9.1
Major site activities for the coming reporting month will include:
Continue
erection of hoarding & fence and site office area set up in Portion C;
Carry
out slewing work for CLP 11kVA and 132kVA power cable between P108, P109 &
P113;
Construction
of the concrete cable trough for CLP cable slewing;
Slewing
of the tele-communication cable;
Continue
pre-drilling work at western water, along slopping seawall and at Portion C;
Protection
work to the fuel pipes along the access road at Portion C;
Complete
the piling platform for the Kelly method at P48, P0 and P49 and commence bored
piling work;
Erection
of platform at P50 an P52 for preparation of RCD bored piling;
Continue
the setup of casting yard;
Set-up
facilities for marine delivery of concrete from land plants.
Setting up of silt-curtain. (dolphin exclusion
zone and dolphin watching plan will be implemented in accordance with EP
condition 3.4 and 3.5)
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.