4.
SUMMARY OF EXCEEDANCES, COMPLAINTS, NOTIFICATION OF SUMMONS
AND SUCCESSFUL PROSECUTION
4.1
Summary of Exceedance of the Environmental Quality
Performance Limit
4.1.1
Summary
of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at
AMS6 is reported in the monthly EM&A Reports (for June 2018, July 2018 and August
2018) prepared by Contract No. HY/2011/03.
4.1.2
There
was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level
recorded at station AMS2, AMS3B/AMS3C (Air quality monitoring station (AMS3B)
have been re-located to the alternative air quality monitoring station (AMS3C)
since 20 August 2018) and AMS7B by the
Environmental Team of Contract No. HY/2013/01 during the reporting period.
4.1.3
There
was no Action and Limit Level exceedance for noise recorded at station NMS2 and
station NMS3B/NMS3C (Noise monitoring station (NMS3B) have
been re-located to the alternative noise monitoring station (NMS3C) since 20
August 2018) by the Environmental Team of Contract
No. HY/2013/01 during the reporting period.
4.1.4
There
were Action and Limit Level exceedances recorded at different WQM stations recorded
on twenty-seven days during the reporting period.
The
monitoring and investigation results for the monitoring stations showed in Table 2.2 are reported in the monthly
EM&A Report prepared for Contract No. HY/2013/01.
There
was no Action and Limit Level exceedance recorded on other monitoring dates at
the monitoring stations shown as shown at Table
2.2 by the Environmental Team of Contract No. HY/2013/01 during the
reporting period.
Although
the exceedances were not relevant to Contract No. HY/2013/03, the Contractor
was reminded to continue to fully maintain all water quality mitigation
measures and prevent any water quality impact to seawater.
4.1.5
Ecological
monitoring results at all transects are reported in the EM&A report (for the
reporting period) prepared by Contract No. HY/2013/01.
4.2
Summary of Complaints, Notification of Summons and
Successful Prosecution
4.2.1
There
was one complaint received in relation to the environmental impact during the
reporting period. The summary of environmental complaints is presented in Table 4.1. The details of cumulative
statistics of Environmental Complaints are provided in Appendix I.
Table 4.1 Summary of Environmental
Complaints for the Reporting Period
Log No. |
Environmental
Complaint Ref. No. |
Date of
Complaint Receipt |
Description |
015 |
ENPO-C0135 |
13 June 2018 |
Water discharge |
The
complaint (ENPO-C0135) was received by HyD on 13 June
2018 and was referred by HyD to the ENPO. Then the
ENPO forwarded the complaint by email to the ET (Materialab
Consulants Ltd.) of the Contract No. HY/2013/03 on 25
June 2018. The complainant complained about the construction site of HZMB
artificial island. The construction site discharged muddy water into open
waters.
After
investigation, the ET of Contract No. HY/2013/03 (including Contract No.
HY/2013/06 within Contract No. HY/2013/03) concluded that the captioned
complaint is not related to the construction activities of our contract. Nevertheless,
the Contractor had been reminded to comply with the requirements stipulated in
the Environmental Mitigation Implementation Schedule (EMIS) of the EM&A
Manual, in particular:
• Water
Quality:
W2-
1.
wastewater from temporary site facilities should be
controlled to prevent direct discharge to surface or marine waters;
2.
storm drainage shall be directed to storm drains via
adequately designed sand/silt removal facilities such as sand traps, silt traps
and sediment basins. Channels, earth bunds or sand bag barriers should be
provided on site to properly direct stormwater to
such silt removal facilities. Catchpits and perimeter
channels should be constructed in advance of site formation works and
earthworks;
3.
silt removal facilities, channels and manholes shall
be maintained and any deposited silt and grit shall be removed regularly,
including specifically at the onset of and after each rainstorm;
4.
rainwater pumped out from trenches or foundation
excavations should be discharged into storm drains via silt removal facilities;
5.
measures should be taken to prevent the washout of
construction materials, soil, silt or debris into any drainage system;
6.
open stockpiles of construction materials (e.g.
aggregates and sand) on site should be covered with tarpaulin or similar fabric
during rainstorms;
7.
discharges of surface run-off into foul sewers must
always be prevented in order not to unduly overload the foul sewerage system;
8.
surface run-off from bunded
areas should pass through oil/grease traps prior to discharge to the stormwater system.
4.2.2
No notification of summons or
prosecutions was received during the reporting period.
4.2.3
Statistics
on notifications of summons and successful prosecutions are summarized in Appendix I.