Contract No. HY/2014/05
Hong
Kong-Zhuhai-Macao Bridge
Hong Kong
Boundary Crossing Facilities ¡V Remaining Ancillary Buildings and Facilities
Monthly EM&A Report
No. 15
(Covering the Period from
1 May 2017 to 31 May 2017)
9 June 2017
Revision 1
Main Contractor Environmental
Team
Contents
Executive
Summary
1.4 Construction
Works Undertaken During the Reporting Period
2....... Air Quality Monitoring
4....... Environmental Site Inspection and Audit
4.2 Advice
on the Solid and Liquid Waste Management Status
4.3 Environmental
Licenses and Permits
4.4 Implementation Status of Environmental
Mitigation Measures
4.5 Summary of Exceedance of the Environmental
Quality Performance Limit
4.6 Summary of Complaints, Notification of
Summons and Successful Prosecution
5.1 Construction Programme for the Coming Months
5.2 Environmental Site Inspection Schedule for
the Coming Month
Figures
Figure
2.1 Location
of Air Quality
Monitoring Stations
Figure
3.1 Location
of Noise Monitoring Stations
Appendices
Appendix A Location of
Works Areas
Appendix B Project
Organization for Environmental Works
Appendix C Construction
Programme
Appendix D Event and
Action Plan
Appendix
F Environmental
Licenses and Permits
Appendix G Implementation
Schedule for Environmental Mitigation Measures (EMIS)
Executive Summary
This
Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for
Contract No. HY/2014/05 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary
Crossing Facilities (HZMB HKBCF) ¡V Remaining Ancillary
Buildings and Facilities (includes the construction works of Contract No.
HY/2013/06 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities
¡V Automatic Vehicle Clearance Support System and Contract No. HY/2014/04
Hong
Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Gantry Type
X-ray Vehicle Inspection System within Contract No. HY/2014/05 works area)
(hereafter referred to as ¡§the Contract¡¨) for the Highways Department of Hong
Kong Special Administrative Region (HKSAR). Contract No. HY/2014/05 was awarded
to Leighton ¡V Chun Wo Joint Venture (construction works of Contract No.
HY/2013/06 was awarded to ATAL Technologies Limited and Contract No. HY/2014/04
was awarded to Rapiscan
Systems Pte Ltd within Contract No. HY/2014/05 works area) (hereafter referred
to as ¡§the Contractor¡¨) and Atkins China Limited was appointed as the
Environmental Team (ET) by the Contractor.
Contract
No. HY/2014/05 (includes the construction works of Contract No. HY/2013/06 and
Contract No. HY/2014/04 within Contract No. HY/2014/05 works area) is part of
HZMB HKBCF Project which is a ¡§Designated Project¡¨ under Schedule 2 of the
Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental
Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project.
The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016.
These documents are available through the EIA Ordinance Register. The
construction works
of the
Contract No.
HY/2014/05 commenced on 29 February 2016 while the construction works of the
Contract No. HY/2013/06 and Contract No. HY/2014/04 within Contract No.
HY/2014/05 works area commenced on 3 January 2017 and 13 February 2017 respectively.
Atkins
China Limited has been appointed by the Contractor to implement the
Environmental Monitoring & Audit (EM&A) programme for the Contract in
accordance with the Updated EM&A Manual for HKBCF (Version 1.0) and will
be providing environmental team services to the Contract.
This
is the fifteen monthly EM&A Report for the Contract No.
HY/2014/05 which summarizes findings of the EM&A works during the reporting
period from 1 to 31 May 2017 (includes the construction works of Contract No.
HY/2013/06 and Contract No. HY/2014/04 within Contract No. HY/2014/05 works
area).
Environmental Monitoring and Audit Progress
The
monthly EM&A programme was undertaken in accordance with the Updated
EM&A Manual for HKBCF (Version 1.0). It should be noted that the air quality
and noise monitoring works for the Contract are covered by
Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡V Reclamation Works and
Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V
Section between Scenic Hill and HKBCF.
The ET of the Contract or another ET of the HZMB project is required to
conduct impact air quality monitoring at AMS6 and AMS7 and noise monitoring at
NMS2 and NMS3B as part of EM&A programme if these monitoring stations are
no longer covered under Contract Nos. HY/2010/02 and HY/2011/03. However,
this is subject to ENPO¡¦s final decision on which ET should carry out the
monitoring work at these stations.
The dates of site inspection for the Contract No. HY/2014/05
(includes the construction works of Contract No. HY/2013/06 and Contract No.
HY/2014/04 within Contract No. HY/2014/05 works area) during
the reporting
period are listed below:
Environmental Site Inspection: 4,
10, 17, 25 and 31 May 2017
Breaches of Action and Limit Levels
Summary
of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at
AMS6 shall be referred to the monthly EM&A report prepared by Contract No.
HY/2011/03.
There
was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level
recorded at AMS7 by the Environmental Team of Contract No. HY/2010/02 during
the reporting period.
There
was no Action and Limit Level exceedance for noise recorded at NMS2 and NMS3B
by the Environmental Team of Contract No. HY/2010/02 during the reporting
period.
Complaint Log
There
was one complaint received in relation to the environmental impact during the
reporting period. The complaint investigation is being undertaken and will be reported
in the next reporting period.
Notifications of Summons and Successful
Prosecutions
There
were no notifications of summons or prosecutions received during this reporting
period.
Reporting Change
There was no reporting change during the reporting period.
Future Key Issues
The
future key issues to be undertaken in the upcoming month include:
For
Contract No. HY/2014/05
¡P
Construction
of RC Structure of Buildings 023, 050A1, 050H1, 050H2 and 050A2
¡P
ABWF
works (Internal Finishes) of Buildings 021, 022, 023, 025, 032, 044, 045,
050A1, 050A2, 053, 058 and 059
¡P
ABWF
works (External Finishes) of Buildings 021, 022, 023, 025, 045, 050A1, 050H2,
058 and 059
¡P
ABWF
works (Roof Finishes) of Buildings 022, 023, 025, 032, 044, 045, 050H2, 053,
058 and 059
¡P
MEP
installation of Buildings 021, 022, 023, 025, 032, 044, 045, 053, 058 and 059
¡P
Utilities
and Drainage installation of Building 025, 032, 050A1, 050A2, 050H2, 053, 058
and 059
For
Contract No. HY/2013/06 within Contract No. HY/2014/05 works area
¡P
Conceal
Conduit Installation at Buildings 023, 025 and 032
For Contract No. HY/2014/04 within Contract No. HY/2014/05 works area
¡P
Cabling
Works at Buildings 053 and 054
¡P
Installation
of Doors at Building 058 and 059
For Contract No. HY/2014/05
(i)
Construction of the following
ancillary buildings and facilities including architectural and builder works,
structural steel canopy, reinforced concrete frames, foundations, curtain wall
facade, building services and electrical and mechanical works:
•
Public Toilets at Vehicle Clearance
Plaza (VCP);
•
Customs and Excise Department (C&ED)
Dangerous Good Store (Building 021);
•
Customs Detective Dog Base Building
(Building 022);
•
C&ED Outbound Cargo Examination
Building and Examination Platform (Building 023);
•
Inbound Private Car Annexure
(Building 025);
•
Outbound Private Car Annexure (Building
032);
•
E&M maintenance Building
(Building 044);
•
Highways Depot & Administration
Building (Building 045);
•
Outbound X-ray Building (Building
053);
•
Outbound X-ray Scan Tunnel (Building
058); and
•
Inbound X-ray Scan Tunnel (Building
059).
(ii)
Construction of civil provisions,
cable containment and power supply for the following systems:
•
Automatic Vehicle Clearance Support
System (AVCSS) installed by Contract No. HY/2013/06; and
•
Gantry Type X-ray Vehicle Inspection
System installed by Contract No. HY/2014/04.
(iii) Supply
and installation of Mobile X-ray Vehicle Inspection System and other standalone
equipment;
(iv) Construction
of minor civil engineering works at the periphery of buildings;
(v)
Construction of minor Landscape hardworks and softworks; and
(vi) Other
works which are shown on Drawings or specified in the Specification or which
may be ordered in accordance with the Contract.
For Contract No. HY/2013/06
within Contract No. HY/2014/05 works area
(i)
The Automatic Vehicle Clearance
Support System amid to increasing traffic flow for Hong Kong-Zhuhai-Macao
Bridge Hong Kong Boundary Crossing Facilities;
(ii)
Responsible for designs and develops
a set of tailor-made computer monitoring and control systems to for daily
security operation; and
(iii) The
Clearance Workstations at 72 vehicle clearance kiosks, Customs and Excise¡¦s
inbound and outbound traffic control centers as well as a Vehicle Tracking
System.
For Contract
No. HY/2014/04 within Contract No. HY/2014/05 works area
(i)
The Gantry Type X-ray Vehicle
Inspection System (GXRVIS) aims to provide an integrated, innovative, efficient
and effective vehicle inspection system at the inbound and outbound boundary
control points of Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing
Facilities (HKBCF) for supporting the operations of Customs & Excise
Department (C&ED);
(ii)
Design, supply, deliver to HKBCF,
installation, test and commissioning and maintenance of two sets of Gantry Type
X-ray Vehicle Inspection System and all related components necessary for the
complete operation of the system; and
(iii) Design,
supply, install, test, commission and maintain of the Radioactive Threat
Detection Systems integrated into the Gantry Type X-ray Vehicle Inspection
Systems.
Table 1‑1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
For Contract No. HY/2014/05 |
||||
Engineer or Engineer¡¦s Representative |
Chief Registered Architect |
Malcolm Sage |
3958 7330 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker (Ramboll Environ Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Albert Chan |
3973 0514 |
3621 0180 |
Environmental Officer |
Stephen Tsang |
3973 1806 |
3621 0180 |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours
complaint hotline |
--- |
--- |
3958 7300 |
--- |
For Contract No. HY/2013/06 within Contract No.
HY/2014/05 works area |
||||
Engineer or Engineer¡¦s Representative |
Chief Registered Architect |
Malcolm Sage |
3958 7330 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker (Ramboll Environ Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Mr. Eric Yim |
2565 3355 |
3162 5217 |
Environmental Officer |
Mr. W. Li |
2565 3137 |
3162 5217 |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint hotline |
--- |
--- |
6509 0375 |
--- |
For Contract No.
HY/2014/04 within Contract No. HY/2014/05 works area |
||||
Engineer or Engineer¡¦s Representative |
Chief Registered Architect |
Malcolm Sage |
3958 7330 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker (Ramboll Environ Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Ringo Yau |
9833 1402 |
2707 0816 |
Environmental Officer |
Clarie Tsang |
6371 1362 |
--- |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint hotline |
--- |
--- |
9833 1420 |
--- |
For Contract No. HY/2014/05
¡P
Raft
foundation for Buildings 050A1
¡P
Construction
of RC Structure of Buildings 023, 044, 045, 050H1, 050H2 and 050A2A
¡P
ABWF
works (Internal Finishes) of Buildings 021, 022, 023, 025, 032, 044, 045,
050A2, 053, 058 and 059
¡P
ABWF
works (External Finishes) of Buildings 021, 022, 023, 025, 045, 050A2, 053, 058
and 059
¡P
ABWF
works (Roof Finishes) of Buildings 022, 023, 025, 032, 044, 053, 058 and 059
¡P
MEP
installation of Building 021, 022, 023, 025, 032, 044, 045, 053, 058 and 059
¡P
Utilities
and Drainage installation of Building 025
For
Contract No. HY/2013/06 within Contract No. HY/2014/05 works area
¡P
Conceal
Conduit Installation Buildings 025 and 032
For
Contract No. HY/2014/04 within Contract No. HY/2014/05 works area
¡P
Cabling
Works at Buildings 053 and 054
¡P
Installation
of Extension Pieces and Door frames at Building 058
¡P
Installation
of Doors at Building 059
Table 2‑1 Construction
Dust Monitoring Locations
ID |
Location
Description |
AMS 6(1) |
Dragonair/CNAC (Group)
Building |
AMS 7(1) |
Hong Kong SkyCity Marriott
Hotel |
Remark:
(1) The ET of this Contract should conduct impact air
quality monitoring at the AMS listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring
station(s) is/are no longer covered by another ET of the HZMB project.
Table 2‑2 Action
and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 6 ¡V Dragonair / CNAC
(Group) Building (HKIA) |
360 |
500 |
AMS 7 - Hong Kong SkyCity Marriott
Hotel |
370 |
Table 2‑3
Action
and Limit Levels for 24-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 6 ¡V Dragonair / CNAC
(Group) Building (HKIA) |
173 |
260 |
AMS 7 - Hong Kong SkyCity
Marriott Hotel |
183 |
Table 3‑1 Construction
Noise Monitoring Locations
ID |
Location Description |
NMS2(1) |
Seaview
Crescent |
NMS3B(1)(2) |
Site Boundary
of Site Office
Area at Works Area WA2 |
Remarks:
(1)
The ET of
this Contract should conduct impact noise monitoring at the NMS listed in the
table as part of EM&A programme according to the latest notification from ENPO when the monitoring
station(s) is/are no longer covered by another ET of the HZMB project.
(2)
The Action
and Limit Levels for schools will be applied for this alternative monitoring
location.
Table 3‑2 Action
and Limit Level for Construction Noise
Parameter |
Action Level |
Limit Level |
07:00 ¡V 19:00 hours
on normal weekdays |
When one
documented complaint is received |
75 dB(A)* |
Notes :
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
* Limit level is 70 dB(A) for schools and 65 dB(A) during school examination period.
Table 4‑1 Summary
of Environmental Site Inspections for Contract No. HY/2014/05
Date of Audit |
Observations |
Actions Taken by Contractor /
Recommendation |
Date of Observations Closed |
26 April 2017 |
1. Rubbish was scattered on the ground at Building
032 work area. |
1. The rubbish on the ground was cleared at the
Building 032 works area. |
25 May 2017 |
4 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
10 May 2017 |
1. Oil product was stored in a plastic bottle and found
without proper drip tray at Building 058. |
1. Oil container was removed at Building 058. |
17 May 2017 |
17 May 2017 |
1. The dust emission was observation during the
handling process of cement at Building 025. 2. The used cement bags were found at Building
025. 3. Oily water was found in the drip tray at
Building 022. |
1. A tarpaulin was provided and it will be used
during the handling process of cement at Building 025. 2. The used cement bags were removed at Building
025. 3. The oily water was cleared in the drip tray at
Building 022. |
25 May 2017 |
25 May 2017 |
1. Chemical containers were found without drip
tray at Building 044. |
1. The chemical containers were removed at
Building 044. |
31 May 2017 |
31 May 2017 |
1. General refuses were observed on the ground at
Building 023 work area. |
1. The Contractor was reminded to clear the
rubbish on the ground at the Building 023 works and keep the site tidiness. |
Follow-up action undertaken by the Contractor will
be inspected during the site inspection to be undertaken in June 2017. |
Table
4‑2 Summary
of Environmental Site Inspections for Contract No. HY/2013/06 within Contract
No. HY/2014/05 works area
Date of Audit |
Observations |
Actions Taken by Contractor /
Recommendation |
Date of Observations Closed |
4 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
10 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
17 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
25 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
31 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
Table
4-3 Summary
of Environmental Site Inspections for Contract No. HY/2014/04 within Contract
No. HY/2014/05 works area
Date of Audit |
Observations |
Actions Taken by Contractor /
Recommendation |
Date of Observations Closed |
4 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
10 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
17 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
25 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
31 May 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
Table 4-4 A Summary of Environmental Complaints for the Reporting Month
Environmental Complaint No. |
Date of Complaint Received |
Description of Environmental Complaints |
004 |
31 May 2017 |
Air Quality |
Table 5-1 Construction
Activities for June 2017
Site Area |
Description of Activities |
For Contract No. HY/2014/05 |
|
Buildings 023, 050A1, 050H1, 050H2 and 050A2 |
Construction of RC Structure |
Buildings 021, 022, 023, 025, 032, 044, 045, 050A1, 050A2, 053, 058
and 059 |
ABWF works (Internal Finishes) |
Buildings 021, 022, 023, 025, 045, 050A1, 050H2, 058 and 059 |
ABWF works (External Finishes) |
Buildings 022, 023, 025, 032, 044, 045, 050H2, 053, 058 and 059 |
ABWF works (Roof Finishes) |
Buildings 021, 022, 023, 025, 032, 044, 045, 053, 058 and 059 |
MEP installation |
Building 025, 032, 050A1, 050A2, 050H2, 053, 058 and 059 |
Utilities and Drainage installation |
For Contract No. HY/2013/06 within Contract No.
HY/2014/05 works area |
|
Buildings 023, 025 and 032 |
Conceal Conduit Installation |
For Contract No. HY/2014/04 within Contract No.
HY/2014/05 works area |
|
Buildings 053 and 054 |
Cabling Works |
Buildings 058 and 059 |
Installation of Doors |
Appendix A
Location of Works Areas
Appendix B
Project Organization for Environmental Works
Appendix C
Construction Programme
Appendix D
Event and Action Plan
Appendix E
Waste Flow Table
Appendix F
Environmental Licenses and Permits
Appendix G
Implementation Schedule for Environmental Mitigation Measures (EMIS)
Appendix H
Statistics on Environmental Complaints, Notification of Summons and Successful
Prosecutions
Appendix I
Environmental Site Inspection Schedule