7.
IMPLEMENTATION STATUS OF
ENVIRONMENTAL MITIGATION MEASURE
7.1.1
According
to the EPD’s letter (EPD ref. () in AX(12) in EP771/E1/100), EPD has no comment on the Proposal
for Termination of EM&A Programme in Construction Phase, the EM&A
programme for Contract No: HY/2019/01 have been terminated on 5 July 2022.
The
implementation status of the environmental mitigation measures
during
the reporting period is summarized in Appendix C.