7.         ENVIRONMENTAL SITE INSPECTION AND AUDIT

 

7.1       Site Inspection

 

7.1.1    Site audits were carried out by ET on weekly basis to monitor the implementation of proper environmental management practices and mitigation measures in the Project site.

 

7.1.2    The joint site audits for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) were conducted on 5, 11, 18 and 26 May 2017 by the representatives of Engineer, Contractor, ET and IEC (IEC for 26 May 2017).

 

7.1.3    Particular observations during the site inspection and corrective actions undertaken by the Contractor are described below:

 

For Contract No. HY/2013/03

 

28 April 2017

1.    The Contractor was reminded to remove stagnant water accumulated at drip trays at CUE works area. Subsequently, stagnant water at drip trays was removed. The observation was closed on 05 May 2017.

2.    The Contractor was reminded to improve housekeeping at Bridge A7. The Contractor was reminded to improve housekeeping at Bridge A7. Subsequently, housekeeping was improved. The observation was closed on 05 May 2017.

 

05 May 2017

1.      The Contractor was reminded to provide drip trays for chemical containers at Building 037. Subsequently, drip trays were provided. The observation was closed on 11 May 2017.

2.      The Contractor was reminded to remove general waste accumulated at Building 037. Subsequently, general waste was removed. The observation was closed on 11 May 2017.

 

            11 May 2017

1.      The Contractor was reminded to increase watering for dust suppression on site. Subsequently, watering was increased for dust suppression. The observation was closed on 18 May 2017.

2.      The Contractor was reminded to remove stagnant water accumulated at Building 040. Subsequently, stagnant water was removed. The observation was closed on 18 May 2017.

 

18 May 2017

1.    The Contractor was reminded to remove stagnant water accumulated at Building 041. Subsequently, stagnant water was removed. The observation was closed on 26 May 2017.

2.    The Contractor was reminded to remove general waste accumulated at A9 Bridge. Subsequently, general waste was removed. The observation was closed on 26 May 2017.

 

26 May 2017

1.      The Contractor was reminded to remove general and construction waste accumulated on site. Follow-up actions for outstanding observation will be checked in the upcoming site inspections and reported in the coming reporting period.

2.      The Contractor was reminded to remove stagnant water accumulated on site. Follow-up actions for outstanding observation will be checked in the upcoming site inspections and reported in the coming reporting period.

 

            For Contract No. HY/2013/06 within Contract No. HY/2013/03 works area

 

05 May 2017

1. Nil findings.

 

11 May 2017

1. Nil findings.

 

18 May 2017

1. Nil findings.

 

26 May 2017

1. Nil findings.

 

7.2    Advice on the Solid and Liquid Waste Management Status

 

7.2.1... The Contractor of Contract No. HY/2013/03 registered as a chemical waste producer for the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.

 

7.2.2    The monthly summary of waste flow table for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) are detailed in Appendix E.

 

7.2.3    Contract No. HY/2013/03 has been assigned to arrange for delivery of surplus filling materials from Contract No. HY/2013/03 to Tuen Mun - Chek Lap Kok Link (TM-CLKL) project of HZMB by marine access. The estimated quantity of surplus filling materials is confirmed by Resident Site Staff of Contract No. HY/2013/03. The summary of surplus filling materials delivered to TM-CLKL project up to the end of May 2017 is shown in Table 7.1.

 

Table 7.1 Summary of Surplus Filling Materials Delivered to TM-CLKL Project

Month/Year

Quantity disposed (in ‘000m3)

HY/2013/03

Total

May 2017

12.637

12.637

Total

12.637

12.637

            Note:

The disposal quantity of surplus filling materials provided by Resident Site Staff is in tonnes (for Contract No. HY/2013/03: 29,065 tonnes). In order to convert the disposal quantity from tonnes to m3, a conversion factor is used and shown as follows:

Volume (in m3) = Mass (in tonnes) / 2.3 (in tonnes/ m3)

Where 2.3 (in tonnes/ m3) is the density of surplus filling materials provided by the Contractor

 

7.2.4    1.440 (in‘000m3) of excavated marine sediment (from Contract No. HY/2013/03), 12.682 (in‘000m3) of Inert C & D Wastes and 1.321 (in‘000m3) of Non-inert C & D Wastes were generated (from Contract No. HY/2013/03) in this reporting period. 12.637(in‘000m3) of Inert C & D Wastes were reused in other projects and 0.045(in‘000m3) of Inert C & D Wastes was disposed as public fill. No Inert C & D Wastes and 0.020 (in tonnes) of Non-inert C & D Wastes were generated (from Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) in this reporting period. 0.020 (in tonnes) metals were generated and recycled (from Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) in this reporting period.

 

7.2.5    The excavated marine mud from the land-based works was disposed of at the designated disposal sites within Hong Kong as allocated by the Marine Fill Committee. The Contractor of Contract No. HY/2013/03 shall ensure no spilling and overflowing of materials during loading / unloading / transportation is allowed.

 

7.2.6... The Contractor was reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packing, Labelling and Storage of Chemical Waste.

 

7.2.7... Contractor of Contract No. HY/2013/03’s site arrangement for disposal of bentonite slurry to Tseung Kwan O Area 137 Fill Bank was checked by ET and formal consent has been obtained from Tseung Kwan O Area 137 Fill Bank for receiving used bentonite slurry generated from Contract No. HY/2013/03.

 

7.3       Environmental Licenses and Permits

 

7.3.1    The valid environmental licenses and permits for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) during the reporting period are summarized in Appendix F. The Contractor of Contract No. HY/2013/06 was advised to register as a chemical waste producer when chemical waste is expected to generate for the foreseeable future from the operations (For Registration as Waste Producer Pursuant to Waste Disposal (Chemical Waste) (General) Regulation).

 

7.4       Implementation Status of Environmental Mitigation Measures

 

7.4.1... In response to the site audit findings, the Contractor carried out corrective actions.

 

7.4.2... A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix G. All necessary mitigation measures at this stage of works were implemented properly.

 

7.4.3... Implementation status of Regular Marine Travel Route Plan (RMTRP) was checked by ET. Training of marine travel route for marine vessels operator was given to relevant staff and relevant records were kept properly. The marine traffic records and geographical plots of all the vessels tracks to demonstrate the conformance of the vessel to the proposed route in May 2017 would be provided to ER, ETL, IEC/ENPO for checking within the month of June 2017.

 

7.4.4... With respect to condition 3.26A of EP-353/2009/K approved by EPD on 11 April 2016, the numbers and operating periods of floating grout production facilities and floating concrete batching plants on-site to review on the compliance to this EP condition were checked. Under Contract No. HY/2013/03, no floating concrete batching plant was operated on-site during the reporting period.

 

7.4.5... As silt curtain was installed on 11 May 2017, Dolphin Watching Plan (DWP) should be implemented. Implementation status of DWP was checked by ET. Before the installation of silt curtain, ET conducted visual inspection of the presence of dolphins in the surrounding water. Besides, dolphin watching training was provided to the representatives of the Contractor during April 2017. The records of dolphin watching training, regular inspection of the silt curtains and visual inspection of waters surrounded by the silt curtain in May 2017 would be provided to ER, ETL, IEC/ENPO for checking within the month of June 2017.

 

7.5       Summary of Exceedance of the Environmental Quality Performance Limit

 

7.5.1    Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

 

7.5.2    There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

7.5.3    There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

7.5.4    There was no Action and Limit Level exceedance for water quality recorded at the monitoring stations shown at Table 4.1 by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

7.5.5    Ecological monitoring results at all transects are reported in the EM&A report prepared by Contract No. HY/2010/02.

 

7.6...... Summary of Complaints, Notification of Summons and Successful Prosecution

 

7.6.1    There was one complaint received in relation to the environmental impact during the reporting period. The summary of environmental complaints is presented in Table 7.1. The details of cumulative statistics of Environmental Complaints are provided in Appendix H.

 

Table 7.1 Summary of Environmental Complaints for the Reporting Month

Log No.

Environmental Complaint Ref. No.

Date of Complaint Receipt

Description

008

ENPO-C0119                  

31 May 2017

Air pollution

 

The complaint (ENPO-C0119) was received by EPD from a member of the public on 31 May 2017 and was referred by EPD to the ENPO. Then the ENPO forwarded the complaint by email to the ET (Materialab Consulants Ltd.) of the Contract No. HY/2013/03 on 01 June 2017.

 

Details of Complaint

            The complaint was forwarded from IEC on 01 June 2017, with the following information provided by EPD:

 

            The complainant complained that as there was no watering for dust suppression on the road next to Building 044 and 045 on the artificial island of HZMB, a lot of dust was raised when vehicles passed by causing serious nuisance.

 

            Investigation of Complaint

            The complaint was still under investigation. Details will be reported in the coming reporting period.

 

7.6.2    There was no notification for summons or prosecutions received in relation to the environmental impact during this reporting period.

 

7.6.3    Statistics on environmental complaints, notifications of summons and successful prosecutions are provided in Appendix H.