Contract No. HY/2014/05
Hong Kong-Zhuhai-Macao
Bridge
Hong Kong
Boundary Crossing Facilities ¡V Remaining Ancillary Buildings and Facilities
Monthly EM&A Report
No. 34
(Covering the Period from
1 December 2018 to 31 December 2018)
11 October 2019
Revision 3
Main Contractor Environmental
Team
Contents
Executive
Summary
1.4 Construction
Works Undertaken During the Reporting Period
2....... Air Quality Monitoring
4....... Environmental Site Inspection and Audit
4.2 Advice
on the Solid and Liquid Waste Management Status
4.3 Environmental
Licenses and Permits
4.4 Implementation Status of Environmental
Mitigation Measures
4.5 Summary of Exceedance of the Environmental
Quality Performance Limit
4.6 Summary of Complaints, Notification of
Summons and Successful Prosecution
5.1 Construction Programme for the Coming Months
5.2 Environmental Site Inspection Schedule for
the Coming Month
Figures
Figure 2.1 Location
of Air Quality and Noise Monitoring
Stations
Appendices
Appendix
A Landscape
Checklist
Appendix B Location of Works Areas
Appendix C Project
Organization for Environmental Works
Appendix D Event and
Action Plan
Appendix E Implementation
Schedule for Environmental Mitigation Measures (EMIS)
Appendix F Statistics
on Environmental Complaints, Notification of Summons and Successful
Prosecutions
Executive Summary
This
Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for
Contract No. HY/2014/05 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary
Crossing Facilities (HZMB HKBCF) ¡V Remaining Ancillary
Buildings and Facilities (includes the construction works of Contract No.
HY/2013/06 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities
¡V Automatic Vehicle Clearance Support System within Contract No. HY/2014/05
works area) (hereafter referred to as ¡§the Contract¡¨) for the Highways
Department of Hong Kong Special Administrative Region (HKSAR). Contract No.
HY/2014/05 was awarded to Leighton ¡V Chun Wo Joint Venture (construction works
of Contract No. HY/2013/06 was awarded to ATAL Technologies Limited within
Contract No. HY/2014/05 works area) (hereafter referred to as ¡§the Contractor¡¨)
and Atkins China Limited was appointed as the Environmental Team (ET) by the
Contractor.
Contract
No. HY/2014/05 (includes the construction works of Contract No. HY/2013/06
within Contract No. HY/2014/05 works area) is part of HZMB HKBCF Project which
is a ¡§Designated
Project¡¨ under Schedule 2 of the Environmental Impact Assessment Ordinance
(EIAO) (Cap 499) and Environmental Impact Assessment (EIA) Report (Register No.
AEIAR-145/2009) was prepared for the Project. The current
Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016.
These documents are available through the EIA Ordinance Register. The
construction works
of the
Contract No.
HY/2014/05 commenced on 29 February 2016 while the construction works of the
Contract No. HY/2013/06 and Contract No. HY/2014/04 within Contract No.
HY/2014/05 works area commenced on 3 January 2017 and 13 February 2017
respectively. As confirmed by RE in July 2018, the construction works of
Contract No. HY/2014/04 within Contract No. HY/2014/05 works area have been
completed.
Atkins
China Limited has been appointed by the Contractor to implement the
Environmental Monitoring & Audit (EM&A) programme for the Contract in
accordance with the Updated EM&A Manual for HKBCF (Version 1.0) and
will be providing environmental team services to the Contract.
This
is the thirty-forth monthly EM&A Report for the Contract No. HY/2014/05
which summarizes findings of the EM&A works during the reporting period
from 1 to 31 December 2018 (includes the construction works of Contract No.
HY/2013/06 within Contract No. HY/2014/05 works area).
Landscape
Checklist is shown in Appendix
A.
Environmental Monitoring and Audit Progress
The
monthly EM&A programme was undertaken in accordance with the Updated
EM&A Manual for HKBCF (Version 1.0). It should be noted
that air quality and noise monitoring works for the Contract are
covered by Contract
No. HY/2013/04 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing
Facilities (HZMB HKBCF) ¡V Infrastructure Works Stage II (Southern Portion) and
Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V
Section between Scenic Hill and HKBCF. The ET of the Contract or another ET of
the HZMB project is required to conduct impact air quality monitoring at AMS6
and AMS7B and noise monitoring at NMS2 and NMS3C as part of EM&A programme,
if these monitoring stations are no longer covered under Contract Nos.
HY/2013/04 and HY/2011/03. However,
this is subject to ENPO¡¦s final decision on which ET should carry out the
monitoring work at these stations.
The works site area in Hong Kong-Zhuhai-Macao
Bridge was handed over to the relevant authorities since 24 October 2018 and
the site had been changed to a closed area, no site inspection was conducted for the Contract No.
HY/2014/05 during the reporting period.
Breaches of Action and Limit Levels
Summary
of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at
AMS6 shall be referred to the monthly EM&A report prepared by Contract No.
HY/2011/03.
There was no Action and Limit Level exceedance of 1-hr TSP level and
24-hr TSP level recorded at AMS7B by the Environmental Team of Contract No.
HY/2013/04 during the reporting period.
There
was no Action and Limit Level exceedance for noise recorded at NMS2 and NMS3C
by the ET of Contract No. HY/2013/04 during the reporting period.
Complaint Log
There
was no complaint received in relation to the environmental impact during the
reporting period.
Notifications of Summons and Successful
Prosecutions
There were
no notifications of summons or prosecutions received during this reporting
period.
Reporting Change
There
was no reporting change during the reporting period.
No
construction works will be conducted by Contract No. HY/2014/05 in the upcoming
month.
For Contract No. HY/2014/05
(i)
Construction of the following
ancillary buildings and facilities including architectural and builder works,
structural steel canopy, reinforced concrete frames, foundations, curtain wall
facade, building services and electrical and mechanical works:
•
Public Toilets at Vehicle Clearance
Plaza (VCP);
•
Customs and Excise Department
(C&ED) Dangerous Good Store (Building 021);
•
Customs Detective Dog Base Building
(Building 022);
•
C&ED Outbound Cargo Examination
Building and Examination Platform (Building 023);
•
Inbound Private Car Annexure
(Building 025);
•
Outbound Private Car Annexure
(Building 032);
•
E&M maintenance Building
(Building 044);
•
Highways Depot & Administration
Building (Building 045);
•
Outbound X-ray Building (Building
053);
•
Outbound X-ray Scan Tunnel (Building
058); and
•
Inbound X-ray Scan Tunnel (Building
059).
(ii)
Construction of civil provisions,
cable containment and power supply for the following systems:
•
Automatic Vehicle Clearance Support
System (AVCSS) installed by Contract No. HY/2013/06; and
•
Gantry Type X-ray Vehicle Inspection
System installed by Contract No. HY/2014/04.
(iii) Supply
and installation of Mobile X-ray Vehicle Inspection System and other standalone
equipment;
(iv) Construction
of minor civil engineering works at the periphery of buildings;
(v)
Construction of minor Landscape hardworks and softworks; and
(vi) Other
works which are shown on Drawings or specified in the Specification or which
may be ordered in accordance with the Contract.
For Contract No. HY/2013/06
within Contract No. HY/2014/05 works area
(i)
The Automatic Vehicle Clearance
Support System amid to increasing traffic flow for Hong Kong-Zhuhai-Macao
Bridge Hong Kong Boundary Crossing Facilities;
(ii)
Responsible for designs and develops
a set of tailor-made computer monitoring and control systems
to for daily security operation; and
(iii) The
Clearance Workstations at 72 vehicle clearance kiosks, Customs and Excise¡¦s
inbound and outbound traffic control centers as well as a Vehicle Tracking
System.
For Contract
No. HY/2014/04 within Contract No. HY/2014/05 works area
(i)
The Gantry Type X-ray Vehicle
Inspection System (GXRVIS) aims to provide an integrated, innovative, efficient
and effective vehicle inspection system at the inbound and outbound boundary
control points of Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing
Facilities (HKBCF) for supporting the operations of Customs & Excise
Department (C&ED);
(ii)
Design, supply, deliver to HKBCF,
installation, test and commissioning and maintenance of two sets of Gantry Type
X-ray Vehicle Inspection System and all related components necessary for the
complete operation of the system; and
(iii) Design,
supply, install, test, commission and maintain of the Radioactive Threat
Detection Systems integrated into the Gantry Type X-ray Vehicle Inspection
Systems.
Table 1‑1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
For Contract No. HY/2014/05 |
||||
Engineer or Engineer¡¦s Representative |
Chief Registered Architect |
Malcolm Sage |
3958 7330 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker
(Ramboll Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Eric Kwok |
3973 1817 |
3621 0180 |
Environmental Officer |
Stephen Tsang |
3973 1806 |
3621 0180 |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint
hotline |
--- |
--- |
3958 7300 |
--- |
For Contract No. HY/2013/06 within Contract No.
HY/2014/05 works area |
||||
Engineer or Engineer¡¦s Representative (RE) |
Chief Registered Architect |
Malcolm Sage |
3958 7330 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker
(Ramboll Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Mr. Eric Yim |
2565 3355 |
3162 5217 |
Environmental Officer |
Mr. W. Li |
2565 3137 |
3162 5217 |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint hotline |
--- |
--- |
6509 0375 |
--- |
Table 2‑1 Construction
Dust Monitoring Locations
ID |
Location
Description |
AMS6(1) |
Dragonair/CNAC (Group)
Building |
AMS7B(2) |
3RS site office |
Remark:
(1) The ET of this Contract should conduct impact air quality
monitoring at the AMS listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring
station(s) is/are no longer covered by another ET of the HZMB project.
(2) A proposal for re-location of AQM station
(AMS7) for HZMB HKBCF Project was justified by the ET Leader for
Contract No. HY/2013/01 on 22 January 2018; verified by the IEC on 24
January 2018; and submitted to EPD on 30 January 2018, and the AQM has
been carrying out at the alternative AQM station with EPD's consent
since 6 February 2018.
Table 2‑2 Action
and Limit Levels for 1-hr TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS6 ¡V Dragonair / CNAC
(Group) Building (HKIA) |
360 |
500 |
AMS7B ¡V 3RS site office |
370 |
Table 2‑3
Action
and Limit Levels for 24-hr TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS6 ¡V Dragonair / CNAC
(Group) Building (HKIA) |
173 |
260 |
AMS7B ¡V 3RS site office |
183 |
Table 3‑1 Construction
Noise Monitoring Locations
ID |
Location Description |
NMS2(1) |
Seaview
Crescent |
NMS3C (1)(2)(3) |
Ying Tung
Estate Refuse Collection Point |
Remarks:
(1)
The ET of
this Contract should conduct impact noise monitoring at the NMS listed in the
table as part of EM&A programme according to the latest notification from ENPO when the monitoring
station(s) is/are no longer covered by another ET of the HZMB project.
(2)
The Action
and Limit Levels for schools will be applied for this alternative monitoring
location.
(3)
NMS3C has been undertaking
by the ET for Contract No. HY/2013/04 since 20 August 2018.
Table 3‑2 Action
and Limit Level for Construction Noise
Parameter |
Action Level |
Limit Level |
07:00 ¡V 19:00 hours
on normal weekdays |
When one
documented complaint is received |
75 dB(A)* |
Notes:
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to
be followed.
* Limit level is 70 dB(A) for schools and 65 dB(A) during school examination period.