2.                    EM&A REQUIREMENTS

2.1                    Summary of EM&A Requirement

2.1.1                The Quarterly EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0). It should be noted that the air quality, noise and the post-construction dolphin monitoring works for the Contract are covered by Contract No. HY/2019/01 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Phase 2 and Other Works¡¨.

2.1.2                According to the Contract Specific EM&A Manual, air quality monitoring at station AMS2, AMS3C and AMS7B, and noise monitoring at station NMS2 and NMS3C are covered by Contract No. HY/2019/01. It should be noted that the air quality monitoring at station AMS6 is covered by Contract No. HY/2011/03. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 as part of EM&A programme if the impact air quality monitoring work is no longer covered by Contract No. HY/2011/03 respectively. However, this is subject to ENPO¡¦s final decision on which ET should carry out the monitoring work at these stations.

2.1.3                The most updated air and noise locations are summarized in Table 2.1. The locations of the air quality and noise monitoring stations shown in Figure 2 and Figure 3, respectively.

2.1.4                The remaining post-construction dolphin monitoring works under Contract No. HY/2013/04 ¡§HZMB HKBCF ¡V Infrastructure Works Stage II (Southern Portion)¡¨ were suspended from 1 March 2020. The ET of Contract No. HY/2019/01 is required and continues the full implementation of environmental monitoring commencing on 1 March 2020.

2.1.5                Currently, the role of dolphin monitoring and data collection are still under Contract No. HY/2012/08 ¡§Tuen Mun-Chek Lap Kok Link ¡V Northern Connection Sub-sea Tunnel Section¡¨. To avoid redundancy in the monitoring effort, the findings of Contract No. HY/2012/08 were used for this reporting month. The dolphin monitoring programme have adopted the standard line-transect method (Buckland et al. 2001) to survey the pre-set and fixed transect lines defined by AFCD in the Northeast Lantau (NEL) and Northwest Lantau (NWL) survey areas.

2.2                   Monitoring Requirement

2.2.1                The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A report prepared for this Contract.

2.2.2                The air quality monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information for AMS6 are detailed in the monthly EM&A report prepared for Contract No. HY/2011/03.

2.3                   Action and Limit Levels

2.3.1                The Action and Limit Levels for noise impact monitoring have been set and are presented in Appendix C.

2.4                   Event and Action Plans

2.4.1                The event and action plans for air quality and noise monitoring are presented in Appendix D.

2.5                   Mitigation Measures

2.5.1                The Contractor had implemented environmental mitigation measures and requirements as stated in the EIA Reports, the EP and EM&A Manuals. The implementation status of the environmental mitigation measures during the reporting period is summarized in Appendix E.