for weekly site inspections for January 2017 is provided in Appendix I.