9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

9.1         Major site activities for the coming reporting month will include:

Ÿ   Continue erection of hoarding & fence and site office area set up in Portion C;

Ÿ   Carry out slewing work for CLP 11kVA and 132kVA power cable between P108, P109 & P113;

Ÿ   Construction of the concrete cable trough for CLP cable slewing;

Ÿ   Slewing of the tele-communication cable;

Ÿ   Continue pre-drilling work at western water, along slopping seawall and at Portion C;

Ÿ   Protection work to the fuel pipes along the access road at Portion C;

Ÿ   Complete the piling platform for the Kelly method at P48, P0 and P49 and commence bored piling work;

Ÿ   Erection of platform at P50 an P52 for preparation of RCD bored piling;

Ÿ   Continue the setup of casting yard;

Ÿ   Set-up facilities for marine delivery of concrete from land plants.

Ÿ   Setting up of silt-curtain. (dolphin exclusion zone and dolphin watching plan will be implemented in accordance with EP condition 3.4 and 3.5)

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

9.3         A tentative construction programme is provided in Appendix A.