2.                    AIR QUALITY

2.1                                      Monitoring Requirement

2.1.1                                 In accordance with the Contract Specific EM&A Manual, 1-hour and 24-hour Total Suspended Particulates (TSP) levels should be measured at the designated air quality monitoring stations to indicate the impacts of construction dust on air quality. Impact 1-hour TSP monitoring was conducted for at least three times every 6 days, while impact 24-hour TSP monitoring was carried out for at least once every 6 days.

2.2                                      Monitoring Equipment

2.2.1                                 24-hour TSP air quality monitoring was performed using High Volume Sampler (HVS) deployed at the designated monitoring stations. The HVS shall meet all the requirements of the EM&A Manual.

2.2.2                                 A portable direct reading dust meter was used to carry out the 1-hour TSP monitoring.

2.2.3                                 The model of the air quality monitoring equipment used is summarized in Table 2.1.

2.3                                      Monitoring Methodology for HVS

2.3.1                                 The following guidelines were adopted during the installation of HVS:

 

¡P              Sufficient support is provided to secure the samplers against gusty wind.

¡P              No two samplers are placed less than 2 meters apart.

¡P              The distance between the sampler and an obstacle, such as buildings, is at least twice the height that the obstacle protrudes above the sampler.

¡P              A minimum of 2 meters of separation from walls, parapets and penthouses is required for rooftop samples.

¡P              A minimum of 2 meters separation from any supporting structure, measured horizontally is required.

¡P              No furnaces or incineration flues are nearby.

¡P              Airflow around the samplers is unrestricted.

¡P              The samplers are more than 20 meters from the drip line.

¡P              Any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring.

¡P              Permission must be obtained to set up the samplers and to obtain access to the monitoring stations.

¡P              A secured supply of electricity is needed to operate the samplers.

 

2.3.2                                 Prior to the commencement of the dust sampling, the flow rate of the high volume sampler shall be properly set. The power supply should be checked to ensure the proper functioning of the sampler. The sampler is recommended to be operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air monitoring station.

2.3.3                                 The filter holding frame should be removed by loosening the four nuts and placing carefully a weighted and conditioned filter at the centre with the stamped number upwards on a supporting screen.

2.3.4                                 The filter should be aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter. The filter holding frame should be tightened to the filter holder with swing bolts. The applied pressure should be sufficient to avoid air leakage at the edges.

2.3.5                                 A programmed timer should be used to control the duration of operation. Information should be recorded on the record sheet, which included the starting time, the weather condition and the filter number.

2.3.6                                 After sampling process is finished, the filter should be removed and sent to the laboratory for weighting. The elapsed time should also be recorded.

2.3.7                                 All filters should be equilibrated in a conditioning environment for 24 hours before weighting. The conditioning environment temperature should be between 25¢XC and 30¢XC and not vary by more than ¡Ó3¢XC; the relative humidity (RH) should be <50% and not vary by more than ¡Ó5%. A convenient working RH is 40%.

2.4                                      Maintenance and Calibration for HVS

2.4.1                                 The high volume motors and their accessories should be properly maintained, including routine motor brushes replacement and electrical wiring checking, to ensure that the equipment and a continuous power supply were in good working condition.

2.4.2                                 Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at fortnightly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The calibration certificate for the HVS is provided in Appendix D.

2.5                                      Monitoring Methodology for Direct Reading Dust Meter

2.5.1                                 Portable Laser Particle Photometer Monitors should be operated in accordance with the Manufacturer¡¦s instruction Manual as below:

 

a) Pulling up the air sampling inlet cover

b) Changing the Mode 0 to BG

c) Pressing Start/Stop switch

d) Turning the knob to SENSI.ADJ and press it

e) Pressing Start/Stop switch again

f) Returning the knob to the position MEASURE slowly

g) Pressing the timer set switch to set measuring time

h) Removing the cap and start the measurement

 

2.6                                      Maintenance and Calibration for Direct Reading Dust Meter

2.6.1                                 ET shall submit sufficient information to the IEC to prove that the instrument is capable of achieving comparable results to the HVS. The instrument should also be calibrated regularly, and the 1-hour sampling shall be determined periodically by the HVS to check the validity and accuracy of the results measured by direct reading method. The calibration certificate for the direct reading dust meter is provided in Appendix D.

2.7                                      Monitoring Locations

2.7.1                                 In accordance with the Contract Specific EM&A Manual, four air quality monitoring locations, namely AMS2, AMS3C, AMS6 and AMS7B were set up at the proposed locations. AMS2, AMS3C and AMS7B are covered by Contract No. HY/2019/01 ¡§Hong Kong-Zhuhai- Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Phase 2 and Other Works¡¨

2.7.2                                 AMS6 is covered by Contract No. HY/2011/03 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road (HZMB HKLR) ¡V Section between Scenic Hill and HKBCF¡¨. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 as part of EM&A programme if this air quality monitoring station is no longer covered by Contract No. HY/2011/03.

2.7.3                                 Due to the existing air quality monitoring location AMS7B would be hand over back to Airport Authority for their construction works. A new alternative air quality monitoring location is still under processing.  Air quality monitoring location AMS7B was temporary suspended, effective from 10 December 2020.

2.7.4                                 According to the email date 11 August 2021, EPD have no comment on the Proposal for Relocation of Monitoring Location AMS 7B, the monitoring location AMS 7B are proposed to be relocated by alternative monitoring location AMS 7C for air quality monitoring. The monitoring location AMS 7C has resumed air quality monitoring on 5 October 2021.

2.7.5                                 The most updated locations of air quality monitoring are summarized in Table 2.2 and they are shown in Figure 2.

2.8                                      Monitoring Results

2.8.1                                 The schedule of air quality monitoring in reporting month is provided in Appendix E.

2.8.2                                 No Action / Limit Level exceedance was recorded for 1-hr and 24-hr TSP at AMS2, AMS3C and AMS7C.

2.8.3                                 The monitoring results for AMS6 are reported in the monthly EM&A Reports prepared for Contract No. HY/2011/03.

2.8.4                                 The weather conditions during the monitoring are provided in Appendix K.

2.8.5                                 The monitoring data of 1-hr TSP and 24-hr TSP are summarized in Table 2.3. Detailed monitoring data are presented in Appendix F.

2.8.6                                 The Event and Action Plan for air quality is given in Appendix H.

2.8.7                                 The wind data obtained from the on-site wind station during the reporting period is provided in Appendix G.