8.                   FUTURE KEY ISSUES

8.1                   Construction Programme for the Next Month

¡P            No main construction works will be carried out in the next reporting period.

8.2                   Key Issues for the Coming Month

8.2.1                                 Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management and landscape and visual impact issues.

8.3                   Monitoring Schedules for the Next Month

8.3.1                                 The tentative schedule for environmental monitoring in the coming month is provided in Appendix I.