Verification by IEC

 

Certification by ET

 

 

 

 

                       

 

 

Contract No. HY/2014/05

Hong Kong-Zhuhai-Macao Bridge

Hong Kong Boundary Crossing Facilities ¡V Remaining Ancillary Buildings and Facilities

 

 

 

 

Monthly EM&A Report No. 35

(Covering the Period from 1 January 2019 to 31 January 2019)

 

24 October 2019

 

Revision 4

 

 

 

 

 

 

 

Main Contractor                                                                                                          Environmental Team 

 

 


 

 

Contents

Executive Summary

1...... Introduction. 1

1.1                          Basic Project Information. 1

1.2                          Project Organisation. 2

1.3                          Construction Programme. 3

1.4                          Construction Works Undertaken During the Reporting Period. 3

2....... Air Quality Monitoring.. 4

2.1                          Monitoring Locations. 4

2.2                          Monitoring Requirements. 4

2.3                          Monitoring Results. 5

3....... Noise Monitoring.. 6

3.1                          Monitoring Locations. 6

3.2                          Monitoring Requirements. 6

3.3                          Monitoring Results. 6

4....... Environmental Site Inspection and Audit 7

4.1                          Site Inspection. 7

4.2                          Advice on the Solid and Liquid Waste Management Status. 7

4.3                          Environmental Licenses and Permits. 7

4.4                          Implementation Status of Environmental Mitigation Measures. 7

4.5                          Summary of Exceedance of the Environmental Quality Performance Limit 7

4.6                          Summary of Complaints, Notification of Summons and Successful Prosecution. 7

5....... Future Key Issues. 8

5.1                          Construction Programme for the Coming Months. 8

5.2                          Environmental Site Inspection Schedule for the Coming Month. 8

6....... Conclusions. 9

6.1                          Conclusions. 9

 

 

 

 

 

 

 

 

 

 

Figures

Figure 2.1          Location of Air Quality and Noise Monitoring Stations

 

Appendices

Appendix A       Landscape Checklist

Appendix B       Location of Works Areas

Appendix C       Project Organization for Environmental Works

Appendix D       Event and Action Plan

Appendix E       Implementation Schedule for Environmental Mitigation Measures (EMIS) 

Appendix F       Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions  


Executive Summary

This Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract No. HY/2014/05 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HZMB HKBCF) ¡V Remaining Ancillary Buildings and Facilities (includes the construction works of Contract No. HY/2013/06 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Automatic Vehicle Clearance Support System within Contract No. HY/2014/05 works area) (hereafter referred to as ¡§the Contract¡¨) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). Contract No. HY/2014/05 was awarded to Leighton ¡V Chun Wo Joint Venture (construction works of Contract No. HY/2013/06 was awarded to ATAL Technologies Limited within Contract No. HY/2014/05 works area) (hereafter referred to as ¡§the Contractor¡¨) and Atkins China Limited was appointed as the Environmental Team (ET) by the Contractor.

Contract No. HY/2014/05 (includes the construction works of Contract No. HY/2013/06 within Contract No. HY/2014/05 works area) is part of HZMB HKBCF Project which is a ¡§Designated Project¡¨ under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. The construction works of the Contract No. HY/2014/05 commenced on 29 February 2016 while the construction works of the Contract No. HY/2013/06 and Contract No. HY/2014/04 within Contract No. HY/2014/05 works area commenced on 3 January 2017 and 13 February 2017 respectively. As confirmed by RE in July 2018, the construction works of Contract No. HY/2014/04 within Contract No. HY/2014/05 works area have been completed. 

Atkins China Limited has been appointed by the Contractor to implement the Environmental Monitoring & Audit (EM&A) programme for the Contract in accordance with the Updated EM&A Manual for HKBCF (Version 1.0) and will be providing environmental team services to the Contract.

This is the thirty-fifth monthly EM&A Report for the Contract No. HY/2014/05 which summarizes findings of the EM&A works during the reporting period from 1 to 31 January 2019 (includes the construction works of Contract No. HY/2013/06 within Contract No. HY/2014/05 works area).

Landscape Checklist is shown in Appendix A. Reporting of landscape monitoring during 12-month establishment period after this reporting period shall be referred to monthly EM&A report prepared by Contract No. HY/2013/04.

Environmental Monitoring and Audit Progress

The monthly EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0). It should be noted that air quality and noise monitoring works for the Contract are covered by Contract No. HY/2013/04 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HZMB HKBCF) ¡V Infrastructure Works Stage II (Southern Portion) and Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill and HKBCF. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 and AMS7B and noise monitoring at NMS2 and NMS3C as part of EM&A programme, if these monitoring stations are no longer covered under Contract Nos. HY/2013/04 and HY/2011/03. However, this is subject to ENPO¡¦s final decision on which ET should carry out the monitoring work at these stations. 

The works site area in Hong Kong-Zhuhai-Macao Bridge was handed over to the relevant authorities since 24 October 2018 and the site had been changed to a closed area, no site inspection was conducted for the Contract No. HY/2014/05 during the reporting period.

Breaches of Action and Limit Levels

Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7B by the Environmental Team of Contract No. HY/2013/04 during the reporting period.

There was no Action and Limit Level exceedance for noise recorded at NMS2 and NMS3C by the ET of Contract No. HY/2013/04 during the reporting period.

Complaint Log

There was no complaint received in relation to the environmental impact during the reporting period.

Notifications of Summons and Successful Prosecutions      

There were no notifications of summons or prosecutions received during this reporting period.

Reporting Change

There was no reporting change during the reporting period.

Future Key Issues

No construction works will be conducted by Contract No. HY/2014/05 in the upcoming month.

 

 


1        Introduction

1.1                Basic Project Information

1.1.1          This Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract No. HY/2014/05 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HZMB HKBCF) ¡V Remaining Ancillary Buildings and Facilities (includes the construction works of Contract No. HY/2013/06 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Automatic Vehicle Clearance Support System and Contract No. HY/2014/04 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Gantry Type X-ray Vehicle Inspection System within Contract No. HY/2014/05 works area)  (hereafter referred to as ¡§the Contract¡¨) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). Contract No. HY/2014/05 was awarded to Leighton ¡V Chun Wo Joint Venture (construction works of Contract No. HY/2013/06 was awarded to ATAL Technologies Limited and Contract No. HY/2014/04 was awarded to Rapiscan Systems Pte Ltd within Contract No. HY/2014/05 works area) (hereafter referred to as ¡§the Contractor¡¨) and Atkins China Limited was appointed as the Environmental Team (ET) by the Contractor.

1.1.2          Contract No. HY/2014/05 (includes the construction works of Contract No. HY/2013/06 and Contract No. HY/2014/04 within Contract No. HY/2014/05 works area) is part of HZMB HKBCF which is a ¡§Designated Project¡¨ under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499).  An Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. The construction works of the Contract No. HY/2014/05 commenced on 29 February 2016 while the construction works of the Contract No. HY/2013/06 and Contract No. HY/2014/04 within Contract No. HY/2014/05 works area commenced on 3 January 2017 and 13 February 2017 respectively. As confirmed by RE in July 2018, the construction works of Contract No. HY/2014/04 within Contract No. HY/2014/05 works area have been completed. The works areas of the Contract are shown in Appendix B.

1.1.3          The proposed works under this Contract comprise the following:

For Contract No. HY/2014/05

(i)    Construction of the following ancillary buildings and facilities including architectural and builder works, structural steel canopy, reinforced concrete frames, foundations, curtain wall facade, building services and electrical and mechanical works:

       Public Toilets at Vehicle Clearance Plaza (VCP);

       Customs and Excise Department (C&ED) Dangerous Good Store (Building 021);

       Customs Detective Dog Base Building (Building 022);

       C&ED Outbound Cargo Examination Building and Examination Platform (Building 023);

       Inbound Private Car Annexure (Building 025);

       Outbound Private Car Annexure (Building 032);

       E&M maintenance Building (Building 044);

       Highways Depot & Administration Building (Building 045);

       Outbound X-ray Building (Building 053);

       Outbound X-ray Scan Tunnel (Building 058); and

       Inbound X-ray Scan Tunnel (Building 059).

(ii)   Construction of civil provisions, cable containment and power supply for the following systems:

       Automatic Vehicle Clearance Support System (AVCSS) installed by Contract No. HY/2013/06; and

       Gantry Type X-ray Vehicle Inspection System installed by Contract No. HY/2014/04.

(iii)  Supply and installation of Mobile X-ray Vehicle Inspection System and other standalone equipment;

(iv)  Construction of minor civil engineering works at the periphery of buildings;

(v)   Construction of minor Landscape hardworks and softworks; and

(vi)  Other works which are shown on Drawings or specified in the Specification or which may be ordered in accordance with the Contract.

For Contract No. HY/2013/06 within Contract No. HY/2014/05 works area

(i)    The Automatic Vehicle Clearance Support System amid to increasing traffic flow for Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities;

(ii)   Responsible for designs and develops a set of tailor-made computer monitoring and control systems to for daily security operation; and

(iii)  The Clearance Workstations at 72 vehicle clearance kiosks, Customs and Excise¡¦s inbound and outbound traffic control centers as well as a Vehicle Tracking System.

For Contract No. HY/2014/04 within Contract No. HY/2014/05 works area

(i)    The Gantry Type X-ray Vehicle Inspection System (GXRVIS) aims to provide an integrated, innovative, efficient and effective vehicle inspection system at the inbound and outbound boundary control points of Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) for supporting the operations of Customs & Excise Department (C&ED);

(ii)   Design, supply, deliver to HKBCF, installation, test and commissioning and maintenance of two sets of Gantry Type X-ray Vehicle Inspection System and all related components necessary for the complete operation of the system; and

(iii)  Design, supply, install, test, commission and maintain of the Radioactive Threat Detection Systems integrated into the Gantry Type X-ray Vehicle Inspection Systems.

1.1.4      This is the thirty-fifth Monthly EM&A Report for the Contract No. HY/2014/05 which summarizes the findings of the EM&A programme during the reporting period from 1 to 31 January 2019. (includes the construction works of Contract No. HY/2013/06 within Contract No. HY/2014/05 works area).

1.2                Project Organisation

1.2.1      The project organization structure and lines of communication with respect to the on-site environmental management structure is shown in Appendix C. The key personnel contact names and numbers are summarized in Table 1‑1. 

Table 11         Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

For Contract No. HY/2014/05

Engineer or Engineer¡¦s Representative
(AECOM Asia Co. Ltd.)

Chief Registered Architect

Malcolm Sage

3958 7330

3468 2076

Environmental Project Office / Independent Environmental Checker (Ramboll Hong Kong Limited)

Environmental Project Office Leader

Y. H. Hui

3465 2888

3465 2899

Independent Environmental Checker

Ray Yan

3465 2888

3465 2899

Contractor
(Leighton ¡V Chun Wo Joint Venture)

Site Agent

Eric Kwok

3973 1817

3621 0180

Environmental Officer

Stephen Tsang

3973 1806

3621 0180

Environmental Team
(Atkins China Limited)

Environmental Team Leader

Keith Chau

2972 1721

2890 6343

24 hours complaint hotline

---

---

3958 7300

---

For Contract No. HY/2013/06 within Contract No. HY/2014/05 works area

Engineer or Engineer¡¦s Representative (RE)
(AECOM Asia Co. Ltd.)

Chief Registered Architect

Malcolm Sage

3958 7330

3468 2076

Environmental Project Office / Independent Environmental Checker (Ramboll Hong Kong Limited)

Environmental Project Office Leader

Y. H. Hui

3465 2888

3465 2899

Independent Environmental Checker

Ray Yan

3465 2888

3465 2899

Contractor
(ATAL Technologies Limited)

Site Agent

Mr. Eric Yim

2565 3355

3162 5217

Environmental Officer

Mr. W. Li

2565 3137

3162 5217

Environmental Team
(Atkins China Limited)

Environmental Team Leader

Keith Chau

2972 1721

2890 6343

24 hours complaint hotline

---

---

6509 0375

---

1.3                Construction Programme

1.3.1      As all the sections under Contract No. HY/2014/05 and HY/2013/06 were handed over to the relevant authorities on 24 October 2018 and the site had been changed to closed area, no construction programme will be provided.

1.4                Construction Works Undertaken During the Reporting Period

1.4.1      As all the sections under Contract No. HY/2014/05 and HY/2013/06 were handed over to the relevant authorities on 24 October 2018 and the site had been changed to closed area, no construction works undertaken during the reporting period.

 

 

2        Air Quality Monitoring

2.1                Monitoring Locations

2.1.1      The air quality monitoring works for the Contract are covered by Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill and HKBCF and Contract No. HY/2013/04 HZMB HKBCF ¡V Infrastructure Works Stage II (Southern Portion) since 1 October 2018. 

2.1.2      The ET of the Contract or another ET of the HZMB project is required to conduct air quality monitoring at AMS6 and AMS7B as part of EM&A programme if these air quality monitoring stations are no longer covered under Contract Nos. HY/2011/03 and HY/2013/04. Figure 2.1 shows the locations of the air monitoring stations.

Table 21         Construction Dust Monitoring Locations

ID

Location Description

AMS6(1)

Dragonair/CNAC (Group) Building

AMS7B(2)

3RS site office

Remark:

(1)    The ET of this Contract should conduct impact air quality monitoring at the AMS listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

(2)    A proposal for re-location of AQM station (AMS7) for HZMB HKBCF Project was justified by the ET Leader for Contract No. HY/2013/01 on 22 January 2018; verified by the IEC on 24 January 2018; and submitted to EPD on 30 January 2018, and the AQM has been carrying out at the alternative AQM station with EPD's consent since 6 February 2018.

2.2                Monitoring Requirements

2.2.1      The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared for Contract Nos. HY/2011/03 and HY/2013/04.

2.2.2      The Action and Limit Levels for 1-hr TSP and 24-hr TSP are provided in Table 2-2 and Table 2-3, respectively.

Table 22         Action and Limit Levels for 1-hr TSP

Monitoring Station

Action Level, µg/m3

Limit Level, µg/m3

AMS6 ¡V Dragonair / CNAC (Group) Building (HKIA)

360

500

AMS7B ¡V 3RS site office

370

Table 23        Action and Limit Levels for 24-hr TSP

Monitoring Station

Action Level, µg/m3

Limit Level, µg/m3

AMS6 ¡V Dragonair / CNAC (Group) Building (HKIA)

173

260

AMS7B ¡V 3RS site office

183

 

2.2.3      The event and action plan is provided in Appendix D.

2.2.4      If exceedance(s) at these station(s) is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

2.3                Monitoring Results

2.3.1      The monitoring results for AMS6 and AMS7B are reported in the monthly EM&A Reports prepared for Contract Nos. HY/2011/03 and HY/2013/04, respectively.

2.3.2      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A Report prepared by Contract No. HY/2011/03. No Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7B by the Environmental Team of Contract No. HY/2013/04 during the reporting period. Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS7B shall be referred to the monthly EM&A Report prepared by Contract No. HY/2013/04.


3        Noise Monitoring

3.1                Monitoring Locations

3.1.1      The noise monitoring works for the Contract are covered by Contract No. HY/2013/04. The ET of the Contract or another ET of the HZMB of the HZMB project is required to conduct impact noise monitoring at NMS2 and NMS3C as part of EM&A programme if these noise monitoring stations are no longer covered under Contract No. HY/2013/04. Figure 2.1 shows the locations of noise monitoring stations.

Table 31         Construction Noise Monitoring Locations

ID

Location Description

NMS2(1)

Seaview Crescent

NMS3C (1)(2)(3)

Ying Tung Estate Refuse Collection Point

Remarks:

(1)        The ET of this Contract should conduct impact noise monitoring at the NMS listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project. 

(2)        The Action and Limit Levels for schools will be applied for this alternative monitoring location.

(3)        NMS3C has been undertaking by the ET for Contract No. HY/2013/04 since 20 August 2018.

 

3.2                Monitoring Requirements

3.2.1      The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology and monitoring schedule are detailed in the monthly EM&A Reports prepared for Contract No. HY/2013/04.

3.2.2      The Action and Limit Levels for construction noise are defined in Table 3-2.

Table 32         Action and Limit Level for Construction Noise

Parameter

Action Level

Limit Level

07:00 ¡V 19:00 hours on normal weekdays

When one documented complaint is received

75 dB(A)*

Notes:     

If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.

* Limit level is 70 dB(A) for schools and 65 dB(A) during school examination period.

  

3.2.3      The event and action plan is provided in Appendix D.

3.2.4      If exceedance(s) at these station(s) is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

3.3                Monitoring Results

3.3.1      The monitoring results for NMS2 and NMS3C are reported in the monthly EM&A Reports prepared for Contract No. HY/2013/04. No noise exceedances were recorded at stations NMS2 and NMS3C by the ET of Contract No. HY/2013/04 during the reporting period.

4        Environmental Site Inspection and Audit

4.1                Site Inspection

4.1.1      The works site area in Hong Kong-Zhuhai-Macao Bridge was handed over to the relevant authorities since 24 October 2018 and the site area was changed to closed area, no site inspection was conducted for the Contract No. HY/2014/05 during the reporting period.

4.1.2      The landscape work of green roof for Contract No. HY/2014/05 was commenced on 11 December 2017. As confirmed by RE, landscape works for Contract No. HY/2014/05 is considered substantially completed as of 23 April 2018. The related certificate (Ref.: BWLM: TTHK: wmy:60313494/C8/M15/905/M0531-2018010932T) dated 13 September 2018 was issued by RE. No inspection for landscape works (construction phase) was conducted for Contract No. HY/2014/05 during the reporting period.

4.2               Advice on the Solid and Liquid Waste Management Status

4.2.1      The works site area of Contract No. HY/2014/05 was handed over to the relevant authorities since 24 October 2018 and no chemical waste and general refuse were generated during reporting period.

4.3               Environmental Licenses and Permits

4.3.1      The works site area of Contract No. HY/2014/05 was handed over to the relevant authorities since 24 October 2018, therefore, no environmental licenses and permits is required during reporting period.

4.4               Implementation Status of Environmental Mitigation Measures

4.4.1      The works site area of Contract No. HY/2014/05 was handed over to the relevant authorities since 24 October 2018, therefore, no environmental mitigation measures is recorded. The EMIS is shown in Appendix E.

4.5               Summary of Exceedance of the Environmental Quality Performance Limit

4.5.1      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

4.5.2      There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7B by the Environmental Team of Contract No. HY/2013/04 during the reporting period.

4.5.3      No noise exceedances were recorded at stations NMS2 and NMS3C by the ET of Contract No. HY/2013/04 during the reporting period.

4.6                Summary of Complaints, Notification of Summons and Successful Prosecution

4.6.1      There was no complaint received in relation to the environmental impact during the reporting period.

4.6.2      Statistics on environmental complaints, notifications of summons and successful prosecutions are summarized in Appendix F.


5        Future Key Issues

5.1               Construction Programme for the Coming Months

5.1.1       The Contract No. HY/2014/05 was handed over to the relevant authorities since 24 October 2018 and the works site area had been changed to a closed area. No construction programme will be provided.

5.2               Environmental Site Inspection Schedule for the Coming Month

5.2.1      The Contract No. HY/2014/05 was handed over to the relevant authorities since 24 October 2018 and the works site area had been changed to a closed area. No site inspection will be conducted.


6        Conclusions

6.1               Conclusions

6.1.1      The construction works of the Contract No. HY/2014/05 commenced on 29 February 2016. while the construction works of the Contract No. HY/2013/06 and Contract No. HY/2014/04 within Contract No. HY/2014/05 works area commenced on 3 January 2017 and 13 February 2017 respectively. As confirmed by RE in July 2018, the construction works of Contract No. HY/2014/04 within Contract No. HY/2014/05 works area have been completed. The thirty-fifth Monthly EM&A Report for Contract No. HY/2014/05 summarizes findings of the EM&A works during the reporting period from 1 to 31 January 2019 (includes the construction works of Contract No. HY/2013/06). The works site area in Hong Kong-Zhuhai-Macao Bridge was handed over to the relevant authorities since 24 October 2018 and the site area had been change to a closed area.

6.1.2      Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to the monthly EM&A Report prepared by Contract No. HY/2011/03. No Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7B by the Environmental Team of Contract No. HY/2013/04 during the reporting period. Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS7B shall be referred to the monthly EM&A report prepared by Contract No. HY/2013/04 ¡V Hong Kong-Zhuhai-Macao Bridge HKBCF - Infrastructure Works Stage II (Southern Portion) since 1 October 2018.

6.1.3      No noise exceedances were recorded at stations NMS2 and NMS3C by the ET of Contract No. HY/2013/04 during the reporting period. Summary of Action and Limit Level exceedance at NMS2 and NMS3C shall be referred to the monthly EM&A report prepared by Contract No. HY/2013/04 ¡V Hong Kong-Zhuhai-Macao Bridge HKBCF - Infrastructure Works Stage II (Southern Portion) since 1 October 2018.

6.1.4      The works site area in Hong Kong-Zhuhai-Macao Bridge was handed over to the relevant authorities since 24 October 2018 and the site area had been change to a closed area. No site inspection was carried out during the reporting period. Landscape checklist is shown in Appendix A. Reporting of landscape monitoring during 12-month establishment period after this reporting period shall be referred to monthly EM&A report prepared by Contract No. HY/2013/04.

6.1.5      There was no complaint received in relation to the environmental impact during the reporting period.

6.1.7     No notification of summons and successful prosecution was received during the reporting period.