1.
INTRODUCTION
1.1
Basic Project Information
1.1.1
This
Quarterly Environmental Monitoring and Audit (EM&A) Report is prepared for
Contract No. HY/2013/03 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary
Crossing Facilities ¡V Vehicle Clearance Plazas and Ancillary Buildings and
Facilities¡¨ (includes the construction works of Contract No. HY/2013/06 ¡§Hong
Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Automatic
Vehicle Clearance Support System¡¨ within Contract No. HY/2013/03 works area) (hereafter
referred to as ¡§the Contract¡¨) for the Highways Department of Hong Kong Special
Administrative Region (HKSAR). The Contract was awarded to China Harbour
Engineering Co. Limited (construction works of Contract No. HY/2013/06 was
awarded to ATAL Technologies Limited within Contract No. HY/2013/03 works area)
(hereafter referred to as ¡§the Contractor¡¨) and MateriaLab
Consultants Limited (MCL) was appointed as the Environmental Team (ET) by the
Contractor.
1.1.2
Contract
No. HY/2013/03 (includes the construction works of Contract No. HY/2013/06
within Contract No. HY/2013/03 works area) is part of the ¡§Hong
Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities¡¨ (HZMB HKBCF)
Project which is a ¡§Designated Project¡¨ under Schedule 2 of the Environmental
Impact Assessment (EIA) Ordinance (Cap. 499) and for which an EIA Report
(Register No. AEIAR-145/2009) was prepared and approved. The current Environmental
Permit (EP) for HKBCF, namely No. EP-353/2009/K, was issued on 11 April 2016.
These documents are available through the EIA Ordinance Register. Commencement
of Contract No. HY/2013/03 took place on 10 April 2015 while the construction
works and the EM&A programme of Contract No. HY/2013/03 commenced on 29
August 2015 (commencement of Contract No. HY/2013/06 took place on 14 August
2015 while the construction works and the EM&A programme of Contract No.
HY/2013/06 within Contract No. HY/2013/03 works area commenced on 13 September
2016). The works areas of the contract are shown in Appendix A.
1.1.3
This is
the 9th Quarterly EM&A Report summarising the findings of EM&A
activities conducted under Contract No. HY/2013/03 from 01 September 2017 to 30
November 2017 (from 01 September 2017 to 30 November 2017 for the construction
works of Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) (the
¡§reporting period¡¨) and is submitted to fulfil Condition 16.4 of the Updated
EM&A Manual for HKBCF.
1.2
Project Organisation
1.2.1
The organisation chart and lines of
communication with respect to the on-site environmental management structure
together with the contact information of the key personnel are shown in Appendix B. The key personnel contact
names and numbers are summarized in Table
1.1 and Table 1.2.
Table
1.1 Contact Information of Key Personnel (for Contract No. HY/2013/03)
Party |
Position |
Contact Person |
Telephone No. |
Fax No. |
Engineer
or Engineer¡¦s Representative (AECOM
Asia Co. Ltd.) |
Chief Resident Engineer |
Mr. W. S. Ng |
3958 7400 |
3902
8800 |
Environmental
Project Office / Independent Environmental Checker (Ramboll Environ Hong Kong Limited) |
Environmental
Project Office Leader |
Mr. Y.
H. Hui |
3547
2133 |
3465
2899 |
Independent
Environmental Checker (IEC) |
Mr. |
3465
2888 |
3465 2899 |
|
Environmental
Site Supervisor |
Mr.
Ray Yan |
5181
8165 |
3465
2899 |
|
Contractor (China
Harbour Engineering Co. Ltd) |
Site
Agent |
Mr. Paul Pui |
9125 0700 |
2512
0427 |
Environmental
Officer |
Mr. Marko Chan |
9427 2879 |
2512
0427 |
|
Environmental
Team (MateriaLab Consultants Limited) |
Environmental
Team Leader (ETL) |
Mr.
Arthur Cheng |
3565
4115 |
2450
8032 |
24-hr
Complaint Hotline |
-- |
-- |
5236
7111 |
-- |
Table 1.2
Contact Information of Key Personnel (for Contract No. HY/2013/06 within
Contract No. HY/2013/03 works area)
Party |
Position |
Contact Person |
Telephone No. |
Fax No. |
Engineer
or Engineer¡¦s Representative (AECOM
Asia Co. Ltd.) |
Chief Resident Engineer |
Mr. W. S. Ng |
3958 7400 |
3902
8800 |
Environmental
Project Office / Independent Environmental Checker (Ramboll Environ Hong Kong Limited) |
Environmental
Project Office Leader |
Mr. Y.
H. Hui |
3547
2133 |
3465
2899 |
Independent
Environmental Checker (IEC) |
Mr. |
3465
2888 |
3465 2899 |
|
Environmental
Site Supervisor |
Mr.
Ray Yan |
5181
8165 |
3465
2899 |
|
Contractor (ATAL
Technologies Limited) |
Site
Agent |
Mr. Eric Yim |
2565 3355 |
3162
5217 |
Environmental
Officer |
Mr. W. Li |
2565 3137 |
3162
5217 |
|
Environmental
Team (MateriaLab Consultants Limited) |
Environmental
Team Leader (ETL) |
Mr.
Arthur Cheng |
3565
4115 |
2450
8032 |
24-hr
Complaint Hotline |
-- |
-- |
6509
0375 |
-- |
1.3
Construction Programme
1.3.1
The construction programme for Contract
No. HY/2013/03 (includes the construction works of HY/2013/06 within Contract
No. HY/2013/03 works area) are provided in Appendix
C.
1.4
Construction Works undertaken during the Reporting Period
1.4.1
A
summary of the construction activities undertaken during this reporting period
is shown below:
For Contract No. HY/2013/03
September 2017
1.
Building
at Portion A1, B, G, N, J, STP & Pumping Stations;
2.
CUE
Construction at Portion B, C & J;
3.
Drainage
& Sewerage Work, Water Main & Cable Duct at Portion B, H1, H2, J, P, G
& A1;
4.
Radiation
Screen Wall at Portion B, E P, N,M,C;
5.
Sign
Gantry Footing at Portion B;
6.
Sewerage
Pumping Station, High Mast Lighting Foundation & Box Culvert C at Portion G;
7.
Bridge
Works at A1 to A9;
8.
Site
Foundation Works at Portion K;
9.
Cover
Walkway at Portion H1 & H2;
10.
Box
Culvert B at Portion N; Shuttle kiosk & Subway at Portion E
11.
Deployment,
maintenance and inspection of silt curtain;
12.
Construction
of water outfall of box culvert; and
13.
Marine
sediment excavation activities from the land-based works and corresponding
disposal at the designated disposal sites within Hong Kong as allocated by the
Marine Fill Committee.
October 2017
1.
Building
at Portion A1, B, G, N, J, STP & Pumping Stations;
2. CUE Construction at Portion B, C &
J;
3. Drainage & Sewerage Work, Water Main
& Cable Duct at Portion B, H1, H2, J, P, G & A1;
4. Radiation Screen Wall at Portion B, E P,
N,M,C;
5. Sign Gantry Footing at Portion B;
6. Sewerage Pumping Station, High Mast
Lighting Foundation & Box Culvert C at Portion G;
7. Bridge Works at A1 to A9;
8. Site Foundation Works at Portion K;
9. Cover Walkway at Portion H1 & H2;
10. Box Culvert B at Portion N; Shuttle
kiosk & Subway at Portion E
11. Deployment, maintenance and inspection
of silt curtain;
12. Construction of water outfall of box
culvert; and
13. Marine sediment excavation activities
from the land-based works and corresponding disposal at the designated disposal
sites within Hong Kong as allocated by the Marine Fill Committee.
November 2017
1. Building at Portion A1, B, G, N, J, STP
& Pumping Stations;
2. CUE Construction at Portion B, C &
J;
3. Drainage & Sewerage Work, Water Main
& Cable Duct at Portion B, H1, H2, J, P, G & A1;
4. Radiation Screen Wall at Portion B, E P,
N, M, C;
5. Sign Gantry Footing at Portion B;
6. Sewerage Pumping Station, High Mast
Lighting Foundation & Box Culvert C at Portion G;
7. Bridge Works at A1 to A9;
8. Site Foundation Works at Portion K;
9. Cover Walkway at Portion H1 & H2;
10. Box Culvert B at Portion N;
11. Shuttle kiosk & Subway at Portion E.
For Contract No. HY/2013/06 within Contract No.
HY/2013/03 works area
September 2017
1.
Conduits & Wiring
installation at Building 037, kiosk and CUE works area.
October 2017
1.
Conduits & Wiring
installation at Building 037, kiosk and CUE works area.
November 2017
1.
Conduits & Wiring
installation at Building 037, kiosk and CUE works area.