3.            ENVIRONMENTAL MONITORING AND AUDIT

3.1          Air Quality Monitoring Results

3.1.1      The monitoring results for AMS6 are reported in the monthly EM&A Reports (for December 2018 and January 2019) prepared for Contract Nos. HY/2011/03. The monitoring results for AMS2, AMS3C and AMS7B are reported in the monthly EM&A Reports (for December 2018 and January 2019) prepared for Contract Nos. HY/2013/04.

3.1.2      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 is reported in the monthly EM&A Reports (December 2018 and January 2019) prepared by Contract No. HY/2011/03.

3.1.3      There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS2, AMS3C and AMS7B by the Environmental Team of Contract No. HY/2013/04 during the reporting period.

3.2          Noise Monitoring Results

3.2.1      The monitoring results for NMS2 and NMS3C are reported in the monthly EM&A Reports (for December 2018 and January 2019) prepared for Contract No. HY/2013/04.

3.2.2      No noise exceedances were recorded at station NMS2 and NMS3C by the ET of Contract No. HY/2013/04 during the reporting period.

3.3          Water Quality Monitoring Results

3.3.1      The monitoring and investigation results for the monitoring stations shown in Table 2.2 were reported in the monthly EM&A Report (December 2018 and January 2019) prepared for Contract No. HY/2013/04. There were Action Level exceedances recorded at different WQM stations recorded on three days. After investigation, it was concluded that all exceedances were not relevant to Contract No. HY/2013/03.

3.3.2      There was no Action and Limit Level exceedance recorded on other monitoring dates at the monitoring stations shown at Table 2.2 by the Environmental Team of Contract No. HY/2013/04 during the reporting period.

3.4          Ecology Monitoring Results

3.4.1      The dolphin survey results for all transects were reported in the monthly EM&A Reports (for December 2018 and January 2019) prepared by Contract No. HY/2013/04. There was no Action and Limit Level exceedance recorded by the Environmental Team of Contract No. HY/2013/04 during the reporting period (December 2018 to January 2019).

3.5          Implementation of Environmental Measures

3.5.1      As all the sections under Contract No. HY/2013/03 (includes the construction works of HY/2013/06 within Contract No. HY/2013/03 works area) were handed over to the relevant authorities on 24 October 2018 and the site had been changed to a closed area, no site audit was conducted during the reporting period.

3.5.2      A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix D. All necessary mitigation measures at this stage of works were implemented properly.

3.5.3      As confirmed by RSS, all surplus filling materials transported from Contract No. HY/2013/03 to other projects by marine vessels have been completed with the last batch delivered on 07 May 2018.

3.5.4      With respect to condition 3.26A of EP-353/2009/K approved by EPD on 11 April 2016, the numbers and operating periods of floating grout production facilities and floating concrete batching plants on-site to review on the compliance to this EP condition were checked. Under Contract No. HY/2013/03, no floating concrete batching plant was operated on-site during the reporting period.

3.5.5      As all the works in Box Culvert B had been completed, the silt curtain was uninstalled. The Dolphin Watching Plan (DWP) is no longer applicable.

3.5.6      The landscape work of green roof for Contract No. HY/2013/03 was commenced on 07 November 2017. The landscape work of all areas at ground level for Contract No. HY/2013/03 was commenced at early February 2018. Detail commencement date of each building were shown in Table 3.1. Bi-monthly landscape establishment monitoring was conducted on 25 Jan 2019.

Table 3.1 Commencement date of green roof for each building

Building No. of Green Roof

Commencement dates of planting for roof greening

037

07 Nov 2017

043

20 Dec 2017

041

27 Dec 2017

026

22 Jan 2018

039

22 Jan 2018

All areas at ground level

Early Feb 2018

031

08 Mar 2018

046

08 Mar 2018

3.6          Advice on the Solid and Liquid Waste Management Status

3.6.1      The Contractor of Contract No. HY/2013/03 registered as a chemical waste producer for the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.

3.6.2      No extracted marine sediment was treated using cement solidification/stabilisation (Cement S/S) techniques under Contract No. HY/2013/03 during this reporting period. No marine sediment extracted from this Contract was disposed to the Marine Fill Committee (MFC) allocated disposal sites directly without treatment during this reporting period. As a practical mean, the disposal operation is managed by one contractor who is also responsible for applying dumping permit and its subsequent extension applications from EPD. Contract No. HY/2013/03 has been assigned to coordinate and arrange for disposal of extracted marine sediment from all three Contracts (Contract Nos. HY/2013/02, HY/2013/03 and HY/2013/04).

3.6.3      The barge for disposal of marine sediment was morn at the temporary loading and unloading at the east shore of the HKBCF Island, which has been being used by reclamation contractor (Contract No. HY/2010/02) for reclamation activities. In terms of safety consideration and to avoid mixing of sediment between contracts, each dumping date was allocated to one Contract. The quantity of marine sediment disposed on each date was from one Contract.

3.6.4      During dumping, Contractor of Contract No. HY/2013/03 is responsible for transporting the marine sediment from the site area of Contract No. HY/2013/03 to the barge. The estimated quantity of marine sediment in each truck is confirmed by Resident Site Staff of Contract Nos. HY/2013/02, HY/2013/03 and HY/2013/04. The trip tickets for transportation and disposal of marine sediment are collected and checked. Contract No. HY/2013/03 as the dumping permit holder is responsible for reporting to EPD the quantity disposed of as the condition stipulated in the dumping permit. The disposal site allocated to this Project are the Mud Pit CMP Vd of the Confined Marine Sediment Disposal Facility to the East of Sha Chau (ESC).

3.6.5      No marine sediment extracted from bored piling from this Contract was disposed to allocated dumping site during this reporting period. As confirmed by RSS, all marine sediments extracted from HY/2013/02, HY/2013/03 and HY/2013/04 have been completed with the last batch disposal on 30 August 2017. The summary of marine sediment disposed during this reporting period is shown in the following table:

Table 3.2 Summary of Marine Sediment Disposed to Dumping Site

Month/Year

Quantity disposed (in¡¥000m3)

 

HY/2013/02

HY/2013/03

HY/2013/04

Total

Dec 2018

0.000

0.000

0.000

0.000

Jan 2019

0.000

0.000

0.000

0.000

Total

0.000

0.000

0.000

0.000

3.6.6      The summary of waste flow table for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) is detailed in Appendix E.

3.6.7      Contract No. HY/2013/03 has been assigned to arrange for delivery of surplus filling materials from Contract No. HY/2013/03 to other projects, including Tuen Mun - Chek Lap Kok Link (TM- CLKL) project of HZMB, the Airport Authority Hong Kong¡¦s Three Runway (3RS) Project, Wan Chai Development Phase II project, Contract No. HY/2013/02 of HKBCF and Hong Kong Link Road (HKLR) project of HZMB. As confirmed by RSS, all surplus filling materials delivery to other projects have been completed with the last batch on 07 May 2018. The total transported quantity up to the last batch is 379.48358 (in¡¥000m³). The summary of surplus filling materials delivered to other projects up to the end of May 2018 is shown in Table 3.3.

Table 3.3 Summary of Surplus Filling Materials Delivered from Contract No. HY/2013/03 to other projects

Month/Year

Density (in tonnes/m3)

Quantity disposed (in ¡¥000m3)

To HY/2013/02

To TM-CLKL Project

To 3RS Project

To WDII Project

To HKLR Project

Total

May 2017

2.3

0

12.637

0

0

0

12.637

Jun 2017

2.63925

0

14.769

11.238

0

0

26.007

Jul 2017

1.9

0

4.406

34.875

10.048

0.760

50.089

Aug 2017

1.9

0.480

0

67.942

2.761

7.455

78.638

Sep 2017

1.9

5.544

0

62.770

0

4.648

72.962

Oct 2017

/

3.384

0

45.92809

0

0

49.31209

Nov 2017

/

5.412

0

5.507

0

0

10.919

Dec 2017

/

12.57173

0

0

0

0

12.57173

Jan 2018

/

10.228

0

0

0

0

10.228

Feb 2018

/

0

0

0

0

0

0

Mar 2018

/

0.45276

0

0

0

0

0.45276

Apr 2018

/

0

42.544

0

0

0

42.544

May 2018

/

0

13.123

0

0

0

13.123

Total

/

38.07249

87.479

228.26009

12.809

12.863

379.48358

            Remarks:

ž   The variation in density is due to different compositions of surplus filling materials

ž  There may be discrepancies in the total quantities with the quantities of inert C&D materials stated in Appendix E, due to rounding errors

ž  No density was given from October 2017 to May 2018 due to the direct volume figures as provided and confirmed by the RSS

3.7          Environmental Licences and Permits

3.7.1     The valid environmental licences and permits for Contract No. HY/2013/03 (includes Contract No. HY/2013/06 within Contract No. HY/2013/03 works area) during the reporting period are summarized in Appendix F. The Contractor of Contract No. HY/2013/06 was advised to register as a chemical waste producer when chemical waste is expected to generate for the foreseeable future from the operations (For Registration as Waste Producer Pursuant to Waste Disposal (Chemical Waste) (General) Regulation).