2.            EM&A REQUIREMENTS

2.1          Summary of EM&A Requirements

2.1.1      The EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0). It should be noted that the air quality and noise monitoring works for the Contract are covered by Contract No. HY/2013/01 ¡§Hong Kong-Zhuhai-Macao-Bridge HKBCF ¡V Passenger Clearance Building¡¨ and Contract No. HY/2011/03 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill and HKBCF¡¨. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS2, AMS3B, AMS6 and AMS7B (According to the revised Contract Specific EM&A Manual (Rev. 9), the monitoring results for AMS2 and AMS3B will be reported in the monthly EM&A Reports prepared for Contract Nos. HY/2013/03 start from February 2018. The implementation of environmental monitoring for air quality, noise, water quality and marine ecology (dolphin monitoring) have been conducting by the ET for Contract No. HY/2013/01 of which the air quality monitoring station (AMS7) have been re-located to the alternative air quality monitoring station (AMS7B) since 06 February 2018), and noise monitoring at NMS2 and NMS3B, water quality monitoring at the locations shown in Figure 3 and ecological monitoring as shown in Figure 4 as part of EM&A programme if these monitoring stations are no longer covered under Contract Nos. HY/2013/01 and HY/2011/03. However, this is subject to ENPO¡¦s final decision on which ET should carry out the monitoring work at these stations.

The ET of the Contract or another ET of the HZMB project is required to conduct impact ecological monitoring at 24 transects as part of EM&A programme if these transects are no longer covered under Contract No. HY/2013/01. The impact ecological monitoring should adopt line-transect vessel survey method. The survey follows pre-set and fixed transect lines in the two areas defined by AFCD as: Northeast Lantau survey area and Northwest Lantau survey area. The co-ordinates for the transect lines and layout map are shown as in Figure 4.

2.1.2      A summary of air and noise monitoring locations are presented in Table 2.1. The location of air quality and noise monitoring stations are shown as in Figure 1 and Figure 2, respectively.

Table 2.1 Air Quality and Noise Monitoring Locations

Environmental Monitoring

Identification No.

Location Description

Air Quality

AMS2(1) (4)

Tung Chung Development Pier

AMS3B(1) (4)

Site Boundary of Site Office Area at Work Area WA2

AMS6(1)

Dragonair/CNAC (Group) Building (A80)

AMS7(1) (5)

Hong Kong SkyCity Marriott Hotel

AMS7B(1) (5)

3RS Site Offices

Noise

NMS2(2)

Seaview Crescent

NMS3B(2) (3)

Site Boundary of Site Office Area at WA2

                Remarks:

(1)    The ET of this Contract should conduct impact air quality monitoring at the AMS listed in the table as part of EM&A programme according to latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

(2)    The ET of this Contract should conduct impact noise monitoring at the NMS listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

(3)    The Action and Limit Levels for schools will be applied for this alternative monitoring location.

(4)    According to the revised Contract Specific EM&A Manual (Rev. 9), the monitoring results for AMS2 and AMS3B will be reported in the monthly EM&A Reports prepared for Contract Nos. HY/2013/03 start from Feb 2018.

(5)    Air quality monitoring station (AMS7) have been re-located to the alternative air quality monitoring station (AMS7B) since 06 Feb 2018

2.1.3      The water monitoring works for the Contract are covered by Contract No. HY/2013/01 ¡§Hong Kong-Zhuhai-Macao-Bridge HKBCF ¡V Passenger Clearance Building¡¨. The water quality monitoring station (SR3, SR10A and SR10B(N)) had been slightly re-located since 22 December 2017. A summary of water quality monitoring stations are presented in Table 2.2. The location of water quality monitoring stations are shown as in Figure 3.
................................................................... Table 2.2 Water Quality Monitoring Stations

Station

Description

East

North

IS5

Impact Station (Close to HKBCF construction site)

811579

817106

IS(Mf)6

Impact Station (Close to HKBCF construction site)

812101

817873

IS7

Impact Station (Close to HKBCF construction site)

812244

818777

IS8

Impact Station (Close to HKBCF construction site)

814251

818412

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

IS10(N)

Impact Station (Close to HKBCF construction site)

812942

820881

IS(Mf)11

Impact Station (Close to HKBCF construction site)

813562

820716

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS17

Impact Station (Close to HKBCF construction site)

814539

820391

SR3

Sensitive receivers (San Tau SSSI)

810525

816456

SR3(N)

Sensitive receivers (San Tau SSSI)

810689

816591

SR4(N)

Sensitive receivers (Tai Ho)

814705

817859

SR5(N)

Control Station

812569

821475

SR6

Sensitive receivers (Sha Chau and Lung Kwu Chau Marine Park)

805837

821818

SR7       

Sensitive receivers (Tai Mo Do)

814293

821431

SR10A

Sensitive receivers (Ma Wan FCZ) 1

823741

823495

SR10A(N) (1)

Sensitive receivers (Ma Wan FCZ) 1

823644

823484

SR10B(N)

Sensitive receivers (Ma Wan FCZ) 2

823683

823187

SR10B(N2) (1)

Sensitive receivers (Ma Wan FCZ) 2

823689

823159

CS(Mf)3(N)

Control Station

808814

822355

CS(Mf)5

Control Station

817990

821129

CS4

Control Station

810025

824004

CS6

Control Station

817028

823992

CSA(2]

Control Station

818103

823064

             Note:

(1) Additional monitoring station for Ma Wan FCZ

(2) Additional control monitoring station for Ma Wan FCZ

 

Remarks:

The ET of the Contract should conduct impact water quality monitoring at the WQMs listed in the table as part of EM&A programme according to latest notification from ENPO if water quality monitoring is no longer covered by another ET of the HZMB project. The ET of the Contract shall communicate and share the monitoring data to the ET(s) of the other contracts if the water quality monitoring station(s) is/are as part of EM&A programme. SR3(N), SR10A(N) and SR10B(N2) are alternative WQM Stations.

2.2          Monitoring Requirements

2.2.1      The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared by Contract No. HY/2013/01.

2.3          Action and Limit Levels

2.3.1      The Action and Limit Levels for 1-hr TSP and 24-hr TSP are provided in Table 2.3 and Table 2.4 respectively.

Table 2.3 Action and Limit Levels for 1-hour TSP

Monitoring Station

Action Level (µg/m³)

Limit Level (µg/m³)

AMS2

374

500

AMS3B

368

AMS6

360

AMS7

370

AMS7B

370

Table 2.4 Action and Limit Levels for 24-hour TSP

Monitoring Station

Action Level (µg/m³)

Limit Level (µg/m³)

AMS2

176

260

AMS3B

167

AMS6

173

AMS7

183

AMS7B

183

2.3.2      The Action and Limit Levels for construction noise are defined in Table 2.5.

Table 2.5 Action and Limit Level for Construction Noise

Monitoring Station

Action Level

Limit Level

For the Time Period 0700-1900 hrs. on Normal Weekdays

NMS2

When one documented complaint is received

75.0 dB (A) Leq (30 min.)

NMS3B

70.0 dB (A) Leq (30 min.)*

            Notes:

If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.

                * Reduce to 70 dB(A) for schools and 65 dB(A) during school examination period.

2.3.3      The Action and Limit Levels for Water Quality are provided in Table 2.6.

Table 2.6 Action and Limit Levels for Water Quality

Parameters

Action

Limit

DO in mg/L (Surface, Middle & Bottom)

Surface and Middle 5.0

Bottom 4.7

Surface and Middle = 4.2 (except 5 mg/L for FCZ)

Bottom = 3.6

SS in mg/L (depth-averaged) at all  monitoring  stations  and control stations

23.5 and 120% of upstream control station's SS at the same tide of the same day*

34.4 and 130% of upstream control station's SS at the same tide of the same day and 10mg/L for WSD Seawater intakes*

Turbidity  in  NTU  (depth averaged)

27.5 and 120% of upstream control station's turbidity at the same tide of the same day*

47.0 and 130% of upstream control station's turbidity at the same tide of the same day*

* Remarks:    Reference is made to EPD approval of adjustment of water quality assessment criteria issued and became effective on 18 February 2013.

Notes:

1.    ¡¨depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.

2.    For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

3.    For turbidity, SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

4.    All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

5.    The 1%-ile of baseline data for dissolved oxygen (surface and middle) and dissolved oxygen (bottom) are 4.2mg/L and 3.6mg/L respectively.

2.3.4      The Action and Limit Levels for Ecological Monitoring are provided in Table 2.7 and Table 2.8.

Table 2.7 Action and Limit Levels for Ecological Monitoring - Approach to Define Action Level (AL) and Limit Level (LL)

 

North Lantau Social Cluster

NEL

NWL

Action Level

(STG < 70% of baseline) &

(ANI < 70% of baseline)

(STG < 70% of baseline) &

(ANI < 70% of baseline)

Limit Level

[(STG < 40% of baseline) & (ANI < 40% of baseline)] AND

[ (STG < 40% of baseline) & (ANI < 40% of baseline)]

For North Lantau Social Cluster, action level will be trigger if either NEL or NWL fall below the criteria; limit level will be triggered if both NEL and NWL fall below the criteria.

Table 2.8 Derived Value of Action Level (AL) and Limit Level (LL) for Ecological Monitoring

 

North Lantau Social Cluster

NEL

NWL

Action Level

(STG < 4.2) & (ANI < 15.5 )

(STG < 6.9) & (ANI < 31.3)

Limit Level

[(STG < 2.4) & (ANI <8.9)] AND [ (STG < 3.9) & (ANI < 17.9)]

The ET of this Contract should conduct impact ecological monitoring as part of EM&A programme according to latest notification from ENPO when the monitoring transect(s) is/are no longer covered by another ET of the HZMB project.

2.3.5      If exceedance(s) at these transect(s) is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the quarterly EM&A Report.

2.4          Event and Action Plans

2.4.1      The event and action plans are provided in Appendix D.

2.5          Mitigation Measures

2.5.1      Environmental mitigation measures for the contract were recommended in the approved EIA Report. Appendix E lists the recommended mitigation measures and the implementation status.