2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issue on 9 November 2011 for HKLR to the Highways Department as the Permit Holder.

2.5         Figure 1a-c  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

 

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

 

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

(a)   Predrilling works are in progress with marine jack-up rigs, land rigs on micro platforms and timber scaffoldings along sloping seawall at P14, P15, P53, P72, P94 & P104;

(b)   Trial pit excavation to locate the fuel pipes is completed with protection works in progress;

(c)   Slewing of existing 132KV CLP cable into newly built cable trough near the area of P113 and P108 was completed. Backfilling works to P113 area was commenced and to be completed before mid April 2013. Outstanding set of 11KV cable at P108 is to be completed before 3 April 2013;

(d)  Tele-communication cable man-holes for slewing were inspected. Meeting was conducted with relevant parties. It has been confirmed that slewing is feasible with method statement submitted to SO and parties. Workshop will be arranged for further discussion;

(e)   Erection of hoarding & fence and site office area set up in Portion C in are progress with decoration to follow;

(f)   Fabrication of 2 nos. piling platforms at WA4 was completed and the remaining platforms in progress at yard in the mainland;

(g)   Installation of temporary casings for the piling platform was completed at P0 and P49 and in progress at P20;

(h)   Installation of piling jackets at P52 and prefabrication of 2 nos. piling jackets for P50 were completed;

(i)    Piling platform was completed at P48 and the permanent pile casings have been installed;

(j)    Installation of 8 nos. permanent casing at P52 is in progress;

(k)   Rebar cages prefabrication at WA4 and WA7 for piles is in progress;

(l)    Earth Auger (Model: BG40) has been loaded onto Ro-Ro barge ready for transfer to P48 on 27 March 2013;

(m)  Progress of the precast concrete segment casting yard in Zhongshan are as follows:

-                                                           Backfilling works were completed

-                                                           Access roads work are in progress

-                                                           11 piling rigs are working on site (approx. 2800 piles completed)

-                                                           Batch plant installation was completed and trial mixing initial has commenced

-                                                           Gantry rail beams are also in progress (with 4400m completed)

-                                                           Permanent power was energised and water were connected

-                                                           75% of dredging works for the loading jetty were completed

(n) Set up of the floating concrete batching plants was completed and awaiting the confirmation of the VEP and operating license from Marine Department;

(o)   Sub-contractor for piling of land section has been finalized. The company profile of the subcontractor, Bachy, has been submitted to SO for approval.  Setting up works would be commenced as soon as the permit of site establishment is issued by AA;

(p)   Delivery of launching girder and lifting gantry from abroad with containers was commenced on 22 February 2013 for further assembling on site;

(q)   EBS monitoring with witness from SOR’s staff started on 24 January 2013 and report submitted to SO on bi-weekly basis;

(r)   Diversion to existing 1350 drainage pipe and the 600mm water main for facilitating the construction of piling works to pier 106 to 108 pending for permit of tree felling.


Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

 

Table 2.2        Status of Environmental Licences, Notification and Permits

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/A

09/11/2011

N/A

Valid

Consruction Noise Permit (CNP)

WA6B: GW-RS0968-12

24/09/2012 (19:00)

23/03/2013 (23:00)

Expired

WA6B: GW-RS1094-12

29/10/2012(19:00)

28/04/2013(24:00)

Valid

WA3B: GW-RW1146-12

13/11/2012(19:00)

14/05/2013(24:00)

Valid

WA4C: GW-RW0959-12

24/12/2012(19:00)

23/06/2013(23:00)

Valid

WA4B: GW-RW0960-12

24/12/2012(19:00)

23/06/2013(23:00)

Valid

WA4B:GW-RW0047-13

28/01/2013(23:00)

27/07/2013(07:00)

Valid

P48-P52: GW-RS0171-13

24/02/2013(07:00)

23/08/2013(23:00)

Valid

P50-P52:GW-RS0180-13

24/02/2013(23:00)

23/08/2013(07:00)

Valid

WA7: GW-RW0125-13

28/02/2013(19:00)

27/08/2013(23:00)

Valid

Portion C: GW-RS0305-13

29/03/2013(07:00)

30/06/2013(19:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

13/06/2012

N/A

Valid

A/C# 7015341

(Western water and Airport Channel)

20/02/2013

31/05/2013

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A: WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B: WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid