5              Dolphin-related Monitoring

Monitoring Requirements

 

5.1         According to Section 10 of the EM&A Manual, four kinds of ecological monitoring works are required during the construction phase, namely dolphin monitoring, construction-phase underwater noise monitoring, dolphin behavior monitoring and land-based dolphin behavior and movement monitoring.  The 30 days of construction-phase underwater noise monitoring, dolphin behavior monitoring and land-based dolphin behavior and movement monitoring were completed in July 2013.

 

5.2         The monitoring work shall be undertaken by suitably qualified specialist(s), (i.e. dolphin specialist and bio-acoustician), who shall have sufficient (at least 5-10 years) relevant post-graduate experience and publication in the respective aspects. They should be approved by Agriculture, Fisheries and Conservation Department (AFCD) and Environmental Protection Department (EPD).

 

Dolphin Monitoring (Line-transect Vessel Survey)

Monitoring Requirements

5.3         According to EM&A Manual Section 10.3.2, a dolphin monitoring programme should be set up to verify the predictions of impacts and to ensure that there are no unforeseen impacts on the dolphin population during construction phase.

 

5.4         Following the requirement in the EM&A Manual Section 10.4.1, the dolphin monitoring should adopt line-transect vessel survey method, and cover the following line-transect survey areas as in AFCD annual marine mammal monitoring programme.

Monitoring Location

5.5         For this contract, dolphin monitoring will be carried out in the West Lantau (WL) along the line transect. The co-ordinates of all transect lines are shown in Table 5.1 and the transect line layout in West Lantau Survey Areas are shown in Figure 7.

 

Table 5.1       Co-ordinates of transect lines in WL survey area

Line No.

Easting

Northing

Line No.

Easting

Northing

1

Start Point

803750

818500

7

Start Point

800200

810450

1

End Point

803750

815500

7

End Point

801400

810450

2

Start Point

803750

815500

8

Start Point

801300

809450

2

End Point

802940

815500

8

End Point

799750

809450

3

Start Point

802550

814500

9

Start Point

799400

808450

3

End Point

803700

814500

9

End Point

801430

808450

4

Start Point

803120

813600

10

Start Point

801500

807450

4

End Point

801640

813600

10

End Point

799600

807450

5

Start Point

801100

812450

11

Start Point

800300

806500

5

End Point

802900

812450

11

End Point

801750

806500

6

Start Point

802400

811500

12

Start Point

801760

805450

6

End Point

800660

811500

12

End Point

800700

805450

Monitoring Frequency

5.6         Dolphin transect survey was carried out at least twice a month (i.e. complete all the transect lines of West Lantau survey area twice per month) throughout the construction period.

Monitoring Results and Observations

5.7         Detailed monitoring methodology and results can be found in the monthly EM&A report.

 

5.8         A total of 3 Action Level exceedance and 1 Limit Level exceedance were recorded during the construction phrase of the Contract. The summary of exceedance is attached in Appendix G.

 

5.9         According to the ET¡¦s investigation, no direct evidence demonstrated the exceedances of Action/Limit level for dolphin were caused by the Contract during the construction period. No adverse impact on Chinese white dolphins was noticeable from general observations

 

Construction-phase Underwater Noise Monitoring

Monitoring Requirements

5.10     According to EM&A Manual Section 10.3.3 and 10.4.2, construction-phase underwater noise monitoring has to be carried out to verify the assessment outcome in the EIA and to collect field data of this construction activity. The actual underwater noise level of bored piling was monitored during the pile construction in the waters to the west of the Airport for HKLR.

 

5.11     Following the requirement in the EM&A Manual Section 10.6.2, construction-phase underwater noise monitoring was constructed for 10 days from the start of the bored piling activities for the first three pier sites during the bored piling process in the first three sits in the waters to the west of Airport.

Monitoring Location

5.12     The equipment was positioned at an appropriate and safe distance from a barge (about 100m away from the center of the pier) where the piling work was carried out at the pier site to monitor the underwater noise during the bored piling activities. After anchoring, the boat would drift within the radius of the anchor (about 5m), which was unavoidable.

 

5.13     The approximate locations of the monitoring stations are depicted in Figure 5. The co-ordinates of the monitoring station are shown in Table 5.2.

 

Table 5.2       Co-ordinates of underwater noise monitoring stations

Pier No.

Station

Easting

Northing

48

R1

806141

815885

52

R2

806390

816056

 

5.14     Due to programme change, the first two piers were changed to P48 and P52 instead of P20, P47 or P49 proposed in the methodology statement. While the location of impact monitoring has changed, the position of the station remained around 100m away from the piers as proposed. The change in monitoring location would not affect comparison against Action and Limit level.

Monitoring Equipment

5.15     PAM004, a proprietary product of Sea Mammal Research Unit (SMRU), was adopted for impact underwater noise monitoring. It is the same equipment used in baseline monitoring. While this is different from the system proposed in the method statement, the difference in sensitivity and pre-amplifier gain will not affect the monitoring results. Therefore, this still allows compatible comparison of the measurement.

Monitoring Methodology

5.16     The data recorded by PAM004 were transmitted to a receiving station on a boat via cable. The data were viewed on a laptop computer in real time by an operator from Cinotech who has been well trained and technically supported by SMRU for the operation.

 

5.17     The RMS sound pressure level re 1µPa were checked against the Action Level and Limit Level (170 and 180 dB re 1µPa respectively).

Monitoring Results

5.18     Detailed monitoring methodology and results can be found in the monthly EM&A report. No Action/Limit Level exceedance was recorded. The graphical presentation of underwater noise monitoring is shown in Appendix B.

 

 

Dolphin Behaviour Monitoring (Acoustic)

Monitoring Requirements

5.19     According to EM&A Manual Section 10.3.4, acoustic behavior and movement of Chinese White Dolphin near the bored piling sites should be monitored during bridge construction.

Monitoring Location

5.20     The dedicated acoustic surveys with calibrated hydrophone deployment were conducted in the western side of Lantau Island during the construction phase. The research vessel followed a predefined route for systematic search effort in West Lantau waters to cover the HKLR alignment in Northwest and West Lantau waters (in particular the area near the first three bored piling sites), where dolphins will be potentially disturbed by the bored piling works.

 

5.21     The EARs were deployed at two locations: 1) near the bridge alignment (N22¢X17.222, E113¢X53.016), about 500 m from the first three bored piling sites (Site B2), and 2) at a less disturbed site away from the bridge alignment as control site, off Fan Lau (N22¢X11.827, 113¢X50.648; Site B1).  EAR B2 was in water depth 4 m, and EAR B1 in 7 m.

Monitoring Results

5.22     Detailed monitoring methodology and results can be found in the monthly EM&A report.

 

Land-based Dolphin Behaviour and Movement Monitoring

Monitoring Requirements

5.23     According to EM&A Manual Section 10.3.5, land-based theodolite tracking has to be carry out to study dolphin behaviour near bored piling work site, and examine their north-south movement across the bridge alignment during after bridge construction.

 

5.24     Following the requirement in the EM&A Manual Section 10.4.3 and 10.6.3, the monitoring should be conducted at the three pier sites for 30 days from the start of bored piling activities in the waters to the west of Airport.

Monitoring Location

5.25     A theodolite tracking station was set up in Sham Wat located along the northwest coast of Lantau Island (22o16.10¡¦ N. and 113o52.32¡¦ E) as depicted in Figure 6.

Monitoring Frequency

5.26     Thirty days of monitoring would be carried out during the construction phase.

Monitoring Results

5.27     Detailed monitoring methodology and results can be found in the monthly EM&A report.

 

Additional Land-based Dolphin Behaviour and Movement Monitoring

5.28     A total of 64 days of additional monitoring according to the Proposal for Land-based Dolphin Behaviour and Movement Monitoring had been completed in August 2016.

 

 

Land-based Dolphin Behaviour and Movement Monitoring after bridge construction

5.29     According to Section 10 of approved EIA Report, EM&A Manual and Section 2 of approved Proposal for Land-based Dolphin Behavior and Movement Monitoring submitted on 24 January 2013 and approved by the authority on 5 February 2013, land-based theodolite tracking to study dolphin behaviour near bored piling work site, and examine their north-south movement across the bridge alignment shall be conducted before, during and after bridge construction. Summary of the requirements of land-based dolphin monitoring is shown in Table 5.3:

 

Table 5.3 Summary of Land-based of Dolphin Behaviour and Movement Monitoring Requirements

EIA

EM&A Manual

Approved Monitoring Proposal

Requirement for Land-based of dolphin behaviour and movement monitoring

Ÿ  Land-based theodolite tracking to study dolphin behaviour near bored piling work site, and examine their north-south movement across the bridge alignment before, during and after bridge construction.

Ÿ  Land-based theodolite tracking to study dolphin behaviour near bored piling work site, and examine their north-south movement across the bridge alignment before, during and after bridge construction.

Ÿ  The behaviour near the bored piling sites and north-south movement across the bridge alignment of CWD should be monitored in the waters to the west of Airport.

Ÿ  Dolphin behaviour in response to bored piling works and movement near the bored piling sites should be monitored at the first three pier sites for 30 days from the start of bored piling activities in the waters to the west of Airport. However, the number of monitoring days is not well specified for the baseline period.

Ÿ  Therefore, reference to the requirements in the Tuen Mun ¡V Chek Lap Kok Link (TMCLKL) EM&A Manual was made, in which 30 days of theodolite tracking before(i) and 30 days of theodolite tracking from the start of bored piling activities(ii) will be conducted under the present study in order to maintain overall consistency of EM&A Programs for the Hong Kong-Zhuhai-Macao Bridge (HZMB) development.

Frequency

Baseline

Ÿ  Not specified

Ÿ  Baseline for dolphin north-south movement across the bridge alignment shall be established prior to the commencement of works and agreed with AFCD.

Ÿ  30 consecutive days (with 5-6 hours on each survey day).    

Ÿ  It should be noted that every attempt will be made to conduct the monitoring in favorable weather conditions (Beaufort Sea State 3 or below; good visibility of 2km or above).

Impact

Ÿ  Not specified

Ÿ  Dolphin behavior in response to bored piling and movement near the bored piling sites will be monitored at the three pier sites for 30 days from the start of bored piling activities in the waters to the west of Airport.

Ÿ  30 consecutive days (with 5-6 hours on each survey day).            

Ÿ  It should be noted that every attempt will be made to conduct the monitoring in favorable weather conditions (Beaufort Sea State 3 or below; good visibility of 2km or above).

Ÿ  In the proposal, the dolphin specialist has also proposed an additional 64 days of monitoring (twice per month, with 5-6 hours on each survey day) throughout the construction period to examine the impact of bridge construction on north-south movement of CWD across the bridge alignment.

Post-construction

Ÿ  Not specified

Ÿ  Not specified

Not specified

Construction Program and Monitoring Period

Construction Program

5.30     The major construction programme of the Contract is provided in Table 5.4.

 

Table 5.4       Major Construction Program for Contract No. HY/ 2011/09

Description

Period

Commencement of the Contract

May 2012

Construction Commencement

February 2013

Piling

April 2013 ¡V September 2015

Pile Cap and Piers

December 2013 ¡V May 2016

Deck Segment Erection

March 2015 ¡V June 2017

 

5.31     Based on the construction programme in Section 5.30, Land-based theodolite monitoring after bridge construction has been conducted twice per month from September 2016 to August 2018. A total of 48 days of monitoring was carried out after the impact monitoring completion. Summary of Land-based dolphin behavior and movement monitoring across the bridge alignment before, during and after bridge construction are presented in Table 5.5.

 

Table 5.5 Summary of Land-based dolphin behavior and movement monitoring across the bridge alignment before, during and after bridge construction

 

Land-based dolphin behavior and movement monitoring

Monitoring Period

Monitoring Details

Baseline (before bridge construction)

Dec 2012 ¡V Jan 2013

i)          30 consecutive days before bridge construction (i.e. before start of bored piling activities)

Impact (during bridge construction)

Mar 2013 ¡V Aug 2016

i)          30 days from the start of bored piling activities in the waters to the west of Airport; and

ii)        64 days (twice per month) throughout the bridge construction period (Remark: the pile cap and pier construction under Contract HY/2011/09 were completed in May 2016)

Post-construction (after bridge construction)

Sept 2016 ¡V August 2018

i)          48 days (twice per month) after completion of bored piling activities 

 

 

 

5.32     The Land-based Dolphin Behavior and Movement Monitoring for ¡§baseline¡¨, ¡§impact¡¨ and ¡§after bridge construction¡¨ have been conducted by the same dolphin specialist using consistent monitoring methodology and result analysis. 

 

5.33     Details of Land-based dolphin behavior and movement monitoring after bridge construction are presented in the separate Final Report of Land-based Monitoring on North-South Movement of Chinese White Dolphins in West Lantau Waters After Bridge Construction.

 

5.34     All Land-based Dolphin Behaviour and Movement Monitoring have been completed under Contract No. HY/2011/09 and had fulfilled the requirements stated in the EM&A Manual.

 



(i) Baseline Monitoring Frequency for Theodolite Tracking

(ii) Impact Monitoring Frequency for Theodolite Tracking