Contract No. HY/2014/05
Hong Kong-Zhuhai-Macao Bridge
Hong Kong
Boundary Crossing Facilities ¡V Remaining Ancillary Buildings and Facilities
Monthly EM&A Report
No. 13
(Covering the Period
from 1 March 2017 to 31 March 2017)
7 April 2017
Revision 0
Main Contractor Environmental
Team
Contents
Executive
Summary
1.4 Construction
Works Undertaken During the Reporting Period
2....... Air Quality Monitoring
4....... Environmental Site Inspection and Audit
4.2 Advice
on the Solid and Liquid Waste Management Status
4.3 Environmental
Licenses and Permits
4.4 Implementation Status of Environmental
Mitigation Measures
4.5 Summary of Exceedance of the Environmental
Quality Performance Limit
4.6 Summary of Complaints, Notification of
Summons and Successful Prosecution
5.1 Construction Programme for the Coming Months
5.2 Environmental Site Inspection Schedule for
the Coming Month
Figures
Figure 2.1 Location
of Air Quality
Monitoring Stations
Figure 3.1 Location
of Noise Monitoring Stations
Appendices
Appendix A Location of
Works Areas
Appendix B Project
Organization for Environmental Works
Appendix C Construction
Programme
Appendix D Event
and Action Plan
Appendix F Environmental
Licenses and Permits
Appendix G Implementation
Schedule for Environmental Mitigation Measures (EMIS)
Executive Summary
This
Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for
Contract No. HY/2014/05 Hong Kong-Zhuhai-Macao Bridge
Hong Kong Boundary Crossing Facilities (HZMB HKBCF)
¡V Remaining
Ancillary Buildings and Facilities (includes the construction works of Contract
No. HY/2013/06 Hong Kong-Zhuhai-Macao Bridge Hong
Kong Boundary Crossing Facilities ¡V Automatic Vehicle Clearance Support System and
Contract No. HY/2014/04 Hong Kong-Zhuhai-Macao Bridge Hong Kong
Boundary Crossing Facilities ¡V Gantry Type X-ray Vehicle Inspection System within
Contract No. HY/2014/05 works area) (hereafter referred to as ¡§the Contract¡¨)
for the Highways Department of Hong Kong Special Administrative Region (HKSAR).
Contract No. HY/2014/05 was awarded to Leighton ¡V Chun Wo Joint Venture (construction works of Contract No.
HY/2013/06 was awarded to ATAL Technologies Limited and Contract No. HY/2014/04
was awarded to Rapiscan Systems Pte Ltd within Contract No. HY/2014/05
works area) (hereafter referred to as ¡§the Contractor¡¨) and Atkins China
Limited was appointed as the Environmental Team (ET) by the Contractor.
Contract
No. HY/2014/05 (includes the construction works of Contract No. HY/2013/06 and Contract No. HY/2014/04
within Contract No. HY/2014/05 works area) is part of HZMB HKBCF Project
which is a ¡§Designated Project¡¨ under Schedule 2 of the Environmental Impact
Assessment Ordinance (EIAO) (Cap 499) and Environmental Impact Assessment (EIA)
Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016.
These documents are available through the EIA Ordinance Register. The
construction works
of the
Contract No.
HY/2014/05 commenced on 29 February 2016 while the construction works of the
Contract No. HY/2013/06 and Contract No. HY/2014/04 within Contract No. HY/2014/05 works area
commenced on 3 January 2017 and 13 February 2017 respectively.
Atkins
China Limited has been appointed by the Contractor to implement the
Environmental Monitoring & Audit (EM&A) programme for the Contract in
accordance with the Updated EM&A Manual for HKBCF (Version 1.0) and
will be providing environmental team services to the Contract.
This
is the thirteen monthly EM&A Report for the Contract No.
HY/2014/05 which summarizes findings of the EM&A works during the reporting
period from 1 to 31 March 2017 (includes the construction works of Contract No.
HY/2013/06 and Contract No. HY/2014/04
within Contract No. HY/2014/05 works area).
Environmental Monitoring and Audit Progress
The
monthly EM&A programme was undertaken in accordance with the Updated EM&A
Manual for HKBCF (Version 1.0). It
should be noted that the air quality and noise monitoring
works for the Contract are covered by Contract No. HY/2010/02
Hong Kong-Zhuhai-Macao
Bridge HKBCF ¡V Reclamation Works and Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V
Section between Scenic Hill and HKBCF.
The ET of the Contract or another ET of the HZMB project is required to conduct
impact air quality monitoring at AMS6 and AMS7 and noise monitoring at NMS2 and
NMS3B as part of EM&A programme if these monitoring stations are no longer
covered under Contract Nos. HY/2010/02 and HY/2011/03. However,
this is subject to ENPO¡¦s final decision on which ET should carry out the
monitoring work at these stations.
The dates of site inspection for the Contract No. HY/2014/05 (includes the
construction works of Contract No. HY/2013/06 and Contract
No. HY/2014/04 within Contract No. HY/2014/05
works area) during the reporting period are listed below:
Environmental Site Inspection: 1,
8, 15, 22 and 29 March 2017
Breaches of Action and Limit Levels
Summary
of Action and Limit Level exceedance of 1-hr TSP
level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A
report prepared by Contract No. HY/2011/03.
There
was no Action and Limit Level exceedance of 1-hr TSP
level and 24-hr TSP level recorded at AMS7 by the Environmental Team of
Contract No. HY/2010/02 during the reporting period.
There
was no Action and Limit Level exceedance for noise
recorded at NMS2 and NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.
Complaint Log
There
was one complaint received in relation to the environmental impact during the
reporting period. For noise and water quality nuisance, it is found that the
noise and water quality nuisance is not related to Contract No. HY/2014/05
(includes the construction works of Contract No. HY/2013/06
and Contract No. HY/2014/04 within Contract No.
HY/2014/05 works area) after investigation and no follow-up action is required.
Notifications of Summons and Successful
Prosecutions
There
were no notifications of summons or prosecutions received during this reporting
period.
Reporting Change
There was no reporting change during the reporting period.
Future Key Issues
The
future key issues to be undertaken in the upcoming month include:
For Contract No. HY/2014/05
¡P
Earth
Works for Buildings 050A1, 050A2 and 050H2
¡P
Raft
foundation for Buildings 032, 044, 045 and 050H1
¡P
Construction
of RC Structure of Buildings 022, 023, 032, 044, 045 and 050H1
¡P
Installation
of window wall of Building 045
¡P
ABWF
works (Internal Finishes) of Buildings 021, 025, 044, 045, 053, 058 and 059
¡P
ABWF
works (External Finishes) of Buildings 025, 032, 053, 058 and 059
¡P
ABWF
works (Roof Finishes) of Buildings 021, 023, 025, 032 and 053
¡P
Dog
Swimming Pool of Building 022
¡P
Utilities
and Drainage installation of Building 053
For Contract No. HY/2013/06 within Contract No.
HY/2014/05 works area
¡P
Conceal
Conduit Installation at Buildings 025 and 032
For Contract No. HY/2014/04 within Contract No. HY/2014/05 works area
¡P
Hole
drilling at Buildings 058 and 059
¡P
Rebar
scanning at Buildings 058 and 059
¡P
Installation
of rails at Buildings 058 and 059
¡P
Welding
works at Buildings 058 and 059
For
Contract No. HY/2014/05
(i)
Construction of the following
ancillary buildings and facilities including architectural and builder works,
structural steel canopy, reinforced concrete frames, foundations, curtain wall
facade, building services and electrical and mechanical works:
•
Public Toilets at Vehicle Clearance
Plaza (VCP);
•
Customs and Excise Department
(C&ED) Dangerous Good Store (Building 021);
•
Customs Detective Dog Base Building
(Building 022);
•
C&ED Outbound Cargo Examination
Building and Examination Platform (Building 023);
•
Inbound Private Car Annexure
(Building 025);
•
Outbound Private Car Annexure
(Building 032);
•
E&M maintenance Building
(Building 044);
•
Highways Depot & Administration
Building (Building 045);
•
Outbound X-ray Building (Building
053);
•
Outbound X-ray Scan Tunnel (Building
058); and
•
Inbound X-ray Scan Tunnel (Building
059).
(ii)
Construction of civil provisions,
cable containment and power supply for the following systems:
•
Automatic Vehicle Clearance Support
System (AVCSS) installed by Contract No. HY/2013/06; and
•
Gantry Type X-ray Vehicle Inspection
System installed by Contract No. HY/2014/04.
(iii)
Supply and installation of Mobile
X-ray Vehicle Inspection System and other standalone equipment;
(iv) Construction
of minor civil engineering works at the periphery of buildings;
(v)
Construction of minor Landscape hardworks and softworks; and
(vi) Other
works which are shown on Drawings or specified in the Specification or which
may be ordered in accordance with the Contract.
For
Contract No. HY/2013/06
within Contract No. HY/2014/05 works area
(i)
The Automatic Vehicle Clearance
Support System amid to increasing traffic flow for Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities;
(ii)
Responsible for designs and develops
a set of tailor-made computer monitoring and control systems to for daily
security operation; and
(iii)
The Clearance Workstations at 72
vehicle clearance kiosks, Customs and Excise¡¦s inbound and outbound traffic
control centers as well as a Vehicle Tracking System.
For
Contract No. HY/2014/04 within Contract No. HY/2014/05 works area
(i)
The Gantry Type X-ray Vehicle
Inspection System (GXRVIS) aims to provide an integrated, innovative, efficient
and effective vehicle inspection system at the inbound and outbound boundary
control points of Hong Kong-Zhuhai-Macao Bridge Hong
Kong Boundary Crossing Facilities (HKBCF) for supporting the operations of
Customs & Excise Department (C&ED);
(ii)
Design, supply, deliver to HKBCF,
installation, test and commissioning and maintenance of two sets of Gantry Type
X-ray Vehicle Inspection System and all related components necessary for the complete
operation of the system; and
(iii)
Design, supply, install, test,
commission and maintain of the Radioactive Threat Detection Systems integrated
into the Gantry Type X-ray Vehicle Inspection Systems.
Table 1‑1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
For Contract No. HY/2014/05 |
||||
Engineer or Engineer¡¦s Representative |
Chief Resident Engineer |
Michael Tovey |
3958 7339 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker (Ramboll Environ Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Albert Chan |
3973 0514 |
3621 0180 |
Environmental Officer |
Stephen Tsang |
3973 1806 |
3621 0180 |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint
hotline |
--- |
--- |
3958 7300 |
--- |
For Contract No. HY/2013/06 within Contract No.
HY/2014/05 works area |
||||
Engineer or Engineer¡¦s Representative |
Chief Resident Engineer |
Michael Tovey |
3958 7339 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker (Ramboll Environ Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Mr. Eric Yim |
2565 3355 |
3162 5217 |
Environmental Officer |
Mr. W. Li |
2565 3137 |
3162 5217 |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint hotline |
--- |
--- |
6509 0375 |
--- |
For Contract No. HY/2014/04
within Contract No. HY/2014/05 works area |
||||
Engineer or Engineer¡¦s Representative |
Chief Resident Engineer |
Michael Tovey |
3958 7339 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker (Ramboll Environ Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Ringo Yau |
9833 1402 |
2707 0816 |
Environmental Officer |
Clarie Tsang |
6371 1362 |
--- |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint hotline |
--- |
--- |
9833 1420 |
--- |
For Contract No. HY/2014/05
¡P
Earth
Works for Buildings 050H1 and 050H2
¡P
Raft
foundation for Buildings 032, 044, 045 and 050H1
¡P
Construction
of RC Structure of Buildings 022, 023, 025, 032, 044, 045 and 053
¡P
Installation
of window wall of Building 045
¡P
ABWF
works (Internal Finishes) of Buildings 021, 025, 053, 058 and 059
¡P
ABWF
works (External Finishes) of Buildings 025, 032, 053, 058 and 059
¡P
ABWF
works (Roof Finishes) of Buildings 021, 032 and 025
¡P
Dog
Swimming Pool of Building 022
¡P
Utilities
and Drainage installation of Building 053 and 058
For
Contract No. HY/2013/06 within Contract
No. HY/2014/05 works area
¡P
Conceal
Conduit Installation Buildings 025 and 032
For
Contract No. HY/2014/04 within Contract
No. HY/2014/05 works area
¡P
Hole
drilling at Buildings 058 and 059
¡P
Rebar
scanning at Buildings 058 and 059
¡P
Installation
of rails at Buildings 058 and 059
¡P
Welding
works at Buildings 058 and 059
Table 2‑1 Construction
Dust Monitoring Locations
ID |
Location
Description |
AMS 6(1) |
Dragonair/CNAC (Group)
Building |
AMS 7(1) |
Hong Kong SkyCity Marriott
Hotel |
Remark:
(1) The ET of this Contract should conduct impact air
quality monitoring at the AMS listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring
station(s) is/are no longer covered by another ET of the HZMB project.
Table 2‑2 Action
and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 6 ¡V Dragonair / CNAC
(Group) Building (HKIA) |
360 |
500 |
AMS 7 - Hong Kong SkyCity Marriott
Hotel |
370 |
Table 2‑3 Action
and Limit Levels for 24-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 6 ¡V Dragonair / CNAC
(Group) Building (HKIA) |
173 |
260 |
AMS 7 - Hong Kong SkyCity
Marriott Hotel |
183 |
Table 3‑1 Construction
Noise Monitoring Locations
ID |
Location Description |
NMS2(1) |
Seaview Crescent |
NMS3B(1)(2) |
Site
Boundary of Site Office
Area at Works Area WA2 |
Remarks:
(1)
The ET of
this Contract should conduct impact noise monitoring at the NMS listed in the
table as part of EM&A programme according to the latest notification from ENPO when the monitoring
station(s) is/are no longer covered by another ET of the HZMB project.
(2)
The Action
and Limit Levels for schools will be applied for this alternative monitoring
location.
Table 3‑2 Action
and Limit Level for Construction Noise
Parameter |
Action Level |
Limit Level |
07:00 ¡V 19:00 hours
on normal weekdays |
When one
documented complaint is received |
75 dB(A)* |
Notes :
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
* Limit level is 70 dB(A) for schools and 65 dB(A) during school
examination period.
Table 4‑1 Summary
of Environmental Site Inspections for Contract No. HY/2014/05
Date of Audit |
Observations |
Actions Taken by Contractor /
Recommendation |
Date of Observations Closed |
22 February 2017 |
1.
A chemical container was found without drip tray at Building 044. |
1.
The chemical container was removed at Building 044. |
1
March 2017 |
1 March 2017 |
No particular
environmental issue was recorded during the site inspection. |
Nil. |
Nil. |
8 March 2017 |
1. An Environmental Permit was not displayed at
site exit and vehicle access at Building 022. |
1. The Environmental
Permit was displayed at site exit and vehicle access at Building 022. |
15 March 2017 |
15 March 2017 |
1. The chemical container was found without drip tray
at Building 044. 2. The oily water was accumulated in the drip tray
at Building 032. |
1. The chemical
container was removed at Building 044. 2. The oily water
Building 032 was absorbed by sand/soil and the contaminated sand/soil was
treated as chemical waste for proper disposal. |
22 March 2017 |
22 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
29 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
Table 4‑2 Summary
of Environmental Site Inspections for Contract No. HY/2013/06
within Contract No. HY/2014/05 works area
Date of Audit |
Observations |
Actions Taken by Contractor /
Recommendation |
Date of Observations Closed |
1 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
8 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
15 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
22 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
29 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
Table 4-3 Summary
of Environmental Site Inspections for Contract No. HY/2014/04
within Contract No. HY/2014/05 works area
Date of Audit |
Observations |
Actions Taken by Contractor /
Recommendation |
Date of Observations Closed |
1 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
8 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
15 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
22 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
29 March 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
Table 4-4 A Summary of Environmental Complaints for the Reporting Month
Environmental Complaint No. |
Date of Complaint Received |
Description of Environmental Complaints |
003 |
28 March 2017 |
Noise and Water Quality |
Table 5-1 Construction
Activities for April 2017
Site Area |
Description of Activities |
For Contract No. HY/2014/05 |
|
Buildings
050A1, 050A2 and 050H2 |
Earth Works |
Buildings
032, 044, 045 and 050H1 |
Raft foundation |
Buildings
022, 023, 032, 044, 045 and 050H1 |
Construction of RC Structure |
Building
045 |
Installation of window wall |
Buildings
021, 025, 044, 045, 053, 058 and 059 |
ABWF works (Internal Finishes) |
Buildings
025, 032, 053, 058 and 059 |
ABWF works (External Finishes) |
Buildings
021, 023, 025, 032 and 053 |
ABWF works (Roof Finishes) |
Building
022 |
Dog Swimming Pool |
Building
053 |
Utilities and Drainage installation |
For Contract No. HY/2013/06 within Contract No.
HY/2014/05 works area |
|
Buildings
025 and 032 |
Conceal Conduit Installation |
For Contract No. HY/2014/04 within Contract No.
HY/2014/05 works area |
|
Buildings
058 and 059 |
Hole drilling |
Buildings
058 and 059 |
Rebar scanning |
Buildings
058 and 059 |
Installation of rails |
Buildings
058 and 059 |
Welding works |