SITE INSPECTION AND AUDIT
5.1.1
Site
audits were carried out by ET on weekly basis to monitor the implementation of
proper environmental management practices and mitigation measures in the
Project site.
5.1.2
In
the reporting month, five site inspections were carried out on 1, 9, 15, 20 and
29 June 2022.
5.1.3
No
outstanding issues were reported during the reporting month. Details of
observations recorded during the site inspections are summarized in Appendix G.
5.2.1
As
informed by AECOM, the commencement date of the 12-month establishment period
for the landscape monitoring under this contract is 5 January 2022. Bi-monthly
landscape and visual site audits will be conducted from 5 January 2022 to 4 January
2023.
5.2.2
A
bi-monthly landscape and visual site audit was carried out on 20 June 2022 by a
Registered Landscape Architect. The bi-monthly landscape and visual site audit
checklist was counter-signed by IEC and presented in Appendix J.
5.3.1
The
Contractor registered as a chemical waste producer for the Contract. Sufficient
numbers of receptacles were available for general refuse collection and
sorting.
5.3.2
The
monthly summary of waste flow table is detailed in Appendix D.
5.3.3
If
off-site disposal is required, the excavated marine mud from the land-based
works shall be disposed of at the designated disposal sites within Hong Kong as
allocated by the Marine Fill Committee or other locations as agreed by the
Director. The Contractor shall ensure no spilling and overflowing of materials
during loading / unloading / transportation is allowed.
5.3.4
The
Contractor was reminded that chemical waste containers should be properly
treated and stored temporarily in designated chemical waste storage area on
site in accordance with the Code of Practice on the Packing, Labelling and
Storage of Chemical Waste.