8.         FUTURE KEY ISSUES

 

8.1       Construction Programme for the Coming Months

 

8.1.1    As informed by the Contractor, the following are the major construction activities anticipated in September 2017:

 

For Contract No. HY/2013/03

 

1.       Building at Portion A1, B, G, N, J, STP & Pumping Stations;

2.       CUE Construction at Portion B, C & J;

3.       Drainage & Sewerage Work, Water Main & Cable Duct at Portion B, H1, H2, J, P, G & A1;

4.       Radiation Screen Wall at Portion B, E, P, N, M, C;

5.       Sign Gantry Footing at Portion B;

6.       Sewerage Pumping Station, High Mast Lighting Foundation & Box Culvert C at Portion G;

7.            Bridge Works at A1 to A9;

8.       Site Foundation Works at Portion K;

9.       Cover Walkway at Portion H1 & H2;

10.    Box Culvert B at Portion N; Shuttle kiosk & Subway at Portion E;

11.    Deployment, maintenance and inspection of silt curtain;

12.    Construction of water outfall of box culvert; and

13.    Marine sediment excavation activities from the land-based works and corresponding disposal at the designated disposal sites within Hong Kong as allocated by the Marine Fill Committee.

 

For Contract No. HY/2013/06 within Contract No. HY/2013/03 works area

 

1.          Conduits, Wiring & display panel installation at Building 037, kiosk and CUE works area.

 

8.2       Environmental Site Inspection Schedule for the Coming Month

 

8.2.1    The tentative schedule for weekly site inspections for September 2017 is provided in Appendix I.