3.            ENVIRONMENTAL MONITORING AND AUDIT

3.1          Air Quality Monitoring Results

3.1.1      The monitoring results for AMS6 are reported in the monthly EM&A Reports (for December 2017, January 2018 and February 2018) prepared for Contract Nos. HY/2011/03. The monitoring results for AMS2, AMS3B, AMS7 and AMS7B are reported in the monthly EM&A Reports (for December 2017, January 2018 and February 2018) prepared for Contract Nos. HY/2013/01.

3.1.2      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 is reported in the monthly EM&A Reports (for December 2017, January 2018 and February 2018) prepared by Contract No. HY/2011/03.

3.1.3      There was one Action and Limit Level exceedance of 24-hr TSP level recorded at station AMS3B by the Environmental Team of Contract No. HY/2013/01 on 23 December 2017. There were two Action and Limit Level exceedances of 24-hr TSP level recorded at station AMS2 and AMS3B by the Environmental Team of Contract No. HY/2013/01 on 17 January 2018. After investigation, it was concluded that all exceedances were not relevant to Contract No. HY/2013/03. There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded on other monitoring dates at station AMS2 and AMS3B by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

3.1.4      There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 and AMS7B by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

3.2          Noise Monitoring Results

3.2.1      The monitoring results for NMS2 and NMS3B are reported in the monthly EM&A Reports (for December 2017, January 2018 and February 2018) prepared for Contract No. HY/2013/01.

3.2.2      No noise exceedances were recorded at stations NMS2 and NMS3B by the ET of Contract No. HY/2013/01 during the reporting period.

3.3          Water Quality Monitoring Results

3.3.1      The monitoring results for the monitoring stations shown in Table 2.2 were reported in the monthly EM&A Report (for December 2017, January 2018 and February 2018) prepared for Contract No. HY/2013/01. There were Action and Limit Level exceedances recorded at different WQM stations during mid-ebb and mid-flood tide on nine days. The summary of water quality exceedances is shown in Table 3.1. After investigation, it was concluded that all exceedances were not relevant to Contract No. HY/2013/03.

Table 3.1   Action and Limit Levels for Water Quality

Station

Exceedance Level

DO (S&M)

DO (Bottom)

Turbidity

SS

Ebb

Flood

Ebb

Flood

Ebb

Flood

Ebb

Flood

IS5

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS(Mf6)

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS7

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS8

Action

0

0

0

0

0

0

1

(13 Dec)

2

(06 Dec, 08 Dec)

Limit

0

0

0

0

0

0

0

0

IS(Mf)9

Action

0

0

0

0

0

0

1

(11 Dec)

1

(06 Dec)

Limit

0

0

0

0

0

0

0

0

IS10(N)

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS(Mf)11

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS(Mf)16

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

IS17

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

SR3

Action

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

SR4(N)

Action

0

0

0

0

0

0

0

1

(08 Dec)

Limit

0

0

0

0

0

0

0

0

SR5(N)

Action

0

0

0

0

0

0

0

1

(06 Dec)

Limit

0

0

0

0

0

0

0

0

SR6

Action

0

0

0

0

0

0

4

(04 Dec,

08 Dec,

22 Dec, 31 Jan)

4

(06 Dec,

20 Dec,

22 Dec, 02 Feb)

Limit

0

0

0

0

0

0

0

0

SR7

Action

0

0

0

0

0

0

0

2

(04 Dec, 02 Feb)

Limit

0

0

0

0

0

0

0

0

SR10A

Action

0

0

0

0

0

0

0

1

(08 Dec)

Limit

0

0

0

0

0

0

0

0

SR10B(N)

Action

0

0

0

0

0

0

0

1

(04 Dec)

Limit

0

0

0

0

0

0

0

0

Note:  S&M: Surface & Middle

3.4          Ecology Monitoring Results

3.4.1      The dolphin survey results for all transects were reported in the monthly EM&A Reports (for December 2017, January 2018 and February 2018) prepared by Contract No. HY/2013/01. There was no Action and Limit Level exceedance recorded by the Environmental Team of Contract No. HY/2013/01 during the reporting period (December 2017 to February 2018).

3.5          Implementation of Environmental Measures

3.5.1      In response to the site audit findings, the Contractor carried out corrective actions. Details of site audit findings and the corrective actions during the reporting period are presented in Appendix F.

3.5.2      A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix E. All necessary mitigation measures at this stage of works were implemented properly.

3.5.3      Implementation status of Regular Marine Travel Route Plan (RMTRP) was checked by ET. In general, the Contractor has complied with the plan. Training of marine travel route for marine vessels operator was given to relevant staff and relevant records were kept properly. Marine traffic records which indicated the number of trips data for pelican barge, hopper barge, tug boat, floating concrete batching plant and derrick lighter on the implementation of RMTRP from December 2017 to February 2018 were checked by ET. The marine traffic records and geographical plots of all the vessels tracks to demonstrate the conformance of the vessel to the proposed route in December 2017, January 2018 and February 2018 were provided by Contractor to ER, IEC/ENPO for checking within the month of January 2018, February 2018 and March 2018 respectively. The implementation of marine traffic follows the Regular Marine Travel Route Plan with respect to ET¡¦s checking on the marine traffic records for the reporting period.

3.5.4      With respect to condition 3.26A of EP-353/2009/K approved by EPD on 11 April 2016, the numbers and operating periods of floating grout production facilities and floating concrete batching plants on-site to review on the compliance to this EP condition were checked. Under Contract No. HY/2013/03, no floating concrete batching plant was operated on-site during the reporting period.

3.5.5      As silt curtain was installed since May 2017, Dolphin Watching Plan (DWP) should be implemented. The status of silt curtain was reviewed by ET and there was no change on the status of silt curtain during the reporting period. Implementation status of DWP was checked by ET. The records of dolphin watching training, regular inspection of the silt curtains and visual inspection of waters surrounded by the silt curtain in December 2017, January 2018 and February 2018 would be provided to ER, ETL, IEC/ENPO for checking within the month of January 2018, February 2018 and March 2018 respectively.

3.5.6      The landscape work of green roof for Contract No. HY/2013/03 was commenced on 07 November 2017. Detail commencement date of each building were shown in Table 3.2. The implementation of mitigation measures for landscape and visual resources recommended in the EIA Report were monitoring during the reporting period. Landscape and visual mitigation measures in accordance with the EP, EIA and EM&A Manual were implemented by the Contractor.

Table 3.2 Commencement date of green roof for each building

Building No. of Green Roof

Commencement dates of planting for roof greening

037

07 Nov 2017

043

20 Dec 2017

041

27 Dec 2017

026

22 Jan 2018

039

22 Jan 2018

 

3.6          Advice on the Solid and Liquid Waste Management Status

3.6.1      The Contractor of Contract No. HY/2013/03 registered as a chemical waste producer for the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.

3.6.2      No extracted marine sediment was treated using cement solidification/stabilisation (Cement S/S) techniques under Contract No. HY/2013/03 during this reporting period. No marine sediment extracted from this Contract was disposed to the Marine Fill Committee (MFC) allocated disposal sites directly without treatment during this reporting period. As a practical mean, the disposal operation is managed by one contractor who is also responsible for applying dumping permit and its subsequent extension applications from EPD. Contract No. HY/2013/03 has been assigned to coordinate and arrange for disposal of extracted marine sediment from all three Contracts (Contract Nos. HY/2013/02, HY/2013/03 and HY/2013/04).

3.6.3      The barge for disposal of marine sediment was morn at the temporary loading and unloading at the east shore of the HKBCF Island, which has been being used by reclamation contractor (Contract No. HY/2010/02) for reclamation activities. In terms of safety consideration and to avoid mixing of sediment between contracts, each dumping date was allocated to one Contract. The quantity of marine sediment disposed on each date was from one Contract.

3.6.4      During dumping, Contractor of Contract No. HY/2013/03 is responsible for transporting the marine sediment from the site area of Contract No. HY/2013/03 to the barge. The estimated quantity of marine sediment in each truck is confirmed by Resident Site Staff of Contract Nos. HY/2013/02, HY/2013/03 and HY/2013/04. The trip tickets for transportation and disposal of marine sediment are collected and checked. Contract No. HY/2013/03 as the dumping permit holder is responsible for reporting to EPD the quantity disposed of as the condition stipulated in the dumping permit. The disposal site allocated to this Project are the Mud Pit CMP Vd of the Confined Marine Sediment Disposal Facility to the East of Sha Chau (ESC).

3.6.5      No marine sediment extracted from bored piling from this Contract was disposed to allocated dumping site during this reporting period. As confirmed by RSS, all marine sediments extracted from HY/2013/02, HY/2013/03 and HY/2013/04 have been completed with the last batch disposal on 30 August 2017. The summary of marine sediment disposed during this reporting period is shown in the following table:

Table 3.3 Summary of Marine Sediment Disposed to Dumping Site

Month/Year

Quantity disposed (in¡¥000m3)

 

HY/2013/02

HY/2013/03

HY/2013/04

Total

Dec 2017

0.000

0.000

0.000

0.000

Jan 2018

0.000

0.000

0.000

0.000

Feb 2018

0.000

0.000

0.000

0.000

Total

0.000

0.000

0.000

0.000

 

3.6.6      The summary of waste flow table for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) is detailed in Appendix G.

3.6.7      Contract No. HY/2013/03 has been assigned to arrange for delivery of surplus filling materials from Contract No. HY/2013/03 to other projects, including Tuen Mun - Chek Lap Kok Link (TM-CLKL) project of HZMB, the Airport Authority Hong Kong¡¦s Three Runway (3RS) Project, Wan Chai Development Phase II Project, Contract No. HY/2013/02 of HKBCF and Hong Kong Link Road (HKLR) project of HZMB. The estimated quantity of surplus filling materials is confirmed by Resident Site Staff of Contract No. HY/2013/03. The summary of surplus filling materials delivered to other projects up to the end of February 2018 is shown in Table 3.4.

Table 3.4 Summary of Surplus Filling Materials Delivered from Contract No. HY/2013/03 to other projects

Month/Year

Density (in tonnes/m3)

Quantity disposed (in ¡¥000m3)

To HY/2013/02

To TM-CLKL Project

To 3RS Project

To WDII Project

To HKLR Project

Total

May 2017

2.3

0

12.637

0

0

0

12.637

Jun 2017

2.63925

0

14.769

11.238

0

0

26.007

Jul 2017

1.9

0

4.406

34.875

10.048

0.760

50.089

Aug 2017

1.9

0.480

0

67.942

2.761

7.455

78.638

Sep 2017

1.9

5.544

0

62.770

0

4.648

72.962

Oct 2017

/

3.384

0

45.92809

0

0

49.31209

Nov 2017

/

5.412

0

5.507

0

0

10.919

Dec 2017

/

12.57173

0

0

0

0

12.57173

Jan 2018

/

10.228

0

0

0

0

10.228

Feb 2018

/

0

0

0

0

0

0

Total

/

37.61973

31.812

228.26009

12.809

12.863

323.36382

            Remarks:

ž   The variation in density is due to different compositions of surplus filling materials

ž  There may be discrepancies in the total quantities with the quantities of inert C&D materials stated in Appendix G, due to rounding errors

ž  No density was given from October 2017 to February 2018 due to the direct volume figures as provided and confirmed by the RSS

3.6.8      Contractor of Contract No. HY/2013/03¡¦s site arrangement for disposal of bentonite slurry to Tseung Kwan O Area 137 Fill Bank was checked by ET and formal consent has been obtained from Tseung Kwan O Area 137 Fill Bank for receiving used bentonite slurry generated from Contract No. HY/2013/03.

3.7          Environmental Licences and Permits

3.7.1     The valid environmental licences and permits for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) during the reporting period are summarized in Appendix H. The Contractor of Contract No. HY/2013/06 was advised to register as a chemical waste producer when chemical waste is expected to generate for the foreseeable future from the operations (For Registration as Waste Producer Pursuant to Waste Disposal (Chemical Waste) (General) Regulation).