CONCLUSION AND RECOMMENDATION
9.1.1                                
1-hour TSP and 24-hour TSP impact monitoring at AMS2, AMS3C and
AMS7B were carried out in the reporting month, no Action / Limit Level
exceedance was recorded during the period. 
9.1.2                                
Summary of Action and Limit Level exceedance of 1-hour TSP level
and 24-hour TSP level at AMS6 shall be referred to the monthly EM&A report
prepared by Contract No. HY/2011/03.
9.1.3                                
Construction noise monitoring were carried out in the reporting
month, no Action / Limit Level exceedance was recorded during the period. 
9.1.4                                
Based
on previous dolphin surveys conducted for the HZMB project, monthly variation
in dolphin occurrence within the survey areas was observed. Hence, it is more
suitable to assess whether post-construction activities of the HKBCF have
adverse impacts on dolphin occurrence every quarter where monthly comparison of
distribution, group size, and encounter rates will be conducted.
9.1.5                                
Four environmental site inspections were carried out in the
reporting month. Recommendations on mitigation measures for air quality impact
and chemical and waste management were given to the Contractor for remediating
the deficiencies identified during the site inspections. 
9.1.6                                
Referring to the Contractor¡¦s information, no environmental
complaint, notification of summons and successful prosecution was received in
the reporting month.
9.2.1                                
The recommended environmental mitigation measures, as proposed in
the EIA reports and EM&A Manuals shall be effectively implemented to
minimize the potential environmental impacts from the Project. The EM&A
programme would effectively monitor the environmental impacts generated from
the construction activities and ensure the proper implementation of mitigation
measures.
9.2.2                                
According to the environmental site inspections performed in the
reporting month, the following recommendations were provided:
 
Air Quality Impact
¡P         
Dust suppression measure should be provided
at the main haul road. 
¡P         
Water spray should be provided at all main exit to prevent sludge from
being taken outside the site area.
Construction Noise Impact
¡P         
No specific observation was
identified in the reporting month. 
Water Quality Impact
¡P         
No specific observation was
identified in the reporting month. 
Chemical and Waste Management
¡P         
All waste generated at the site
should be cleaned and collected. 
Landscape and Visual Impact
¡P         
No specific observation was
identified in the reporting month. 
Permit/ Licenses
¡P         
No specific observation was identified