5.
SITE INSPECTION AND AUDIT
5.1.1
Site
audits were carried out by ET on weekly basis to monitor the implementation of
proper environmental management practices and mitigation measures in the
Project site.
5.1.2
Details of observations recorded during the site inspections are
summarized in Appendix G.
5.1.3
According
to the EPD’s letter (EPD ref. () in AX(12) in EP771/E1/100), EPD has no comment on the Proposal
for Termination of EM&A Programme in Construction Phase, the site
inspection for Contract No: HY/2019/01 have been terminated on 5 July 2022. The
last inspection was completed on 29 June 2022.
5.2
Landscape and Visual Site Audit
(Establishment Period)
5.2.2
The next bi-monthly landscape and visual site audit was schedule
on 15 August 2022.
5.3
Advice on the Solid and Liquid
Waste Management Status
5.3.1
The Contractor registered as a chemical waste producer for the
Contract. Sufficient numbers of receptacles were available for general refuse
collection and sorting.
5.3.2
The monthly summary of waste flow table is detailed in Appendix D.
5.3.3
If off-site disposal is required, the excavated marine mud from
the land-based works shall be disposed of at the designated disposal sites
within Hong Kong as allocated by the Marine Fill Committee or other locations
as agreed by the Director. The Contractor shall ensure no spilling and
overflowing of materials during loading / unloading / transportation is
allowed.
5.3.4
The Contractor was reminded that chemical waste containers should
be properly treated and stored temporarily in designated chemical waste storage
area on site in accordance with the Code of Practice on the Packing, Labelling
and Storage of Chemical Waste.