Table 8.1 Waste
Management Checklist
Activities |
Timing |
Monitoring Frequency |
If non-compliance, Action Required |
All necessary waste disposal
permits or licences have been obtained. |
Before the commencement of demolition works |
Once |
Apply for the necessary permits/ licences prior to disposal of
the waste. The ET shall ensure that corrective action has been taken. |
Only licensed waste haulier are used for waste collection. |
Throughout the works |
Weekly |
The ET shall inform the ER and IEC of the non-compliance. The ER
shall instruct the Contractor to use a licensed waste haulier. The Contractor
shall temporarily suspend waste collection of that particular waste until a
licensed waste haulier is used. Corrective action shall be undertaken within 48 hours. |
Records of quantities of wastes
generated, recycled and disposed are properly kept. For demolition
material/waste, the number of loads for each day shall be recorded (quantity
of waste can then be estimated based on average truck load. Should landfill
charging be implemented, the receipts of the charge could be used for
estimating the
quantity). |
Throughout the works |
Weekly |
The Contractor shall estimate
the missing data based on previous records and the activities carried out.
The ET shall audit the results and forward to the ER and IEC for approval. |
Wastes
are removed from site in a timely manner. General refuse is collected on a daily basis. |
Throughout the works |
Weekly |
The
ET shall inform the ER and IEC of the non-compliance.
The ER shall instruct the Contractor to remove waste accordingly. |
Waste storage areas are properly cleaned and do not cause
windblown litter and dust nuisance. |
Throughout the works |
Weekly |
The ET
shall inform the ER and IEC of the non-compliance. The ER shall instruct the Contractor
to clean the storage area and/or cover the waste. |
Different types of waste are segregated in different containers
or skip to enhance recycling of material and proper disposal of waste. |
Throughout
the works |
Weekly |
The ET shall inform the ER and IEC of the non-compliance. The ER
shall instruct the Contractor to provide separate skips/ containers. The
Contractor shall ensure the workers place the waste in the appropriate
containers. |
Chemical wastes are stored, handled and disposed of in
accordance with the Code of Practice on the Packaging, Handling and Storage
of Chemical Wastes, published by the EPD. |
Throughout the works |
Weekly |
The ET shall inform the ER and IEC of the non-compliance. The ER
shall instruct the Contractor to rectify the problems immediately. Warning
shall be given to the Contractor if corrective actions are not taken within
24 hrs and the Waste Control Group of
the EPD shall be identified. |
Demolition material/waste in dump trucks are properly covered
before leaving the site. |
Throughout the works |
Weekly |
The
ET shall inform the ER and IEC of the non-compliance. The ER shall instruct
the Contractor to comply. The Contractor shall prevent trucks shall leaving
the site until the waste are properly covered. |
Wastes are disposal of at
licensed sites. |
Throughout the works |
Weekly |
The ET shall inform the ER and IEC of the non-compliance. The ER
shall warn the Contractor and instruct the Contractor to ensure the wastes
are disposed of at the licensed sites. Should it involve chemical waste, the
Waste Control Group of EPD shall be notified. |
Note:
ET – Environmental Team, IEC – Independent Environmental Checker,
ER – Project Manager, Supervisor or their representative’s.