Contract No.
HY/2014/05
Hong Kong-Zhuhai-Macao Bridge
Hong Kong Boundary Crossing Facilities ¡V
Remaining Ancillary Buildings and Facilities
Quarterly EM&A Report No. 5
(Covering the Period from 1 March 2017 to 31 May 2017)
14
August 2017
Revision
2
Main Contractor Environmental
Team
Contents
Executive Summary
1.4 Construction
Works Undertaken During the Reporting Period
2.1 Summary of EM&A Requirements
3....... Environmental Monitoring
and Audit
3.1 Air Quality Monitoring Results
3.3 Implementation
of Environmental Measures
3.4 Advice
on the Solid and Liquid Waste Management Status
3.5 Environmental
Licenses and Permits
4....... Summary
of Exceedance, Complaint, Notification of Summons and Successful Prosecution
4.1 Summary
of Exceedance of the Environmental Quality Performance Limit
4.2 Summary
of Complaints, Notification of Summons and Successful Prosecution
5....... Comments,
Recommendations and Conclusion
Figures
Figure 2.1 Location of Air Quality Monitoring
Stations
Figure 2.2 Location of Noise Monitoring
Stations
Appendices
Appendix A Location
of Works Areas
Appendix B Project
Organization for Environmental Works
Appendix C Construction
Programme
Appendix D Event
and Action Plan
Appendix E Implementation
Schedule for Environmental Mitigation Measures (EMIS)
Appendix F Site
Audit Findings and Corrective Actions
Appendix G Waste
Flow Table
Appendix H Environmental
Licenses and Permits
Appendix I Statistics
on Environmental Complaints, Notification of Summons and Successful
Prosecutions
Executive Summary
This Quarterly
Environmental Monitoring and Audit (EM&A) Report is prepared for Contract
HY/2014/05 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities
(HKBCF)
¡V Remaining Ancillary Buildings and
Facilities (includes the construction works of Contract No. HY/2013/06 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Automatic
Vehicle Clearance Support System and Contract No. HY/2014/04 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V
Gantry Type X-ray Vehicle Inspection System within Contract No. HY/2014/05
works area) (hereafter referred to as ¡§the Contract¡¨) for the Highways
Department of Hong Kong Special Administrative Region (HKSAR). Contract No.
HY/2014/05 was awarded to Leighton ¡V Chun Wo Joint Venture (construction works
of Contract No. HY/2013/06 was awarded to ATAL Technologies Limited and Contract
No. HY/2014/04 was awarded to Rapiscan Systems Pte Ltd
within Contract No. HY/2014/05 works area) (hereafter referred to as ¡§the
Contractor¡¨) and Atkins China Limited was appointed as the Environmental Team
(ET) by the Contractor.
Contract No. HY/2014/05
(includes the construction works of Contract No. HY/2013/06 and Contract No.
HY/2014/04 within Contract No. HY/2014/05 works area) is part of HZMB HKBCF
Project which is a
¡§Designated Project¡¨ under Schedule 2 of the
Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental
Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was
prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K
for HKBCF was issued on 11 April 2016. These documents are available through the EIA
Ordinance Register. The
construction works of the Contract
No. HY/2014/05 commenced on 29 February 2016 while the construction works of
the Contract No. HY/2013/06 and Contract No. HY/2014/04 within Contract No.
HY/2014/05 works area commenced on 3 January 2017 and 13 February 2017
respectively.
Atkins China Limited has
been appointed by the Contractor to implement the Environmental Monitoring
& Audit (EM&A) programme for the Contract in accordance with the Updated EM&A
Manual for
HKBCF (Version1.0) and will be providing
environmental team services to the Contract.
This is the Fifth Quarterly EM&A Report for the Contract No. HY/2014/05 which summarizes findings of the
EM&A works during the reporting period from 1 March 2017 to 31 May 2017
(includes the construction works of Contract No. HY/2013/06 and Contract No.
HY/2014/04 within Contract No. HY/2014/05 works area).
Environmental
Monitoring and Audit Progress
The EM&A programme was
undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0).
It should be noted that the air quality and noise monitoring works for the Contract are covered by
Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao
Bridge HKBCF
¡V Reclamation Works and Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill
and HKBCF. The ET of the Contract
or another ET of the HZMB project is required to conduct impact air quality
monitoring at AMS6 and AMS7 and noise monitoring at NMS2 and NMS3B as part of
EM&A programme if these monitoring stations are no longer covered under
Contract Nos. HY/2010/02 and HY/2011/03. However, this is subject to ENPO¡¦s final decision
on which ET should carry out the monitoring work at these stations.
The
dates of environmental site inspection for the
Contract No. HY/2014/05 (includes the construction works of Contract No.
HY/2013/06 and Contract No. HY/2014/04 within Contract No. HY/2014/05 works
area) during
the reporting period are
listed below:
Environmental Site Inspection
Date |
||
March
2017 |
April
2017 |
May 2017 |
1, 8, 15, 22 and 29 |
5, 12, 19 and 26 |
4, 10, 17, 25 and 31 |
Breaches of
Action and Limit Levels
Summary of Action and Limit
Level exceedance of 1-hr TSP level and 24-hr TSP level at station AMS6 shall be
referred to the monthly EM&A Reports (for March, April and May 2017)
prepared by Contract No. HY/2011/03.
There was no Action and
Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7
by the Environmental Team of Contract No. HY/2010/02 during the reporting
period.
There was no Action and
Limit Level exceedance for noise recorded at NMS2 and NMS3B by the
Environmental Team of Contract No. HY/2010/02 during the reporting period.
Implementation of Environmental
Measures
Site inspections were
carried out on a weekly basis to monitor the implementation of proper
environmental pollution control and mitigation measures for the Project.
Potential environmental impacts due to the construction activities were
monitored and reviewed.
Complaint Log
There were two complaints
received in relation to the environmental impact during the reporting period.
An investigation for noise and water quality complaint received on 28 March
2017 was carried out. It was found that the complaint was not related to
Contract No. HY/2014/05 (includes the construction works of Contract No.
HY/2013/06 and Contract No. HY/2014/04 within Contract No. HY/2014/05 works
area). For air quality complaint received on 31 May 2017, the complaint is
under investigation and will be reported in the next reporting period.
Notifications
of Summons and Successful Prosecutions
There was no notification
of summon or prosecution received during this reporting period.
Reporting
Change
There was no reporting
change during the reporting period.
Table
1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
For Contract No.
HY/2014/05 |
||||
Engineer or
Engineer¡¦s Representative |
Chief Resident
Engineer |
Darrel Kingan |
3958 7339 |
3468 2076 |
Chief
Registered Architect |
Malcolm Sage(1) |
3958 7330 |
||
Environmental Project
Office / Independent Environmental Checker |
Environmental
Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent
Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Albert Chan |
3973 0514 |
3621 0180 |
Environmental
Officer |
Wu Yun Kau |
5505 8633 |
3621 0180 |
|
Environmental
Team |
Environmental
Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours
complaint hotline |
--- |
--- |
3958 7300 |
--- |
For Contract No.
HY/2013/06 within Contract No. HY/2014/05 works area |
||||
Engineer or
Engineer¡¦s Representative |
Chief Resident
Engineer |
Darrel Kingan |
3958 7339 |
3468 2076 |
Chief
Registered Architect |
Malcolm Sage(1) |
3958 7330 |
||
Environmental
Project Office / Independent Environmental Checker |
Environmental
Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent
Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Mr. Eric Yim |
2565 3355 |
3162 5217 |
Environmental
Officer |
Mr. W. Li |
2565 3137 |
3162 5217 |
|
Environmental
Team |
Environmental
Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours
complaint hotline |
--- |
--- |
6509 0375 |
--- |
For Contract No.
HY/2014/04 within Contract No. HY/2014/05 works area |
||||
Engineer or
Engineer¡¦s Representative |
Chief Resident
Engineer |
Darrel Kingan |
3958 7339 |
3468 2076 |
Chief Registered
Architect |
Malcolm Sage(1) |
3958 7330 |
||
Environmental
Project Office / Independent Environmental Checker |
Environmental
Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent
Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Ringo Yau |
9833 1402 |
2707 0816 |
Environmental
Officer |
Clarie Tsang |
6371 1362 |
--- |
|
Environmental
Team |
Environmental
Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours
complaint hotline |
--- |
--- |
9833 1420 |
--- |
For Contract No. HY/2014/05
¡P
Earth
Works for Buildings 050A1, 050A2, 050H1 and 050H2
¡P
Raft
foundation for Buildings 032, 044, 045, 050A1 and 050H1
¡P
Construction
of RC Structure of Buildings 022, 023, 025, 032, 044, 045, 053, 050H1, 050H2
and 050A2A
¡P
Installation
of window wall of Building 045
¡P
ABWF
works (Internal Finishes) of Buildings 021, 022, 023, 025, 032, 044, 045,
050A2, 053, 058 and 059
¡P
ABWF
works (External Finishes) of Buildings 021, 022, 023, 025, 032, 045, 050A2,
053, 058 and 059
¡P
ABWF
works (Roof Finishes) of Buildings 021, 022, 023, 025, 032, 044, 053, 058 and
059
¡P
Dog
Swimming Pool of Building 022
¡P
MEP
installation of Buildings 021, 022, 023, 025, 032, 044, 045, 053, 058 and 059
¡P
Utilities
and Drainage installation of Buildings 025, 053 and 058
For Contract No. HY/2013/06 within Contract No. HY/2014/05 works area
¡P
Conceal
Conduit Installation of Buildings 025 and 032
For Contract No. HY/2014/04 within Contract No. HY/2014/05 works area
¡P
Hole
drilling at Buildings 058 and 059
¡P
Rebar
scanning at Buildings 058 and 059
¡P
Installation
of rails, extension pieces and door frames at Buildings 058 and 059
¡P
Installation
of Doors at Building 059
¡P
Welding
works at Buildings 058 and 059
¡P
Cabling
works at Buildings 053 and 054
Table 2.1 Summary
of Impact EM&A Requirements
Environmental
Monitoring |
ID |
Location Description |
Air Quality |
AMS6(1) |
Dragonair/CNAC
(Group) Building |
AMS7(1) |
Hong
Kong SkyCity Marriott Hotel |
|
Noise |
NMS2(2) |
Seaview
Crescent |
NMS3B(2),(3) |
Site Boundary
of Site Office
Area at Works Area WA2 |
Remarks:
(1)
The ET of this
Contract should conduct impact air quality monitoring at the AMS listed in the
table as part of EM&A programme according to the latest notification from
ENPO when the monitoring station(s) is/are no longer covered by another ET of
the HZMB project.
(2)
The ET of
this Contract should conduct impact noise monitoring at the NMS listed in the
table as part of EM&A programme according to the latest notification from
ENPO when the monitoring station(s) is/are no longer covered by another ET of
the HZMB project.
(3)
The Action
and Limit Levels for schools will be applied for this alternative monitoring
location.
Table 2.2 Action
and Limit Levels for 1-hour TSP
Monitoring
Station |
Action
Level, µg/m3 |
Limit
Level, µg/m3 |
AMS6
¡V Dragonair/CNAC (Group) Building (HKIA) |
360 |
500 |
AMS7
¡V Hong Kong SkyCity Marriott Hotel |
370 |
Table 2.3 Action
and Limit Levels for 24-hour TSP
Monitoring
Station |
Action
Level, µg/m3 |
Limit
Level, µg/m3 |
AMS6
¡V Dragonair/CNAC (Group) Building (HKIA) |
173 |
260 |
AMS7
¡V Hong Kong SkyCity Marriott Hotel |
183 |
Table 2.4 Action
and Limit Level for Construction Noise
Parameter |
Action Level |
Limit Level |
07:00 ¡V 19:00 hours
on normal weekdays |
When one documented complaint is received |
75 dB(A)* |
Notes:
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by
the
Noise Control Authority have to be followed.
* Reduce to 70 dB(A) for schools and 65 dB(A) during school examination
period.
Table 4-1 A Summary of Environmental Complaints for the Reporting Period
Environmental Complaint No. |
Date of Complaint Received |
Description of Environmental Complaints |
003 |
28
March 2017 |
Noise
and Water Quality |
004 |
31
May 2017 |
Air
Quality |