1.
2.
3.
4.
5.
6.
9.1.1
1-hour TSP and 24-hour TSP impact monitoring at AMS2, AMS3C and
AMS7C were carried out in the reporting month, no Action / Limit Level
exceedance was recorded during the period.
9.1.2
Summary of Action and Limit Level exceedance of 1-hour TSP level
and 24-hour TSP level at AMS6 shall be referred to the monthly EM&A report
prepared by Contract No. HY/2011/03.
9.1.3
Construction noise monitoring were carried out in the reporting
month, no Action / Limit Level exceedance was recorded during the period.
9.1.4
Five environmental site inspections were carried out in the
reporting month. No recommendations on mitigation measures was given to the Contractor for remediating the deficiencies
identified during the site inspections.
9.1.5
Referring to the Contractor¡¦s information, no environmental
complaint, notification of summons and successful prosecution was received in
the reporting month.
9.2.1
The recommended environmental mitigation measures, as proposed in
the EIA reports and EM&A Manuals shall be effectively implemented to
minimize the potential environmental impacts from the Project. The EM&A
programme would effectively monitor the environmental impacts generated from
the construction activities and ensure the proper implementation of mitigation
measures.
9.2.2
According to the environmental site inspections performed in the
reporting month, the following recommendations were provided:
Air Quality Impact
¡P
Cement material should be
covered.
Construction Noise Impact
¡P
No specific observation was
identified in the reporting month.
Water Quality Impact
¡P
Stagnant water should be
cleared to prevent overflow from drip tray.
Chemical and Waste Management
¡P
Waste generated at the site
should be cleared and collected.
Permit/ Licenses
¡P
No specific observation was identified
in the reporting month. [This is the bookmark for