5.            COMMENTS, RECOMMENDATIONS AND CONCLUSIONS

5.1          Comments

5.1.1      According to the environmental site inspections undertaken during the reporting period, the following recommendations were provided:

For Contract No. HY/2013/03

1.       CHEC was reminded to clean the U channel on site;

2.       CHEC was reminded to provide bunding on site to prevent overflow due to the heavy rain;

3.       CHEC was reminded to remove the chemical on site;

4.       CHEC was reminded to increase watering for the paved road on site;

5.       CHEC was reminded to remove the construction waste accumulated on site;

6.       CHEC was reminded to remove the stagnant water accumulated on site;

7.       CHEC was reminded to provide proper cover for the stockpile on site;

8.       CHEC was reminded to provide a new NRMM label for the generator on site;

9.       CHEC was reminded to provide drip tray for the hydraulic machine on site;

10.    CHEC was reminded to provide proper bunding for the gullies on site; and

11.    CHEC was reminded to remove the general waste accumulated on site.

For Contract No. HY/2013/06 within Contract No. HY/2013/03 works area

1.       The Contractor was reminded to remove the general waste accumulated in their work area on site.

5.1.2      A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix E. All necessary mitigation measures at this stage of works were implemented properly.

5.2          Recommendations

5.2.1      With implementation of the recommended environmental mitigation measures, the contract¡¦s environmental impacts were considered environmentally acceptable. The weekly environmental site inspections ensured that all the environmental mitigation measures recommended were effectively implemented.

5.2.2      The recommended environmental mitigation measures, as included in the EM&A programme, effectively minimize the potential environmental impacts from the contract. Also, the EM&A programme effectively monitored the environmental impacts from the construction activities and ensure the proper implementation of mitigation measures. No particular recommendation was advised for the improvement of the programme.

5.3          Conclusions

5.3.1      Commencement of Contract No. HY/2013/03 took place on 10 April 2015 and the construction works of Contract No. HY/2013/03 commenced on 29 August 2015 (commencement of Contract No. HY/2013/06 took place on 14 August 2015 and the construction works of Contract No. HY/2013/06 commenced on 13 September 2016 within Contract No. HY/2013/03 works area). This is the 12th Quarterly EM&A Report summarising the findings of EM&A activities conducted under Contract No. HY/2013/03 from 01 June 2018 to 31 August 2018 (includes the findings of EM&A activities conducted under Contract No. HY/2013/06 within Contract No. HY/2013/03 works area from 01 June 2018 to 31 August 2018).

5.3.2      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A Reports (for June 2018, July 2018 and August 2018) prepared by Contract No. HY/2011/03.

5.3.3      There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS2, AMS3B/AMS3C (Air quality monitoring station (AMS3B) have been re-located to the alternative air quality monitoring station (AMS3C) since 20 August 2018) and AMS7B by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

5.3.4      There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B/NMS3C (Noise monitoring station (NMS3B) have been re-located to the alternative noise monitoring station (NMS3C) since 20 August 2018) by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

5.3.5      There were Action and Limit Level exceedances recorded at different WQM stations recorded on twenty-seven days by the Environmental Team of Contract No. HY/2013/01 during reporting period. After investigation, it was concluded that all exceedances were not relevant to Contract No. HY/2013/03. There was no Action and Limit Level exceedance recorded on other monitoring dates at the monitoring stations shown as shown at Table 2.2 by the Environmental Team of Contract No. HY/2013/01 during the reporting period.

5.3.6      Ecological monitoring results at all transects are reported in the EM&A report prepared by Contract No. HY/2013/01.

5.3.7      Environmental site inspection was carried out on 07, 14, 20 and 28 June 2018, 05, 13, 20 and 26 July 2018, 02, 06, 17, 23 and 30 August 2018 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area). Recommendations on remedial actions were given to the Contractors for the deficiencies identified during the site inspections.

5.3.8      There was one complaint received in relation to the environmental impact during the reporting period. After investigation, the complaint was not related to Contract No. HY/2013/03.

5.3.9      There were no notifications of summons or prosecutions received during the reporting period.