8.                    FUTURE KEY ISSUES

8.1                    Construction Programme for the Next Month

¡P            Security measure at existing gate at SPTI (land-based);

¡P            Recessed Cover at SPTI and NPTI (land-based);

¡P            UPS room near building 062 (land-based);

¡P            Minor Works at PCB (land-based);

¡P            Excavation at VCP and WA3 (land-based);

¡P            Road & Drain works at SPTI and NPTI (land-based);

¡P            Vertical access at PCB (land-based);

¡P            Covered Walkway at SPTI and NPTI (land-based);

¡P            Public Toilet at NPTI (land-based);

¡P            Kiosks Construction at VCP (land-based);

¡P            Landscape Works at G1 and G5 (land-based);

¡P            Conceal Conduits Works at VCP (land-based);

¡P            Resurfacing Works at BCF (land-based).

8.2                   Key Issues for the Coming Month

8.2.1                Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management and landscape and visual impact issues.

8.3                   Monitoring Schedules for the Next Month

8.3.1                The tentative schedule for environmental monitoring in the coming month is provided in Appendix E.