Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

2nd, 8th, 12th, 18th, 24th and 30th April 2013

24-hr TSP Monitoring

2nd, 8th, 12th, 18th, 24th and 30th April 2013

Noise Monitoring

3rd, 9th, 15th and 25th April 2013

Water Quality Monitoring

1st, 3rd, 5th, 8th, 10th, 12th, 15th, 17th, 19th, 22th, 24th, 26th and 29th April 2013

Dolphin Monitoring (Line-transect Vessel Surveys)

9th and 17th April 2013

(1)Construction-phase underwater Noise Monitoring

With Bored Piling Activities:

2nd, 3rd, 5th, 8th, 9th, 10th, 25th, 26th, 27th, 29th and 30th  April 2013

Without Bored Piling Activities:

11th April 2013

(1)Dolphin Behaviour Monitoring

With Bored Piling Activities:

1st, 2nd, 3rd, 5th, 7th, 8th, 10th and 11th April 2013

(1)Land-based Dolphin Behaviour and Movement Monitoring

With Bored Piling Activities:

1st, 2nd, 4th, 5th, 7th, 8th, 9th, 10th and 11th April 2013

Environmental Site Inspection

2nd, 9th, 16th, 26th and 30th April 2013

Archaeological Site Inspection

(2)N/A

Remark: (1)Dolphin-related monitoring was conducted in the reporting month. According to the EM&A Manual for HKLR, the dolphin-related monitoring was conducted during the bored piling activities (e.g. installation of permanent casting for bored piling activities) which presented in Appendix A.  The dolphin-related monitoring conducted without bored piling activities are for reference only.

        (2) No archaeological site inspection was conducted in the reporting month.