1.
2.
3.
4.
5.
6.
9.1.1
1-hour
TSP and 24-hour TSP impact monitoring at AMS2, AMS3C and AMS7B were carried out
in the reporting month, no Action / Limit Level exceedance was recorded during
the period.
9.1.2
Summary
of Action and Limit Level exceedance of 1-hour TSP level and 24-hour TSP level
at AMS6 shall be referred to the monthly EM&A report prepared by Contract
No. HY/2011/03.
9.1.3
Construction
noise monitoring were carried out in the reporting month, no Action / Limit
Level exceedance was recorded during the period.
9.1.4
Based
on previous dolphin surveys conducted for the HZMB project, monthly variation
in dolphin occurrence within the survey areas was observed. Hence, it is more
suitable to assess whether post-construction activities of the HKBCF have
adverse impacts on dolphin occurrence every quarter where monthly comparison of
distribution, group size, and encounter rates will be conducted.
9.1.5
Five
environmental site inspections were carried out in the reporting month. Recommendations
on mitigation measures for air quality impact, water quality impact and chemical
and waste management were given to the Contractor for remediating the
deficiencies identified during the site inspections.
9.1.6
Referring
to the Contractor¡¦s information, no environmental complaint, notification of
summons and successful prosecution was received in the reporting month.
9.2.1
The
recommended environmental mitigation measures, as proposed in the EIA reports
and EM&A Manuals shall be effectively implemented to minimize the potential
environmental impacts from the Project. The EM&A programme would
effectively monitor the environmental impacts generated from the construction
activities and ensure the proper implementation of mitigation measures.
9.2.2
According
to the environmental site inspections performed in the reporting month, the
following recommendations were provided:
Air
Quality Impact
¡P
Dust
suppression measure should be provided.
Construction
Noise Impact
¡P
No
specific observation was identified in the reporting month.
Water
Quality Impact
¡P
Stagnant
water should be avoided.
Chemical
and Waste Management
¡P
Drip
tray should be provided for chemical container.
¡P
The
contractor was reminder to maintain housekeeping.
Landscape
and Visual Impact
¡P
No
specific observation was identified in the reporting month.
Permit/
Licenses
¡P
NRMM
label should be provided to replace the substandard label.