9.                    CONCLUSION AND RECOMMENDATION

9.1                                      Conclusions

9.1.1                                 1-hour TSP and 24-hour TSP impact monitoring at AMS2, AMS3C and AMS7C were carried out in the reporting month, no Action / Limit Level exceedance was recorded during the period.

9.1.2                                 Summary of Action and Limit Level exceedance of 1-hour TSP level and 24-hour TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

9.1.3                                 Construction noise monitoring were carried out in the reporting month, no Action / Limit Level exceedance was recorded during the period.

9.1.4                                 Four environmental site inspections were carried out in the reporting month. Recommendations on mitigation measures for air quality impact and chemical and waste management were given to the Contractor for remediating the deficiencies identified during the site inspections.

9.1.5                                 Two Bi-weekly Landscape and Visual Site audits were carried out by a Registered Landscape Architect in the reporting month.

9.1.6                                 Referring to the Contractor¡¦s information, no environmental complaint, notification of summons and successful prosecution was received in the reporting month.

9.2                                      Comment and Recommendations

9.2.1                                 The recommended environmental mitigation measures, as proposed in the EIA reports and EM&A Manuals shall be effectively implemented to minimize the potential environmental impacts from the Project. The EM&A programme would effectively monitor the environmental impacts generated from the construction activities and ensure the proper implementation of mitigation measures.

9.2.2                                 According to the environmental site inspections performed in the reporting month, the following recommendations were provided:

Air Quality Impact

¡P          Cement material should be stored and covered properly.

Construction Noise Impact

¡P          No specific observation was identified in the reporting month.

Water Quality Impact

¡P          No specific observation was identified in the reporting month.

Chemical and Waste Management

¡P          To avoid storing too much waste, waste generated at the site should be cleared and collected frequently.

¡P          Drip tray should be provided to prevent chemical leakage.

Landscape and Visual Impact

¡P          No specific observation was identified in the reporting month.

Permit/ Licenses

¡P          No specific observation was identified in the reporting month. [This is the bookmark for the end of the main section. Do not put content past this point]