Contract No.
HY/2014/05
Hong Kong-Zhuhai-Macao Bridge
Hong Kong Boundary Crossing Facilities ¡V
Remaining Ancillary Buildings and Facilities
Quarterly EM&A Report No. 6
(Covering the Period from 1 June 2017 to 31 August 2017)
6
October 2017
Revision
1
Main Contractor Environmental
Team
Contents
Executive Summary
1.4 Construction
Works Undertaken During the Reporting Period
2.1 Summary of EM&A Requirements
3....... Environmental Monitoring
and Audit
3.1 Air Quality Monitoring Results
3.3 Implementation
of Environmental Measures
3.4 Advice
on the Solid and Liquid Waste Management Status
3.5 Environmental
Licenses and Permits
4....... Summary
of Exceedance, Complaint, Notification of Summons and Successful Prosecution
4.1 Summary
of Exceedance of the Environmental Quality Performance Limit
4.2 Summary
of Complaints, Notification of Summons and Successful Prosecution
5....... Comments,
Recommendations and Conclusion
Figures
Figure 2.1 Location of Air Quality Monitoring
Stations
Figure 2.2 Location of Noise Monitoring
Stations
Appendices
Appendix A Location
of Works Areas
Appendix B Project
Organization for Environmental Works
Appendix C Construction
Programme
Appendix D Event
and Action Plan
Appendix E Implementation
Schedule for Environmental Mitigation Measures (EMIS)
Appendix F Site
Audit Findings and Corrective Actions
Appendix G Waste
Flow Table
Appendix H Environmental
Licenses and Permits
Appendix I Statistics
on Environmental Complaints, Notification of Summons and Successful
Prosecutions
Executive Summary
This Quarterly
Environmental Monitoring and Audit (EM&A) Report is prepared for Contract
HY/2014/05 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities
(HKBCF)
¡V Remaining Ancillary Buildings and
Facilities (includes the construction works of Contract No. HY/2013/06 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Automatic
Vehicle Clearance Support System and Contract No. HY/2014/04 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V
Gantry Type X-ray Vehicle Inspection System within Contract No. HY/2014/05
works area) (hereafter referred to as ¡§the Contract¡¨) for the Highways
Department of Hong Kong Special Administrative Region (HKSAR). Contract No.
HY/2014/05 was awarded to Leighton ¡V Chun Wo Joint Venture (construction works
of Contract No. HY/2013/06 was awarded to ATAL Technologies Limited and
Contract No. HY/2014/04 was awarded to Rapiscan
Systems Pte Ltd within Contract No. HY/2014/05 works area) (hereafter referred
to as ¡§the Contractor¡¨) and Atkins China Limited was appointed as the
Environmental Team (ET) by the Contractor.
Contract No. HY/2014/05
(includes the construction works of Contract No. HY/2013/06 and Contract No.
HY/2014/04 within Contract No. HY/2014/05 works area) is part of HZMB HKBCF
Project which is a
¡§Designated Project¡¨ under Schedule 2 of the
Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental
Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was
prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K
for HKBCF was issued on 11 April 2016. These documents are available through the EIA
Ordinance Register. The
construction works of the Contract
No. HY/2014/05 commenced on 29 February 2016 while the construction works of the
Contract No. HY/2013/06 and Contract No. HY/2014/04 within Contract No.
HY/2014/05 works area commenced on 3 January 2017 and 13 February 2017
respectively.
Atkins China Limited has
been appointed by the Contractor to implement the Environmental Monitoring
& Audit (EM&A) programme for the Contract in accordance with the Updated EM&A
Manual for
HKBCF (Version1.0) and will be providing
environmental team services to the Contract.
This is the Sixth Quarterly EM&A Report for the Contract No. HY/2014/05 which summarizes findings of the
EM&A works during the reporting period from 1 June 2017 to 31 August 2017
(includes the construction works of Contract No. HY/2013/06 and Contract No.
HY/2014/04 within Contract No. HY/2014/05 works area).
Environmental
Monitoring and Audit Progress
The EM&A programme was
undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0).
It should be noted that the air quality and noise monitoring works for the Contract are covered by
Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao
Bridge HKBCF
¡V Reclamation Works and Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill
and HKBCF. The ET of the Contract
or another ET of the HZMB project is required to conduct impact air quality
monitoring at AMS6 and AMS7 and noise monitoring at NMS2 and NMS3B as part of
EM&A programme if these monitoring stations are no longer covered under
Contract Nos. HY/2010/02 and HY/2011/03. However, this is subject to ENPO¡¦s final decision
on which ET should carry out the monitoring work at these stations.
The
dates of environmental site inspection for the
Contract No. HY/2014/05 (includes the construction works of Contract No.
HY/2013/06 and Contract No. HY/2014/04 within Contract No. HY/2014/05 works
area) during
the reporting period are
listed below:
Environmental Site Inspection
Date |
||
June
2017 |
July
2017 |
August 2017 |
7, 14, 21 and 28 |
3, 13, 17 and 24 |
1, 7, 14, 25 and 28 |
Breaches of
Action and Limit Levels
Summary of Action and Limit
Level exceedance of 1-hr TSP level and 24-hr TSP level at station AMS6 shall be
referred to the monthly EM&A Reports (for June, July and August 2017)
prepared by Contract No. HY/2011/03.
There was no Action and
Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7
by the Environmental Team of Contract No. HY/2010/02 during the reporting
period.
There was no Action and
Limit Level exceedance for noise recorded at NMS2 and NMS3B by the
Environmental Team of Contract No. HY/2010/02 during the reporting period.
Implementation of Environmental
Measures
Site inspections were
carried out on a weekly basis to monitor the implementation of proper
environmental pollution control and mitigation measures for the Project. Potential
environmental impacts due to the construction activities were monitored and
reviewed.
Complaint Log
There was no complaint
received in relation to the environmental impact during the reporting period.
For the dust nuisance complaint
received by EPD on 31 May 2017 during the last reporting period and sent to the
ET on 1 June 2017, it was found that the nuisance of dust emissions from the
haul road traffic near Buildings 044 and 045 was not related to Contract No.
HY/2014/05 (including Contract No. HY/2013/06 HZMB HKBCF - Automatic Vehicle
Clearance Support System and Contract No. HY/2014/04 HZMB HKBCF ¡V Gantry Type
X-ray Vehicle Inspection System within Contract No. HY/2014/05 works area). No
follow up action by Contract No. HY/2014/05 was required.
Notifications
of Summons and Successful Prosecutions
There was no notification
of summon or prosecution received during this reporting period.
Reporting
Change
There was no reporting
change during the reporting period.
Table
1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
For Contract No.
HY/2014/05 |
||||
Engineer or
Engineer¡¦s Representative |
Chief
Registered Architect |
Malcolm Sage |
3958 7330 |
3468 2076 |
Environmental
Project Office / Independent Environmental Checker |
Environmental
Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent
Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Albert Chan |
3973 0514 |
3621 0180 |
Environmental
Officer |
Stephen Tsang |
3973 1806 |
3621 0180 |
|
Environmental Team |
Environmental
Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours
complaint hotline |
--- |
--- |
3958 7300 |
--- |
For Contract No.
HY/2013/06 within Contract No. HY/2014/05 works area |
||||
Engineer or
Engineer¡¦s Representative |
Chief
Registered Architect |
Malcolm Sage |
3958 7330 |
3468 2076 |
Environmental
Project Office / Independent Environmental Checker |
Environmental
Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent
Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Mr. Eric Yim |
2565 3355 |
3162 5217 |
Environmental
Officer |
Mr. W. Li |
2565 3137 |
3162 5217 |
|
Environmental
Team |
Environmental
Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours
complaint hotline |
--- |
--- |
6509 0375 |
--- |
For Contract No.
HY/2014/04 within Contract No. HY/2014/05 works area |
||||
Engineer or
Engineer¡¦s Representative |
Chief Registered
Architect |
Malcolm Sage |
3958 7330 |
3468 2076 |
Environmental
Project Office / Independent Environmental Checker |
Environmental
Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental
Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Ringo Yau |
9833 1402 |
2707 0816 |
Environmental
Officer |
Clarie Tsang |
6371 1362 |
--- |
|
Environmental
Team |
Environmental
Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours
complaint hotline |
--- |
--- |
9833 1420 |
--- |
For
Contract No. HY/2014/05
¡P
Raft
Foundation of Buildings 050A1 and 050A2
¡P
Construction
of RC Structure of Buildings 050H1, 050H2, 050A1 and 050A2
¡P
ABWF
works (Internal Finishes) of Buildings 021, 022, 023, 025, 032, 044, 045, 053,
058, 059, 050A1, 050A2, 050H1 and 050H2
¡P
ABWF
works (External Finishes) of Buildings 021, 022, 023, 025, 032, 044, 045,
050A1, 050H1, 050H2, 053, 058 and 059
¡P
ABWF
works (Roof Finishes) of Buildings 021, 022, 023, 025, 032, 044, 045, 050A1,
050A2, 050H1, 050H2, 053, 058 and 059
¡P
MEP
installation of Buildings 021, 022, 023, 025, 032, 044, 045, 053, 058 059, 050H1,
050H2 and 050A2
¡P
Utilities
and Drainage installation of Building 021, 022, 023, 025, 032, 044, 045, 053,
050A1, 050A2, 050H1, 050H2, 058 and 059
¡P
Installation
of Lift of Buildings 023, 044 and 053
¡P
Construction
of Planter Box and Ramp of Building 023
¡P
PV
Installation and Steel Canopy of Building 023
¡P
Dog
swimming pool of Building 022
For
Contract No. HY/2013/06 within Contract No. HY/2014/05 works area
¡P
Conceal
Conduit Installation and Wiring at Buildings 023, 025 and 032
For
Contract No. HY/2014/04 within Contract No. HY/2014/05 works area
¡P
Cabling
Works at Buildings 053 and 054
¡P
Furniture
delivery at Buildings 053 and 054
¡P
Installation
of Doors at Building 059
¡P
Cabling
Works at Buildings 058 and 059
¡P
Installation
of Extension Pieces and Door frames at Building 058
Table 2.1 Summary
of Impact EM&A Requirements
Environmental
Monitoring |
ID |
Location Description |
Air Quality |
AMS6(1) |
Dragonair/CNAC
(Group) Building |
AMS7(1) |
Hong
Kong SkyCity Marriott Hotel |
|
Noise |
NMS2(2) |
Seaview
Crescent |
NMS3B(2),(3) |
Site Boundary
of Site Office
Area at Works Area WA2 |
Remarks:
(1)
The ET of this
Contract should conduct impact air quality monitoring at the AMS listed in the
table as part of EM&A programme according to the latest notification from
ENPO when the monitoring station(s) is/are no longer covered by another ET of
the HZMB project.
(2)
The ET of
this Contract should conduct impact noise monitoring at the NMS listed in the
table as part of EM&A programme according to the latest notification from
ENPO when the monitoring station(s) is/are no longer covered by another ET of
the HZMB project.
(3)
The Action
and Limit Levels for schools will be applied for this alternative monitoring
location.
Table 2.2 Action
and Limit Levels for 1-hour TSP
Monitoring
Station |
Action
Level, µg/m3 |
Limit
Level, µg/m3 |
AMS6
¡V Dragonair/CNAC (Group) Building (HKIA) |
360 |
500 |
AMS7
¡V Hong Kong SkyCity Marriott Hotel |
370 |
Table 2.3 Action
and Limit Levels for 24-hour TSP
Monitoring
Station |
Action
Level, µg/m3 |
Limit
Level, µg/m3 |
AMS6
¡V Dragonair/CNAC (Group) Building (HKIA) |
173 |
260 |
AMS7
¡V Hong Kong SkyCity Marriott Hotel |
183 |
Table 2.4 Action
and Limit Level for Construction Noise
Parameter |
Action Level |
Limit Level |
07:00 ¡V 19:00 hours
on normal weekdays |
When one documented complaint is received |
75 dB(A)* |
Notes:
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by
the
Noise Control Authority have to be followed.
* Reduce to 70 dB(A) for schools and 65 dB(A) during school examination
period.
Table 4-1 A Summary of Environmental Complaints for the Previous Reporting Period
Environmental Complaint No. |
Date of Complaint Received |
Description of Environmental Complaints |
004 |
31
May 2017 |
Air
Quality |