9.1
Major
site activities for the coming reporting month will include:
WA4
Preparation
for bored piling
Fabrication
of temporary piling platforms and rebar cages
Loading and
unloading
Setup of
casting yard
WA7
Preparation
for bored piling
Fabrication
of temporary piling platforms and rebar cages
Loading and
Unloading
Portion A
Site
clearance and formation
Timber
Scaffolding
Ground
Investigation
Set-up
facilities for marine delivery of concrete from land plants
Portion C
Trial Pit
excavation for U/U
Ground
Investigation
Erection of
hoarding & fencing
Site office
area set up
Pre-drilling
work at western water, along slopping seawall
Protection
work to the fuel pipes along the access road
Slewing
work for CLP 11kVA and 132kVA power cable
Western
Water
Ground
Investigation for design
Pre-drilling
Work
Loading and
Unloading
Preparation
work for bored piling
Setting up
of silt-curtain
Bored
piling excavation and concreting works
9.2
The
tentative environmental monitoring schedule for the next month is shown in Appendix D.
9.3
A
tentative construction programme is provided in Appendix A.