7.
ENVIRONMENTAL
SITE INSPECTION AND AUDIT
7.1
Site
Inspection
7.1.1
Site audits were carried out by ET on weekly basis
to monitor the implementation of proper environmental management practices and
mitigation measures in the Project site.
7.1.2
The landscape work of green roof for Contract No.
HY/2013/03 was commenced on 7 November 2017. The landscape work of all areas at
ground level for Contract No. HY/2013/03 was commenced at early February 2018. Detail
commencement date of each building were shown in Table 7.1. The implementation of mitigation measures for landscape
and visual resources recommended in the EIA Report were monitored during the
reporting period. Landscape and visual mitigation measures in accordance with
the EP, EIA and EM&A Manual were implemented by the Contractor.
Table 7.1 Commencement date of green roof for each
building
Building
No. of Green Roof |
Commencement
dates of planting for roof greening |
037 |
7 Nov
2017 |
043 |
20 Dec
2017 |
041 |
27 Dec
2017 |
026 |
22 Jan
2018 |
039 |
22 Jan
2018 |
All
areas at ground level |
Early
Feb 2018 |
031 |
8 Mar
2018 |
046 |
8 Mar
2018 |
7.1.3
The joint site audits for Contract No. HY/2013/03
(includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) were
conducted on 6, 14, 20 and 27 September 2018 by the representatives of
Engineer, Contractor, ET and IEC (IEC for 14 September 2018).
7.1.4
Particular observations during the site inspection
and corrective actions undertaken by the Contractor are described below:
For Contract No. HY/2013/03
6 September 2018
1.
The Contractor was reminded to remove the stagnant
water accumulated in the construction material at Portion G. The observation
was closed on 14 September 2018.
14 September 2018
1. The Contractor was reminded to provide drip tray
for the chemical at Portion H2. The observation was closed on 20 September 2018.
20 September 2018
1.
The Contractor was reminded to remove the stagnant
water accumulated in the construction material outside Building 049. The
observation was closed on 27 September 2018.
27 September 2018
1.
The Contractor was reminded to remove the general
waste accumulated in their work area. Follow-up actions for outstanding
observation will be checked in the upcoming site inspections and reported in
the coming reporting period.
For Contract
No. HY/2013/06 within Contract No. HY/2013/03 works area
6 September 2018
1.
Nil findings.
14 September 2018
1.
Nil findings.
20 September 2018
1.
Nil findings.
27 September 2018
1.
Nil findings.
7.2
Advice on the
Solid and Liquid Waste Management Status
7.2.1
The Contractor of Contract No. HY/2013/03 registered
as a chemical waste producer for the Contract. Sufficient numbers of receptacles
were available for general refuse collection and sorting.
7.2.2
The monthly summary of waste flow table for Contract
No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03
works area) are detailed in Appendix E.
7.2.3
Contract No. HY/2013/03 has been assigned to arrange
for delivery of surplus filling materials from Contract No. HY/2013/03 to other
projects, including Tuen Mun - Chek Lap Kok Link (TM-CLKL) project of HZMB, the
Airport Authority Hong Kong¡¦s Three Runway (3RS) Project, Wan Chai Development
Phase II project, Contract No. HY/2013/02 of HKBCF and Hong Kong Link Road
(HKLR) project of HZMB. As
confirmed by RSS, all surplus filling materials delivery to other
projects have been completed with the last batch on 7 May 2018. The total transported quantity up to
the last batch is 379.48358 (in¡¥000m3). The summary of surplus
filling materials delivered to other projects up to the end of May 2018 is
shown in Table 7.2.
Table 7.2 Summary of Surplus Filling
Materials Delivered from Contract No. HY/2013/03 to other projects
Month/Year |
Density
(in tonnes/m3) |
Quantity
disposed (in ¡¥000m3) |
|||||
To HY/2013/02 |
To TM-CLKL Project |
To 3RS Project |
To WDII Project |
To HKLR Project |
Total |
||
May
2017 |
2.3 |
0 |
12.637 |
0 |
0 |
0 |
12.637 |
June
2017 |
2.63925 |
0 |
14.769 |
11.238 |
0 |
0 |
26.007 |
July
2017 |
1.9 |
0 |
4.406 |
34.875 |
10.048 |
0.760 |
50.089 |
August
2017 |
1.9 |
0.480 |
0 |
67.942 |
2.761 |
7.455 |
78.638 |
September 2017 |
1.9 |
5.544 |
0 |
62.770 |
0 |
4.648 |
72.962 |
October
2017 |
/ |
3.384 |
0 |
45.92809 |
0 |
0 |
49.31209 |
November
2017 |
/ |
5.412 |
0 |
5.507 |
0 |
0 |
10.919 |
December 2017 |
/ |
12.57173 |
0 |
0 |
0 |
0 |
12.57173 |
January 2018 |
/ |
10.228 |
0 |
0 |
0 |
0 |
10.228 |
February 2018 |
/ |
0 |
0 |
0 |
0 |
0 |
0 |
March 2018 |
/ |
0.45276 |
0 |
0 |
0 |
0 |
0.45276 |
April 2018 |
/ |
0 |
42.544 |
0 |
0 |
0 |
42.544 |
May 2018 |
/ |
0 |
13.123 |
0 |
0 |
0 |
13.123 |
Total |
/ |
38.07249 |
87.479 |
228.26009 |
12.809 |
12.863 |
379.48358 |
Remarks:
The variation in density is due to different compositions of surplus
filling materials
There may be discrepancies in the total quantities with the quantities of
inert C&D materials stated in Appendix E and section 7.2.4, due to rounding
errors
No density was given from October 2017 to May 2018 due to the direct
volume figures as provided and confirmed by the RSS
7.2.4
0.000 (in¡¥000m3) of excavated marine
sediment (from Contract No. HY/2013/03), 0.213 (in¡¥000m3) of Inert C
& D Wastes and 0.444 (in¡¥000m3) of Non-inert C & D Wastes
were generated (from Contract No. HY/2013/03) in this reporting period. 0.000 (in¡¥000m3)
of Inert C & D Wastes were reused in other projects and 0.213 (in¡¥000m3)
of Inert C & D Wastes was disposed as public fill. 0.000 (in tonnes) of Inert
C & D Wastes and 0.020 (in tonnes) of Non-inert C & D Wastes were
generated (from Contract No. HY/2013/06 within Contract No. HY/2013/03 works
area) in this reporting period. 0.000 (in tonnes) metals were generated and
recycled (from Contract No. HY/2013/06 within Contract No. HY/2013/03 works
area) in this reporting period.
7.2.5
The Contractor was reminded that chemical waste
containers should be properly treated and stored temporarily in designated
chemical waste storage area on site in accordance with the Code of Practice on
the Packing, Labelling and Storage of Chemical Waste.
7.3
Environmental
Licenses and Permits
7.3.1
The valid
environmental licenses and permits for Contract No. HY/2013/03 (includes
Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) during the
reporting period are summarized in Appendix
F. The Contractor of Contract No. HY/2013/06 was advised to register as a
chemical waste producer when chemical waste is expected to generate for the
foreseeable future from the operations (For Registration as Waste Producer
Pursuant to Waste Disposal (Chemical Waste) (General) Regulation).
7.4
Implementation
Status of Environmental Mitigation Measures
7.4.1
In response to the site audit findings, the
Contractor carried out corrective actions.
7.4.2
A summary of
the Implementation Schedule of Environmental Mitigation Measures (EMIS) is
presented in Appendix G. All necessary
mitigation measures at this stage of works were implemented properly.
7.4.3
As
confirmed by RSS, all surplus filling materials transported from
Contract No. HY/2013/03 to other projects by marine vessels have been completed
with the last batch delivered on 24 March 2018.
7.4.4
With respect
to condition 3.26A of EP-353/2009/K approved by EPD on 11 April 2016, the
numbers and operating periods of floating grout production facilities and
floating concrete batching plants on-site to review on the compliance to this EP
condition were checked. Under Contract No. HY/2013/03, no floating concrete
batching plant was operated on-site during the reporting period.
7.4.5
As all the
works in Box Culvert B had been completed, the silt curtain was uninstalled in
July 2018. The Dolphin Watching Plan (DWP) is no longer applicable.
7.5
Summary of
Exceedance of the Environmental Quality Performance Limit
7.5.1
Summary of Action and Limit Level exceedance of 1-hr
TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A
report prepared by Contract No. HY/2011/03.
7.5.2
There was no Action and Limit Level exceedance of
1-hr TSP level and 24-hr TSP level recorded at station AMS2, AMS3C and AMS7B by
the Environmental Team of Contract No. HY/2013/01 during the reporting period.
7.5.3
There was no Action and Limit Level exceedance for noise
recorded at station NMS2 and station
NMS3C by the Environmental Team of Contract No. HY/2013/01 during the reporting
period.
7.5.4
Summary of Action and Limit Level exceedance of water
quality at the monitoring
stations shown as shown at Table 4.1 shall be
referred to the monthly EM&A report prepared by Contract No. HY/2013/01.
7.5.5
There were Action Level exceedances recorded on seven
days by the Environmental Team of Contract No. HY/2013/01 during reporting
period. After investigation, it was concluded that all exceedances were not
relevant to Contract No. HY/2013/03. There was no Action and Limit Level
exceedance recorded on other monitoring dates at the monitoring stations shown
as shown at Table 4.1 by the
Environmental Team of Contract No. HY/2013/01 during the reporting period.
7.5.6
Ecological monitoring results at all transects are
reported in the EM&A report prepared by Contract No. HY/2013/01.
7.6
Summary of
Complaints, Notification of Summons and Successful Prosecution
7.6.1
There
was no complaint received in relation to the environmental impact during the
reporting period. The details of cumulative statistics of Environmental
Complaints are provided in Appendix H.
7.6.2
There was no notification for summons or
prosecutions received in relation to the environmental impact during this
reporting period.
7.6.3
Statistics on environmental complaints,
notifications of summons and successful prosecutions are provided in Appendix H.