4.            WATER QUALITY MONITORING

4.1          Monitoring Locations

4.1.1     The water monitoring works for the Contract are covered by Contract No. HY/2013/01 “Hong Kong-Zhuhai-Macao-Bridge HKBCF – Passenger Clearance Building”. The water quality monitoring station (SR3, SR10A and SR10B(N)) had been slightly re-located since 22 December 2017. The ET of the Contract or another ET of the HZMB project is required to conduct impact water quality monitoring at the stations shown in Table 4.1 and Figure 3.

Table 4.1 Water Quality Monitoring Stations

Station

Description

Easting

Northing

IS5

Impact Station (Close to HKBCF construction site)

811579

817106

IS(Mf)6

Impact Station (Close to HKBCF construction site)

812101

817873

IS7

Impact Station (Close to HKBCF construction site)

812244

818777

IS8

Impact Station (Close to HKBCF construction site)

814251

818412

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

IS10(N)

Impact Station (Close to HKBCF construction site)

812942

820881

IS(Mf)11

Impact Station (Close to HKBCF construction site)

813562

820716

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS17

Impact Station (Close to HKBCF construction site)

814539

820391

SR3

Sensitive receivers (San Tau SSSI)

810525

816456

SR3(N)

Sensitive receivers (San Tau SSSI)

810689

816591

SR4(N)

Sensitive receivers (Tai Ho)

814705

817859

SR5(N)

Control Station

812569

821475

SR6

Sensitive receivers (Sha Chau and Lung Kwu Chau Marine Park)

805837

821818

SR7

Sensitive receivers (Tai Mo Do)

814293

821431

SR10A

Sensitive receivers (Ma Wan FCZ) 1

823741

823495

SR10A(N)(1)

Sensitive receivers (Ma Wan FCZ) 1

823644

823484

SR10B(N)

Sensitive receivers (Ma Wan FCZ) 2

823683

823187

SR10B(N2)(1)

Sensitive receivers (Ma Wan FCZ) 2

823689

823159

CS(Mf)3(N)

Control Station

808814

822355

CS(Mf)5

Control Station

817990

821129

CS4

Control Station

810025

824004

CS6

Control Station

817028

823992

CSA(2]

Control Station

818103

823064

Note:

(1) Additional monitoring station for Ma Wan FCZ

(2) Additional control monitoring station for Ma Wan FCZ

Remarks:

The ET of the Contract should conduct impact water quality monitoring at the WQMs listed in the table as part of EM&A programme according to latest notification from ENPO if water quality monitoring is no longer covered by another ET of the HZMB project. The ET of the Contract shall communicate and share the monitoring data to the ET(s) of the other contracts if the water quality monitoring station(s) is/are as part of EM&A programme. SR3(N), SR10A(N) and SR10B(N2) are alternative WQM Stations.

 

 

 

4.2          Monitoring Requirements

4.2.1     The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared by Contract No. HY/2013/01.

4.2.2     The event and action plan is provided in Appendix D.

4.2.3     The Action and Limit Levels for Water Quality are provided in Table 4.2.

Table 4.2   Action and Limit Levels for Water Quality

Parameters

Action

Limit

DO in mg/L (Surface, Middle & Bottom)

Surface and Middle 5.0

Bottom 4.7

Surface and Middle = 4.2 (except 5 mg/L for FCZ)

Bottom = 3.6

SS in mg/L (depth-averaged) at all monitoring stations and control stations

23.5 and 120% of upstream control station's SS at the same tide of the same day*

34.4 and 130% of upstream control station's SS at the same tide of the same day and 10mg/L for WSD Seawater intakes*

Turbidity in NTU (depth-averaged)

27.5 and 120% of upstream control station's turbidity at the same tide of the same day*

47.0 and 130% of upstream control station's turbidity at the same tide of the same day*

* Remarks:    Reference is made to EPD approval of adjustment of water quality assessment criteria issued and became effective on 18 February 2013.

Notes:

1. ”depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.

2. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

3. For turbidity, SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

4. All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

5. The 1%-ile of baseline data for dissolved oxygen (surface and middle) and dissolved oxygen (bottom) are 4.2mg/L and 3.6mg/L respectively.

4.2.4     If exceedance(s) at these stations is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

4.3          Monitoring Results

4.3.1     The monitoring results for the monitoring stations showed in Table 4.1 are reported in the monthly EM&A Report prepared for Contract No. HY/2013/01. There was Action and Limit Level exceedance recorded at different WQM stations during mid-ebb and mid-flood tide on eight days. The summary of water quality exceedances is shown in Table 4.3.

Table 4.3   Action and Limit Levels for Water Quality

Station

Exceedance Level

DO (S&M)

DO (Bottom)

Turbidity

SS

Ebb

Flood

Ebb

Flood

Ebb

Flood

Ebb

Flood

IS5

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS(Mf6)

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS7

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS8

Action

0

0

0

0

0

0

1

(13 Dec)

2

(6 Dec, 8 Dec)

Limit

0

0

0

0

0

0

0

0

IS(Mf)9

Action

0

0

0

0

0

0

1

(11 Dec)

1

(6 Dec)

Limit

0

0

0

0

0

0

0

0

IS10(N)

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS(Mf)11

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS(Mf)16

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS17

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

SR3

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

SR4(N)

Action

0

0

0

0

0

0

0

1

(8 Dec)

Limit

0

0

0

0

0

0

0

0

SR5(N)

Action

0

0

0

0

0

0

0

1

(6 Dec)

Limit

0

0

0

0

0

0

0

0

SR6

Action

0

0

0

0

0

0

3

(4 Dec,

8 Dec,

22 Dec)

3

(6 Dec, 20 Dec, 22 Dec)

Limit

0

0

0

0

0

0

0

 

SR7

Action

0

0

0

0

0

0

0

1

(4 Dec)

Limit

0

0

0

0

0

0

0

 

SR10A

Action

0

0

0

0

0

0

0

1

(8 Dec)

Limit

0

0

0

0

0

0

0

 

SR10B(N)

Action

0

0

0

0

0

0

0

1

(4 Dec)

Limit

0

0

0

0

0

0

0

0

   Note:  S&M: Surface & Middle

 

4.3.2     Regarding the exceedance on 4 December 2017, there was no marine transportation on the date of exceedance. Regarding marine-based works in Box Culvert B, the work undertaken at the date of exceedance was preparation work of precast installation which had a cofferdam to separate seawater and works area. Silt curtain was also maintained to enclose the work area of the outlet of the box culvert fully. All sea water flows into the work area of box culvert B will be treated by desilting facilities before discharge in accordance with the discharge license approved by EPD for Contract No. HY/2013/03. For SS exceedance recorded at the WQM station SR6, SR7 and SR10B(N), the concerned WQM stations where the exceedances were recorded were not close to the marine works area of Contract No. HY/2013/03, while there was no notification of exceedance received at the WQM stations closer to the works areas, such as IS(Mf)11. It was unlikely that the works undertaken by Contract No. HY/2013/03 caused SS exceedance recorded at the concerned WQM station during mid-ebb tide and mid-flood tide on 4 December 2017.

4.3.3     Regarding the exceedance on 6 December 2017, there was no marine transportation on the date of exceedance. Regarding marine-based works in Box Culvert B, the work undertaken at the date of exceedance was preparation work of precast installation which had a cofferdam to separate seawater and works area. Silt curtain was also maintained to enclose the work area of the outlet of the box culvert fully. All sea water flows into the work area of box culvert B will be treated by desilting facilities before discharge in accordance with the discharge license approved by EPD for Contract No. HY/2013/03. For SS exceedance recorded at the WQM station IS8, IS(Mf)9, SR5(N) and SR6, the concerned WQM stations where the exceedances were recorded were not close to the marine works area of Contract No. HY/2013/03, while there was no notification of exceedance received at the WQM stations closer to the works areas, such as IS(Mf)11. It was unlikely that the works undertaken by Contract No. HY/2013/03 caused SS exceedance recorded at the concerned WQM station during mid-flood tide on 6 December 2017.

4.3.4     Regarding the exceedance on 8 December 2017, there was no marine transportation on the date of exceedance. Regarding marine-based works in Box Culvert B, the work undertaken at the date of exceedance was preparation work of precast installation which had a cofferdam to separate seawater and works area. Silt curtain was also maintained to enclose the work area of the outlet of the box culvert fully. All sea water flows into the work area of box culvert B will be treated by desilting facilities before discharge in accordance with the discharge license approved by EPD for Contract No. HY/2013/03. For SS exceedance recorded at the WQM station IS8, SR4(N), SR6 and SR10A, the concerned WQM stations where the exceedances were recorded were not close to the marine works area of Contract No. HY/2013/03, while there was no notification of exceedance received at the WQM stations closer to the works areas, such as IS(Mf)11. It was unlikely that the works undertaken by Contract No. HY/2013/03 caused SS exceedance recorded at the concerned WQM station during mid-ebb tide and mid-flood tide on 8 December 2017.

4.3.5     Regarding the exceedance on 11 December 2017, there was no marine transportation on the date of exceedance. Regarding marine-based works in Box Culvert B, the work undertaken at the date of exceedance was preparation work of precast installation which had a cofferdam to separate seawater and works area. Silt curtain was also maintained to enclose the work area of the outlet of the box culvert fully. All sea water flows into the work area of box culvert B will be treated by desilting facilities before discharge in accordance with the discharge license approved by EPD for Contract No. HY/2013/03. For SS exceedance recorded at the WQM station IS(Mf)9, the concerned WQM stations where the exceedances were recorded were not close to the marine works area of Contract No. HY/2013/03, while there was no notification of exceedance received at the WQM stations closer to the works areas, such as IS(Mf)11. It was unlikely that the works undertaken by Contract No. HY/2013/03 caused SS exceedance recorded at the concerned WQM station during mid-ebb tide on 11 December 2017.

4.3.6     Regarding the exceedance on 13 December 2017, there was no marine transportation on the date of exceedance. Regarding marine-based works in Box Culvert B, the work undertaken at the date of exceedance was preparation work of precast installation which had a cofferdam to separate seawater and works area. Silt curtain was also maintained to enclose the work area of the outlet of the box culvert fully. All sea water flows into the work area of box culvert B will be treated by desilting facilities before discharge in accordance with the discharge license approved by EPD for Contract No. HY/2013/03. For SS exceedance recorded at the WQM station IS8, the concerned WQM stations where the exceedances were recorded were not close to the marine works area of Contract No. HY/2013/03, while there was no notification of exceedance received at the WQM stations closer to the works areas, such as IS(Mf)11. It was unlikely that the works undertaken by Contract No. HY/2013/03 caused SS exceedance recorded at the concerned WQM station during mid-ebb tide on 13 December 2017.

4.3.7     Regarding the exceedance on 20 December 2017, there was marine transportation on the date of exceedance. Regarding marine transportation, the vessels was sized to make sure adequate clearance is maintained between vessels and the sea bed at all states of the tide to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash. For SS exceedance recorded at the WQM station SR6, the concerned WQM stations where the exceedances were recorded were not close to the marine delivery route of Contract No. HY/2013/03, while there was no notification of exceedance received at the WQM stations closer to the marine delivery route, such as IS(Mf)11. Regarding marine-based works in Box Culvert B, the work undertaken at the date of exceedance was preparation work of precast installation which had a cofferdam to separate seawater and works area. Silt curtain was also maintained to enclose the work area of the outlet of the box culvert fully. All sea water flows into the work area of box culvert B will be treated by desilting facilities before discharge in accordance with the discharge license approved by EPD for Contract No. HY/2013/03. For SS exceedance recorded at the WQM station SR6, the concerned WQM stations where the exceedances were recorded were not close to the marine works area of Contract No. HY/2013/03, while there was no notification of exceedance received at the WQM stations closer to the works areas, such as IS(Mf)11. It was unlikely that the works undertaken by Contract No. HY/2013/03 caused SS exceedance recorded at the concerned WQM station during mid-flood tide on 20 December 2017.

4.3.8     Regarding the exceedance on 22 December 2017, there was no marine transportation on the date of exceedance. Regarding marine-based works in Box Culvert B, the work undertaken at the date of exceedance was preparation work of precast installation which had a cofferdam to separate seawater and works area. Silt curtain was also maintained to enclose the work area of the outlet of the box culvert fully. All sea water flows into the work area of box culvert B will be treated by desilting facilities before discharge in accordance with the discharge license approved by EPD for Contract No. HY/2013/03. For SS exceedance recorded at the WQM station SR6, the concerned WQM stations where the exceedances were recorded were not close to the marine works area of Contract No. HY/2013/03, while there was no notification of exceedance received at the WQM stations closer to the works areas, such as IS(Mf)11. It was unlikely that the works undertaken by Contract No. HY/2013/03 caused SS exceedance recorded at the concerned WQM station during mid-ebb tide and mid-flood tide on 22 December 2017.