1.1.1
Fugro Technical Services Limited was commissioned by China Harbour
Engineering Co. Limited (also referred to as ¡§the Contractor¡¨) to undertake the
Environmental Team (ET) services (including environmental monitoring and audit
(EM&A)) for Contract No. HY/2019/01 ¡§Hong Kong-Zhuhai-Macao Bridge Hong
Kong Boundary Crossing Facilities ¡V Phase 2 and Other Works¡¨.
1.1.2
Contract No. HY/2019/01 is part of the ¡§Hong Kong-Zhuhai-Macao
Bridge Hong Kong Boundary Crossing Facilities¡¨ (HZMB HKBCF) Project which is a
¡§Designated Project¡¨ under Schedule 2 of the Environmental Impact Assessment
(EIA) Ordinance (Cap. 499) and for which an EIA Report (Register No. AEIAR-145/2009)
was prepared and approved. The current Environmental Permit (EP) for HKBCF,
namely No. EP-353/2009/K, was issued on 11 April 2016. These documents are
available through the EIA Ordinance Register. The general layout of the Project
area is shown in Figure 1. Commencement
of the Contract took place on 4 December 2019 and the construction site
preparation works commenced in early February 2020.
1.1.3
This is the 31st Monthly EM&A report to document the findings
of site inspection activities and EM&A programme carried out by the
Contractor of Contract No. HY/2019/01 from 1 August 2022 to 31 August 2022
(reporting period) and is submitted to fulfil Condition 5.4 of the EP.
1.2.1
The works to be executed under Contract No. HY/2019/01 include the
following major items:
¡P
Landscaping
and establishment works;
¡P
Irrigation
system and associated drainage pumping system and facilities;
¡P
Erection
and installation in the Passenger Clearance Building;
¡P
Public
transport interchange (PTI) public toilet, satellite refuse collection point
(RCP) and observation guard booths;
¡P
PTI
cross boundary shuttle (CBS) / cross boundary coach (CBC) lanes and covered walkway;
¡P
Vehicle
clearance plazas (VCP) vehicle kiosks and associate automatic vehicle clearance
supporting system (AVCSS).
1.3.1
The Project Organization structure is shown in Appendix B. The key
personnel contact names and numbers are summarized in Table 1.1.
1.4
Construction Programme and Activities
1.4.1
The site layout plan of the Contract is shown in Figure 1.
1.4.2
The construction programme of this Contract is shown in Appendix
A.
1.5
Works
undertaken during the month
1.5.1
No main construction works was carried out in the reporting
period.
1.6.1
A summary of the relevant permits, licenses and/or notifications
on environmental protection for this Contract is presented in Table 1.2.