7.            ENVIRONMENTAL SITE INSPECTION AND AUDIT

7.1          Site Inspection

7.1.1     Site audits were carried out by ET on weekly basis to monitor the implementation of proper environmental management practices and mitigation measures in the Project site.

7.1.2     The landscape work of green roof for Contract No. HY/2013/03 was commenced on 7 November 2017. The landscape work of all areas at ground level for Contract No. HY/2013/03 was commenced at early February 2018. Detail commencement date of each building were shown in Table 7.1. The implementation of mitigation measures for landscape and visual resources recommended in the EIA Report were monitored during the reporting period. Landscape and visual mitigation measures in accordance with the EP, EIA and EM&A Manual were implemented by the Contractor.

Table 7.1 Commencement date of green roof for each building

Building No. of Green Roof

Commencement dates of planting for roof greening

037

7 Nov 2017

043

20 Dec 2017

041

27 Dec 2017

026

22 Jan 2018

039

22 Jan 2018

All areas at ground level

Early Feb 2018

031

8 Mar 2018

046

8 Mar 2018

7.1.3     The joint site audits for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) were conducted on 5, 13, 20 and 26 July 2018 by the representatives of Engineer, Contractor, ET and IEC (IEC for 20 July 2018).

7.1.4     Particular observations during the site inspection and corrective actions undertaken by the Contractor are described below:

For Contract No. HY/2013/03

28 June 2018

1.      The Contractor was reminded to clear the waste at Building 037. The observation was closed on 5 July 2018.

5 July 2018

1.      The Contractor was reminded to provide proper cover for the stockpile at Building 037. The observation was closed on 13 July 2018.

13 July 2018

1. Nil findings.

20 July 2018

1.      The Contractor was reminded to remove the waste accumulated outside Building 049. The observation was closed on 26 July 2018.

2.      The Contractor was reminded to provide a new NRMM label for the generator outside Building 049. The observation was closed on 26 July 2018.

            26 July 2018

1.      The Contractor was reminded to remove the waste accumulated outside Building 049. Follow-up actions for outstanding observation will be checked in the upcoming site inspections and reported in the coming reporting period.

For Contract No. HY/2013/06 within Contract No. HY/2013/03 works area

5 July 2018

1. Nil findings.

13 July 2018

1. Nil findings.

            20 July 2018

1. Nil findings.

            26 July 2018

1. Nil findings.

7.2          Advice on the Solid and Liquid Waste Management Status

7.2.1     The Contractor of Contract No. HY/2013/03 registered as a chemical waste producer for the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.

7.2.2      The monthly summary of waste flow table for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) are detailed in Appendix E.

7.2.3     Contract No. HY/2013/03 has been assigned to arrange for delivery of surplus filling materials from Contract No. HY/2013/03 to other projects, including Tuen Mun - Chek Lap Kok Link (TM-CLKL) project of HZMB, the Airport Authority Hong Kong¡¦s Three Runway (3RS) Project, Wan Chai Development Phase II project, Contract No. HY/2013/02 of HKBCF and Hong Kong Link Road (HKLR) project of HZMB. As confirmed by RSS, all surplus filling materials delivery to other projects have been completed with the last batch on 7 May 2018. The total transported quantity up to the last batch is 379.48358 (in¡¥000m3). The summary of surplus filling materials delivered to other projects up to the end of May 2018 is shown in Table 7.2.

Table 7.2 Summary of Surplus Filling Materials Delivered from Contract No. HY/2013/03 to other projects

Month/Year

Density (in tonnes/m3)

Quantity disposed (in ¡¥000m3)

To HY/2013/02

To TM-CLKL Project

To 3RS Project

To WDII Project

To HKLR Project

Total

May 2017

2.3

0

12.637

0

0

0

12.637

June 2017

2.63925

0

14.769

11.238

0

0

26.007

July 2017

1.9

0

4.406

34.875

10.048

0.760

50.089

August 2017

1.9

0.480

0

67.942

2.761

7.455

78.638

September 2017

1.9

5.544

0

62.770

0

4.648

72.962

October 2017

/

3.384

0

45.92809

0

0

49.31209

November 2017

/

5.412

0

5.507

0

0

10.919

December 2017

/

12.57173

0

0

0

0

12.57173

January 2018

/

10.228

0

0

0

0

10.228

February 2018

/

0

0

0

0

0

0

March 2018

/

0.45276

0

0

0

0

0.45276

April 2018

/

0

42.544

0

0

0

42.544

May 2018

/

0

13.123

0

0

0

13.123

Total

/

38.07249

87.479

228.26009

12.809

12.863

379.48358

            Remarks:

ž   The variation in density is due to different compositions of surplus filling materials

ž  There may be discrepancies in the total quantities with the quantities of inert C&D materials stated in Appendix E and section 7.2.4, due to rounding errors

ž  No density was given from October 2017 to May 2018 due to the direct volume figures as provided and confirmed by the RSS

7.2.4     0.000 (in¡¥000m3) of excavated marine sediment (from Contract No. HY/2013/03), 0.088 (in¡¥000m3) of Inert C & D Wastes and 0.590 (in¡¥000m3) of Non-inert C & D Wastes were generated (from Contract No. HY/2013/03) in this reporting period. 0.000 (in¡¥000m3) of Inert C & D Wastes were reused in other projects and 0.088 (in¡¥000m3) of Inert C & D Wastes was disposed as public fill. 0.000 (in tonnes) of Inert C & D Wastes and 0.100 (in tonnes) of Non-inert C & D Wastes were generated (from Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) in this reporting period. 0.000 (in tonnes) metals were generated and recycled (from Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) in this reporting period.

7.2.5     The Contractor was reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packing, Labelling and Storage of Chemical Waste.

7.3          Environmental Licenses and Permits

7.3.1     The valid environmental licenses and permits for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) during the reporting period are summarized in Appendix F. The Contractor of Contract No. HY/2013/06 was advised to register as a chemical waste producer when chemical waste is expected to generate for the foreseeable future from the operations (For Registration as Waste Producer Pursuant to Waste Disposal (Chemical Waste) (General) Regulation).

7.4          Implementation Status of Environmental Mitigation Measures

7.4.1     In response to the site audit findings, the Contractor carried out corrective actions.

7.4.2     A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix G. All necessary mitigation measures at this stage of works were implemented properly.

7.4.3     As confirmed by RSS, all surplus filling materials transported from Contract No. HY/2013/03 to other projects by marine vessels have been completed with the last batch delivered on 24 March 2018.

7.4.4     With respect to condition 3.26A of EP-353/2009/K approved by EPD on 11 April 2016, the numbers and operating periods of floating grout production facilities and floating concrete batching plants on-site to review on the compliance to this EP condition were checked. Under Contract No. HY/2013/03, no floating concrete batching plant was operated on-site during the reporting period.

7.4.5     As all the works in Box Culvert B had been completed, the silt curtain was uninstalled during the reporting period. The Dolphin Watching Plan (DWP) is no longer applicable.

7.5          Summary of Exceedance of the Environmental Quality Performance Limit

7.5.1      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

7.5.2      There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS2, AMS3B and AMS7B by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

7.5.3      There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

7.5.4      Summary of Action and Limit Level exceedance of water quality at the monitoring stations shown as shown at Table 4.1 shall be referred to the monthly EM&A report prepared by Contract No. HY/2013/01.

7.5.5      There were Action Level exceedances recorded on eight days by the Environmental Team of Contract No. HY/2013/01 during reporting period. After investigation, it was concluded that all exceedances were not relevant to Contract No. HY/2013/03. There was no Action and Limit Level exceedance recorded on other monitoring dates at the monitoring stations shown as shown at Table 4.1 by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

7.5.6      Ecological monitoring results at all transects are reported in the EM&A report prepared by Contract No. HY/2013/01.

7.6          Summary of Complaints, Notification of Summons and Successful Prosecution

7.6.1      There was no complaint received in relation to the environmental impact during the reporting period.

7.6.2      The complaint (ENPO-C0135) was received by HyD on 13 June 2018 and was referred by HyD to the ENPO. Then the ENPO forwarded the complaint by email to the ET (Materialab Consulants Ltd.) of the Contract No. HY/2013/03 on 25 June 2018.

Details of Complaint

            One complaint was received by HyD on 13 June 2018, with the following information provided by HyD:

The complainant complained about the construction site of HZMB artificial island. The construction site discharged muddy water into open waters.

            Investigation of Complaint

Date Complaint Investigated by Environmental Team: 26 June 2018

Summary of Investigation

Interview was conducted on 26 June 2018 with Mr. Marko Chan, Environmental Officer of CHEC. The major construction works under HY/2013/03 were completed. The construction works of Box Culvert B had been completed. As all the excavation works had been completed, there was no exposed earth grounds or stockpiles within the site area. The site protection measures for surface runoff collection and treatment before reaching manhole are effective. There was no discharge activities during the complained period. The drainage system in HZMB artificial island is in force. In addition, the amber rainstorm signal was issued by HKO on 13 June 2018. The source of muddy water could be resulted from the soil of landscaping works and the overflow from HZMB artificial island due to the heavy rain on 13 June 2018.

There was no exceedance recorded at the WQM station close to Box Culvert B during the complained period.

During the site walk conducted on 26 June 2018, Box Culvert B and the gully of drainage system have been visited. By observation, bunding was provided for all the gullies within the contract site area to prevent muddy runoff discharge to the drainage system, the water discharge to the open water from Box Culvert B looked clear.

Investigation Results

Base on the above, the ET of Contract No. HY/2013/03 conclude that the captioned complaint is not related to the construction activities of our contract. Nevertheless, the Contractor had been reminded to comply with the requirements stipulated in the Environmental Mitigation Implementation Schedule (EMIS) of the EM&A Manual, in particular:

Water Quality:

W2-

¡P      wastewater from temporary site facilities should be controlled to prevent direct discharge to surface or marine waters;

¡P      storm drainage shall be directed to storm drains via adequately designed sand/silt removal facilities such as sand traps, silt traps and sediment basins. Channels, earth bunds or sand bag barriers should be provided on site to properly direct stormwater to such silt removal facilities. Catchpits and perimeter channels should be constructed in advance of site formation works and earthworks;

¡P      silt removal facilities, channels and manholes shall be maintained and any deposited silt and grit shall be removed regularly, including specifically at the onset of and after each rainstorm;

¡P      rainwater pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities;

¡P      measures should be taken to prevent the washout of construction materials, soil, silt or debris into any drainage system;

¡P      open stockpiles of construction materials (e.g. aggregates and sand) on site should be covered with tarpaulin or similar fabric during rainstorms;

¡P      discharges of surface run-off into foul sewers must always be prevented in order not to unduly overload the foul sewerage system;

¡P      surface run-off from bunded areas should pass through oil/grease traps prior to discharge to the stormwater system.

Follow up status (complaints)

During weekly site audit on 7, 14 and 20 June 2018, ET confirmed that the Contractor had provided workable and effective water quality mitigation measures on site.

Recommendations to the Contractor

The Contractor was reminded to continue to fully implement all water quality mitigation measures and comply with the requirements of Water Discharge License.

Follow up Status (Overall)

The captioned complaint is not considered valid and therefore, no additional follow up is needed. However, ET has proposed several recommendations to the Contractor, and reminded on complying with the requirements stipulated in the Environmental Mitigation Implementation Schedule (EMIS) of the EM&A Manual. According to site audit conducted recently, ET confirmed all mitigation measures stipulated in the EMIS had been implemented during site audit on 7, 14 and 20 June 2018, in particular to the following aspect:

Water Quality:

W2:

¡P      wastewater from temporary site facilities should be controlled to prevent direct discharge to surface or marine waters;

¡P      storm drainage shall be directed to storm drains via adequately designed sand/silt removal facilities such as sand traps, silt traps and sediment basins. Channels, earth bunds or sand bag barriers should be provided on site to properly direct stormwater to such silt removal facilities. Catchpits and perimeter channels should be constructed in advance of site formation works and earthworks;

¡P      silt removal facilities, channels and manholes shall be maintained and any deposited silt and grit shall be removed regularly, including specifically at the onset of and after each rainstorm;

¡P      rainwater pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities;

¡P      measures should be taken to prevent the washout of construction materials, soil, silt or debris into any drainage system;

¡P      open stockpiles of construction materials (e.g. aggregates and sand) on site should be covered with tarpaulin or similar fabric during rainstorms;

¡P      discharges of surface run-off into foul sewers must always be prevented in order not to unduly overload the foul sewerage system;

¡P      surface run-off from bunded areas should pass through oil/grease traps prior to discharge to the stormwater system.

7.6.3      There was no notification for summons or prosecutions received in relation to the environmental impact during this reporting period.

7.6.4      Statistics on environmental complaints, notifications of summons and successful prosecutions are provided in Appendix H.