Certified by Environmental Team Leader

Verified by Independent Environmental Leader

 

 


Contract No. HY/2013/04 HZMB HKBCF – Infrastructure Works Stage II (Southern Portion)

Quarterly EM&A Report for April 2016 to June 2016

July 2016

China State Construction Engineering (Hong Kong) Limited

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Mott MacDonald, 20/F AIA Kowloon Tower, Landmark East, 100 How Ming Street, Kwun Tong, Kowloon, Hong Kong
t +852 2828 5757 f +852 2827 1823 w    w www.mottmac.com

 

 

 

 

 

 


Information class:

Standard

This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Contents

 

 

 

 

Chapter    Title                                                                                                                           Page

1.1______ Basic Project Information___________________________________________________________ 1

1.2______ Project Organisation______________________________________________________________ 1

1.3______ Construction Programme__________________________________________________________ 2

1.4______ Construction Works undertaken during the Reporting Period________________________________ 2

2.1______ Summary of EM&A Requirements____________________________________________________ 3

2.2______ Monitoring Requirements__________________________________________________________ 3

2.3______ Action and Limit Levels____________________________________________________________ 4

2.4______ Event and Action Plans____________________________________________________________ 4

2.5______ Mitigation Measures______________________________________________________________ 4

3.1______ Air Quality Monitoring Results_______________________________________________________ 5

3.2______ Noise Monitoring Results___________________________________________________________ 5

3.3______ Implementation of Environmental Measures____________________________________________ 5

3.4______ Advice on the Solid and Liquid Waste Management Status_________________________________ 5

3.4.1_____ Disposal of Marine Sediment Extracted from Bored Piling Works____________________________ 6

3.5______ Environmental Licences and Permits_________________________________________________ 7

4.1______ Summary of Exceedance of the Environmental Quality Performance Limit_____________________ 8

4.2______ Summary of Complaints, Notification of Summons and Successful Prosecution_________________ 8

5.1______ Comments_____________________________________________________________________ 9

5.2______ Recommendations_______________________________________________________________ 9

5.3______ Conclusions____________________________________________________________________ 9

 

Tables

Table 1.1:__ Contact Information of Key Personnel 1

Table 2.1:__ Construction Dust Monitoring Locations 3

Table 2.2:__ Action and Limit Levels for 1-hour TSP_ 4

Table 2.3:__ Action and Limit Levels for 24-hour TSP_ 4

Table 2.4:__ Action and Limit Level for Construction Noise_ 4

Table 3.1:__ Summary of Marine Sediment disposed to Dumping Site via Contract No. HY/2013/03_ 7

 

 

Figures

Figure 1                 Location of Air Quality Monitoring Stations

Figure 2                 Location of Noise Monitoring Stations

 

Appendices

Appendix A.          Location of Works Areas

Appendix B.          Project Organization for Environmental Works

Appendix C.         Construction Programme

Appendix D.         Event and Action Plan

Appendix E.          Implementation Schedule for Environmental Mitigation Measures (EMIS)

Appendix F.          Site Audit Findings and Corrective Actions

Appendix G.         Waste Flow Table

Appendix H.         Environmental Licenses and Permits

Appendix I.           Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions

 

 

 

 

 

 

 

 

 


Executive Summary

 

 

 

This Quarterly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract No. HY/2013/04 “Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Infrastructure Works Stage II (Southern Portion)” (hereafter referred to as “the Contract”) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to China State Construction Engineering (Hong Kong) Limited (hereafter referred to as “the Contractor”) and Mott MacDonald Hong Kong Limited (MMHK) was appointed as the Environmental Team (ET) by the Contractor.

The Contract is part of the “Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities” (HZMB HKBCF) Project which is a “Designated Project” under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499) and for which an EIA Report (Register No. AEIAR-145/2009) was prepared and approved. The current Environmental Permit (EP) for HKBCF, namely No. EP-353/2009/K, was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. Commencement of the Contract took place on 13 March 2015 and the construction works commenced on 13 July 2015.

Mott MacDonald Hong Kong Limited has been appointed by the Contractor to implement the Environmental Monitoring & Audit (EM&A) programme for the Contract in accordance with the Updated EM&A Manual for HKBCF (Version 1.0) and will be providing environmental team services for the Contract. This is the 4th Quarterly EM&A Report for the Contract which summaries findings of the EM&A works during the reporting period from 1 April 2016 to 30 June 2016 (the “reporting period”).

Environmental Monitoring and Audit Progress

The EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0).  It should be noted that the air quality and noise monitoring works for the Contract are covered by Contract No. HY/2010/02 “Hong Kong-Zhuhai-Macao Bridge HKBCF – Reclamation Works” and Contract No. HY/2011/03 “Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between Scenic Hill and HKBCF”.  The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 and AMS7 and noise monitoring at NMS2 and NMS3B as part of EM&A programme if these monitoring stations are no longer covered under Contract Nos. HY/2010/02 and HY/2011/03.  However, this is subject to ENPO’s final decision on which ET should carry out the monitoring work at these stations. 

The dates of site inspection during the reporting period are listed below:

ˇ  7, 14, 18 and 26 April, 3, 10, 16, 23 and 31 May and 7, 13, 20 and 28 June 2016

Breaches of Action and Limit Levels

Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 is reported in the monthly EM&A report prepared by Contract No. HY/2011/03.

There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

Complaint Log

There was no complaint received in relation to the environmental impact during the reporting period.

Notifications of Summons and Successful Prosecutions

There were no notifications of summons or prosecutions received during this reporting period.

Reporting Changes

During the reporting period, an application for variation of Environmental Permit for the Project (submitted on 24 March 2016) was approved by EPD on 11 April 2016 with the issue of Environmental Permit No. EP-353/2009/K.

 

 

 

 

 


1             Introduction

 

 

 

1.1            Basic Project Information

This Quarterly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract No. HY/2013/04 “Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Infrastructure Works Stage II (Southern Portion)” (hereafter referred to as “the Contract”) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to China State Construction Engineering (Hong Kong) Limited (hereafter referred to as “the Contractor”) and Mott MacDonald Hong Kong Limited (MMHK) was appointed as the Environmental Team (ET) by the Contractor.

The Contract is part of the Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities” (HZMB HKBCF) Project which is a “Designated Project under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499) and for which an EIA Report (Register No. AEIAR-145/2009) was prepared and approved. The current Environmental Permit (EP) for HKBCF, namely No. EP-353/2009/K, was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. Commencement of the Contract took place on 13 March 2015 and the construction works commenced on 13 July 2015. The works areas of the contract are shown in Appendix A.

This is the 4th Quarterly EM&A Report summarising the findings of EM&A activities conducted under the Contract from 1 April 2016 to 30 June 2016 (the “reporting period”).

1.2            Project Organisation

The organisation chart and lines of communication with respect to the on-site environmental management structure together with the contact information of the key personnel are shown in Appendix B. The key personnel contact names and numbers are summarized in Table 1.1. 

Table 1.1:      Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

Engineer or Engineer’s Representative

(AECOM Asia Co. Ltd.)

Chief Resident Engineer

Alfred Cheng

3958 7471

3468 2076

Environmental Project Office / Independent Environmental Checker (Ramboll Environ Hong Kong Limited)

Environmental Project Office Leader

Y H Hui

3465 2888

3465 2899

 

Independent Environmental Checker

Raymond Dai

3465 2888

3465 2899

 

Environmental Site Supervisor

Ray Yan

5181 8165

3465 2899

Contractor

(China State Construction Engineering (Hong Kong) Limited)

Site Agent

Eddie Tang

9863 7686

2459 4336

Environmental Officer

Gary Ng

9475 6832

2459 4336

Environmental Team

(Mott MacDonald Hong Kong Limited)

Environmental Team Leader

Gary Chow 

 

2828 5874

2827 1823

24-hour Complaint Hotline

-

-

5236 7111

-

1.3            Construction Programme

The Construction Works Programme of the Project is provided in Appendix C.

1.4            Construction Works undertaken during the Reporting Period

A summary of the construction activities undertaken during this reporting period is shown below:

ˇ  Pre-drilling: 33 no. completed

ˇ  Bored Pile: 46 no. completed

ˇ  Driven H Pile: 91 no. completed

ˇ  Pile Cap: 2 no. completed

ˇ  Generation of excavated marine sediment and transport to HKBCF Contract No. HY/2013/03 for disposal.

No marine works were conducted under this contract during the reporting period.

 

 

2             EM&A Requirements

 

 

 

 

2.1            Summary of EM&A Requirements

The EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0).  It should be noted that the air quality and noise monitoring works for the Contract are covered by Contract No. HY/2010/02 “Hong Kong-Zhuhai-Macao Bridge HKBCF – Reclamation Works” and Contract No. HY/2011/03 “Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between Scenic Hill and HKBCF”.  The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 and AMS7 and noise monitoring at NMS2 and NMS3B as part of EM&A programme if these monitoring stations are no longer covered under Contract Nos. HY/2010/02 and HY/2011/03.  However, this is subject to ENPO’s final decision on which ET should carry out the monitoring work at these stations. 

A summary of air and noise monitoring locations are presented in Table 2.1. The location of air quality and noise monitoring stations are shown as in Figure 1 and Figure 2, respectively.

Table 2.1:      Construction Dust Monitoring Locations

Environmental Monitoring

Identification No.

Location Description

Air Quality

AMS6(1)

Dragonair/CNAC (Group) Building

 

AMS7 (1)

Hong Kong SkyCity Marriot Hotel

Noise

NMS2(2)

Seaview Crescent

 

NMS3B(2) (3)

Site Boundary of Site Office Area at Works Area WA2

Remarks:               

(1)           The ET of this Contract should conduct impact air quality monitoring at the AMS listed in the table as part of EM&A programme according to latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

(2)           The ET of this Contract should conduct impact noise monitoring at the NMS listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

(3)           The Action and Limit Levels for schools will be applied for this alternative monitoring location.

2.2            Monitoring Requirements

The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared for Contract Nos. HY/2010/02 and HY/2011/03.

2.3            Action and Limit Levels

The Action and Limit Levels for 1-hr TSP and 24-hr TSP are provided in Table 2.2 and Table 2.3 respectively.

Table 2.2:      Action and Limit Levels for 1-hour TSP

Monitoring Station 

Action Level, mg/m3

Limit Level, mg/m3

AMS6 – Dragonair / SNAC (Group) Building (HKIA)

360

500

AMS7 – Hong Kong SkyCity Marriot Hotel

370

500

Table 2.3:      Action and Limit Levels for 24-hour TSP

Monitoring Station 

Action Level, mg/m3

Limit Level, mg/m3

AMS6 – Dragonair / SNAC (Group) Building (HKIA)

173

260

AMS7 – Hong Kong SkyCity Marriot Hotel

183

260

If exceedance(s) at these stations is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

The Action and Limit Levels for construction noise are defined in Table 2.4.

Table 2.4:      Action and Limit Level for Construction Noise

Parameter

Action Level

Limit Level

07:00 – 19:00 hours on normal weekdays

When one documented complaint is received

75 dB(A)*

Notes:     If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
* Reduce to 70 dB(A) for schools and 65 dB(A) during school examination period.

If exceedance(s) at these stations is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

2.4            Event and Action Plans

The event and action plans for air quality and noise are provided in Appendix D.

2.5            Mitigation Measures

Environmental mitigation measures for the contract were recommended in the approved EIA Report.  Appendix E lists the recommended mitigation measures and the implementation status. 

 

 

 

3             Environmental Monitoring and Audit

 

 

 

 

3.1            Air Quality Monitoring Results

The monitoring results for AMS6 and AMS7 are reported in the monthly EM&A Reports (for April, May and June 2016) prepared for Contract Nos. HY/2011/03 and HY/2010/02 respectively.

Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 is reported in the monthly EM&A Reports (for April, May and June 2016) prepared by Contract No. HY/2011/03.

There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

3.2            Noise Monitoring Results

The monitoring results for NMS2 and NMS3B are reported in the monthly EM&A Reports (for April, May and June 2016) prepared for Contract No. HY/2010/02. 

No noise exceedances were recorded at stations NMS2 and NMS3B by the ET of Contract No. HY/2010/02 during the reporting period.

3.3            Implementation of Environmental Measures

In response to the site audit findings, the Contractor carried out corrective actions. Details of site audit findings and the corrective actions during the reporting period are presented in Appendix F.

A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix E.  Most of the necessary mitigation measures were implemented properly.

The Contractor waters 8 times per day on all exposed soil within the project site and associated works areas when construction activities are being undertaken.

3.4            Advice on the Solid and Liquid Waste Management Status

The Contractor registered as a chemical waste producer for the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting. As a practical means, the disposal operation is managed by a single HKBCF contractor who is also responsible for applying dumping permit and its subsequent extension applications from EPD. Contract No. HY/2013/03 has been assigned to coordinate and arrange for disposal of extracted marine sediment from this Contract.

There was no generation of excavated sediment for treatment during this reporting period. Any treatment of excavated marine sediment will be conducted using cement solidification/stabilization (Cement S/S) techniques and the treated sediment will be reused onsite for either backfilling or landscaping (e.g. berm material).

The summary of waste flow table is detailed in Appendix G.

The Contractor was reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packing, Labelling and Storage of Chemical Waste.

3.4.1        Disposal of Marine Sediment Extracted from Bored Piling Works

3.4.1.1      Background

After the acceptance of the review of the approved Sediment Quality Report (SQR) for this Project under EPD letter dated 19 August 2015, an approval to dispose the marine sediment extracted from bored piling for this Project was then approved under memo from Secretary, Marine Fill Committee (MFC) of CEDD dated 20 August 2015 for the disposal of marine sediment extracted from bored piling works. The disposal sites allocated to this Project are the Mud Pit CMP2 of the Confined Marine Sediment Disposal Facility to the South of The Brothers (or at the East of Sha Chau). As advised by CEDD in the memo dated 19 February 2016, from 00:00 on 22 March 2016 onward, the disposal space at CMP2 of the South of The Brothers is closed and all disposal of contaminated sediment is to be carried out at CMP Vd to the East of Sha Chau (ESC).

There was no generation of excavated sediment for treatment during this reporting period. The marine sediment extracted from this Contract was disposed to the MFC allocated disposal sites directly without treatment.

3.4.1.2      Dumping Arrangements

The barge for disposal of marine sediment will morn at the temporary loading and unloading at the east shore of the HKBCF Island, which has been being used by reclamation contractor (Contract No. HY/2010/02) for reclamation activities. In terms of safety consideration and to avoid mixing of sediment between contracts, each dumping date will be allocated to one Contract. The quantity of marine sediment disposed on each date is from one Contract.

During dumping, each Contractor is responsible for transporting the marine sediment from his site area to the barge. The estimated quantity of marine sediment in each truck is confirmed by Resident Site Staff of each Contract. The trip tickets for transportation and disposal of marine sediment are collected and checked. Contract No. HY/2013/03 as the dumping permit holder is responsible for reporting to EPD the quantity disposed of as the condition stipulated in the dumping permit.

3.4.1.3      Reporting

Marine sediment extracted from bored piling in this Contract was disposed to allocated dumping site via Contract No. HY/2013/03 on 11, 12, 18, 19, 20, 21, 22 and 23 April, and 18, 25 and 30 June 2016. The quantities disposed up to end of June 2016 are in following table (Table 3.1):

Table 3.1:      Summary of Marine Sediment disposed to Dumping Site via Contract No. HY/2013/03

Month/Year

Quantity Disposed (m3)

Up to end March 2016

5,446

April 2016

5,028

May 2016

0

June 2016

1,578

Total =

12,052

Note: For monthly breakdown of these quantities, please refer to the waste flow table in Appendix G.

3.5            Environmental Licences and Permits

The valid environmental licences and permits during the reporting period are summarized in Appendix H.

 

 

 

 

4             Summary of Exceedances, Complaints, Notification of Summons and Successful Prosecution

 

 

 

 

 

4.1            Summary of Exceedance of the Environmental Quality Performance Limit

Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 is reported in the monthly EM&A Reports (for April, May and June 2016) prepared by Contract No. HY/2011/03.

There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

4.2            Summary of Complaints, Notification of Summons and Successful Prosecution

There was no complaint received in relation to the environmental impact during the reporting period. No notification of summons or prosecutions was received during the reporting period.

Statistics on notifications of summons and successful prosecutions are summarized in Appendix I.

 

 

 

5             Comments, Recommendations and Conclusions

 

 

 

 

5.1            Comments

According to the environmental site inspections undertaken during the reporting period, the following recommendations were provided:

ˇ  The Contractor was reminded to implement suitable mitigation measures for the excavated marine sediment stockpile in accordance with the PS.

ˇ  The Contractor was reminded to remove stagnant water from drip trays.

ˇ  The Contractor was reminded to ensure that all NRMMs operated on-site are approved/exempted and affixed with requisite label, as required under the relevant regulation.

ˇ  The Contractor was reminded to provide drip trays for chemical containers.

ˇ  The Contractor was reminded to close the engine doors of a mobile generator during operation.

ˇ  The Contractor was reminded to properly dispose of loose general refuse, cans and bottles.

ˇ  The Contractor was reminded to clear oily water from drip tray and handle it as chemical waste.

A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix E.  Most of the necessary mitigation measures were implemented properly.

5.2            Recommendations

With implementation of the recommended environmental mitigation measures, the contract’s environmental impacts were considered environmentally acceptable. The weekly environmental site inspections ensured that all the environmental mitigation measures recommended were effectively implemented.

The recommended environmental mitigation measures, as included in the EM&A programme, effectively minimize the potential environmental impacts from the contract. Also, the EM&A programme effectively monitored the environmental impacts from the construction activities and ensure the proper implementation of mitigation measures. No particular recommendation was advised for the improvement of the programme.

5.3            Conclusions

Commencement of the Contract took place on 13 March 2015 and the construction works of the Contract commenced on 13 July 2015. This is the 4th Quarterly EM&A Report summarising the findings of EM&A activities conducted under the Contract from 1 April 2016 to 30 June 2016.

Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A Reports (for April, May and June 2016) prepared by Contract No. HY/2011/03.

There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7 by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

Environmental site inspection was carried out on 7, 14, 18 and 26 April, 3, 10, 16, 23 and 31 May and 7, 13, 20 and 28 June 2016. Recommendations on remedial actions were given to the Contractors for the deficiencies identified during the site inspections.

There was no complaint received in relation to the environmental impact during the reporting period.

There were no notifications of summons or prosecutions received during the reporting period.

 

 

 

 

 


Figures

 

 

 

 

Appendix A.   Location of Works Areas

 

 

 

 

Appendix B. Project Organization for Environmental Works

 

 

 

 

 

Appendix C.   Construction Programme

 

 

 

 

Appendix D.   Event and Action Plan

 

 

 

 

 

Appendix E.  Implementation Schedule for Environmental Mitigation Measures (EMIS)

 

 

 

 

 

 

 

Appendix F.    Site Audit Findings and Corrective Actions

 

 

 

 

 

Appendix G.  Waste Flow Table

 

 

 

 

 

 

Appendix H.   Environmental Licenses and Permits

 

 

 

 

 

 

 

Appendix I.     Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions